2722 S REYNIER AVE 90034

Certificate Information: 2722 S REYNIER AVE 90034

Application / Permit
22014-10000-04674
Plan Check / Job No.
B22LA18921
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED 324 SF GARAGE TO ADU WITH 112 SF ADDITION PER STATE LAW
Permit Issued
Issued on 10/14/2022
Issuing Office
Metro
Current Status
CofO Issued on 9/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/20/2022 APPLICANT
Assigned to Plan Check Engineer 9/22/2022 JOSEPH RAFOLS
Corrections Issued 9/24/2022 JOSEPH RAFOLS
Building Plans Picked Up 9/27/2022 APPLICANT
Plan Check Approved 10/14/2022 MINA HABILI
Issued 10/14/2022 APPLICANT
CofO in Progress 9/13/2023 MEL KHACHATOURIAN
Permit Finaled 9/21/2023 DANIEL ORRANTE
CofO Issued 9/21/2023 DANIEL ORRANTE
Permit Finaled 9/21/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 10/3/2022 JEANIE LAM
Roof/Waste drainage to street Cleared 10/3/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 10/4/2022 JEANIE LAM
Sewer availability Cleared 10/5/2022 JEANIE LAM

Contact Information

Contractor Mateos Construction & Remodeling Co; Lic. No.: 1034279-B 6816 POLLARD ST      LOS ANGELES, CA 90042
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/7/2022 Partial Approval EVAN COOPER
Sewer 11/7/2022 Approved EVAN COOPER
Excavation/Setback/Form/Re-Bar 11/28/2022 Corrections Issued EVAN COOPER
Footing/Foundation/Slab 11/28/2022 Not Ready for Inspection EVAN COOPER
Footing/Foundation/Slab 12/5/2022 Corrections Issued OGANES TARAKHCHYAN
Footing/Foundation/Slab 12/7/2022 Corrections Issued JOHNNY MIRANDA
Excavation/Setback/Form/Re-Bar 12/12/2022 Corrections Issued JEREMY TODD
Excavation/Setback/Form/Re-Bar 12/22/2022 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 12/22/2022 Partial Inspection JEREMY TODD
Piling/Pier/Caisson 12/22/2022 Partial Inspection JEREMY TODD
Footing/Foundation/Slab 12/28/2022 Approved JEREMY TODD
ELECTRICAL-Rough 2/16/2023 Not Ready for Inspection CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 2/16/2023 Corrections Issued CLAYTON GRAHAM
ELECTRICAL-Rough 2/22/2023 Approved JEREMY TODD
PLUMBING-Rough 2/22/2023 Approved JEREMY TODD
Wood Frame 2/22/2023 Approved JEREMY TODD
BUILDING-Rough-Frame 2/24/2023 Approved JEREMY TODD
Floor/Roof Diaphrgm/Shear Wall 2/24/2023 Approved JEREMY TODD
Green Building Rough 2/24/2023 Approved JEREMY TODD
HVAC-Rough 2/24/2023 Approved JEREMY TODD
MERV13>=Rough 2/24/2023 Approved JEREMY TODD
Floor/Roof Diaphrgm/Shear Wall 3/2/2023 Approved JEREMY TODD
Interior/Exterior Lathing 3/2/2023 Approved JEREMY TODD
Insulation 3/6/2023 Corrections Issued JESUS PINEDA
Drywall Nailing 3/8/2023 Not Ready for Inspection JEREMY TODD
Insulation 3/8/2023 Approved JEREMY TODD
Drywall Nailing 3/10/2023 Approved JEREMY TODD
Shower Pan 3/10/2023 Not Ready for Inspection JEREMY TODD
Shower Pan 3/20/2023 Approved JEREMY TODD
Interior/Exterior Lathing 4/4/2023 Approved JEREMY TODD
Final 8/2/2023 Corrections Issued ARAM AVEDISIAN
Green Building Final 8/2/2023 Approved ARAM AVEDISIAN
MERV13>=Final 8/2/2023 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 8/2/2023 SGSOV Not Ready ARAM AVEDISIAN
Smoke Detectors 8/2/2023 Not Ready for Inspection ARAM AVEDISIAN
Final 8/16/2023 Not Ready for Inspection MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 8/16/2023 SGSOV Approved MEL KHACHATOURIAN
Smoke Detectors 8/16/2023 Approved MEL KHACHATOURIAN
Final 9/12/2023 OK to Issue CofO MEL KHACHATOURIAN