1235-1235 1/2 E 50TH ST 90011
Certificate Information: 1235-1235 1/2 E 50TH ST 90011
- Application / Permit
- 22014-10000-04669
- Plan Check / Job No.
- B22LA18875
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- 1-STORY ADDITION TO 2-STORY DUPLEX.
- Permit Issued
- Issued on 2/22/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/22/2022 | JOSEPH RAFOLS |
| Corrections Issued | 9/24/2022 | JOSEPH RAFOLS |
| Building Plans Picked Up | 9/28/2022 | APPLICANT |
| Applicant returned to address corrections | 1/23/2023 | KHUONG TRUONG |
| Plan Check Approved | 2/22/2023 | CRISTINA SALAZAR |
| Issued | 2/22/2023 | APPLICANT |
| CofO in Progress | 2/21/2024 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 3/1/2024 | DEROLD HAUFF |
| CofO Issued | 3/1/2024 | DEROLD HAUFF |
| Permit Finaled | 3/1/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/1/2023 | AMAAN MALIK |
| Roof/Waste drainage to street | Cleared | 2/1/2023 | AMAAN MALIK |
| Sewer availability | Cleared | 2/1/2023 | AMAAN MALIK |
| Tenant Habitability Plan | Cleared | 2/21/2023 | MICHAEL SOTO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 11 CEDARWOOD DR POMONA, CA 91766 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/26/2023 | Corrections Issued | BRENDAN MORELLI |
| Footing/Foundation/Slab | 5/26/2023 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 8/1/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 8/1/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 8/1/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 8/1/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 8/1/2023 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 8/1/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Pre-Inspection | 8/15/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 8/18/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 8/29/2023 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 9/18/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 9/18/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2023 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 10/13/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 10/13/2023 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 10/24/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 10/24/2023 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 10/24/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 11/6/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Deputy Wood Construction | 11/6/2023 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 11/6/2023 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 11/15/2023 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 11/15/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 12/6/2023 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 12/6/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 2/1/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 2/1/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 2/1/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 2/1/2024 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 2/1/2024 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 2/1/2024 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 2/1/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 2/20/2024 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Green Building Final | 2/20/2024 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 2/20/2024 | SGSOV Approved | ALEJANDRO DE ARTOLA |