1235-1235 1/2 E 50TH ST 90011

Certificate Information: 1235-1235 1/2 E 50TH ST 90011

Application / Permit
22014-10000-04669
Plan Check / Job No.
B22LA18875
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
1-STORY ADDITION TO 2-STORY DUPLEX.
Permit Issued
Issued on 2/22/2023
Issuing Office
Metro
Current Status
CofO Issued on 3/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/20/2022 APPLICANT
Assigned to Plan Check Engineer 9/22/2022 JOSEPH RAFOLS
Corrections Issued 9/24/2022 JOSEPH RAFOLS
Building Plans Picked Up 9/28/2022 APPLICANT
Applicant returned to address corrections 1/23/2023 KHUONG TRUONG
Plan Check Approved 2/22/2023 CRISTINA SALAZAR
Issued 2/22/2023 APPLICANT
CofO in Progress 2/21/2024 ALEJANDRO DE ARTOLA
Permit Finaled 3/1/2024 DEROLD HAUFF
CofO Issued 3/1/2024 DEROLD HAUFF
Permit Finaled 3/1/2024 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/1/2023 AMAAN MALIK
Roof/Waste drainage to street Cleared 2/1/2023 AMAAN MALIK
Sewer availability Cleared 2/1/2023 AMAAN MALIK
Tenant Habitability Plan Cleared 2/21/2023 MICHAEL SOTO

Contact Information

Contractor Owner-Builder       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/26/2023 Corrections Issued BRENDAN MORELLI
Footing/Foundation/Slab 5/26/2023 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 8/1/2023 Corrections Issued ALEJANDRO DE ARTOLA
Final 8/1/2023 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 8/1/2023 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 8/1/2023 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 8/1/2023 SGSOV Not Ready ALEJANDRO DE ARTOLA
Smoke Detectors 8/1/2023 Corrections Issued ALEJANDRO DE ARTOLA
Pre-Inspection 8/15/2023 Partial Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 8/18/2023 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 8/29/2023 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 9/18/2023 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 9/18/2023 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 10/6/2023 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 10/13/2023 Partial Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 10/13/2023 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 10/24/2023 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 10/24/2023 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 10/24/2023 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 10/24/2023 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 11/6/2023 Corrections Issued ALEJANDRO DE ARTOLA
Deputy Wood Construction 11/6/2023 Approved ALEJANDRO DE ARTOLA
Green Building Rough 11/6/2023 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 11/15/2023 Approved ALEJANDRO DE ARTOLA
Insulation 11/15/2023 Corrections Issued ALEJANDRO DE ARTOLA
Drywall Nailing 12/6/2023 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 12/6/2023 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Final 2/1/2024 Approved ALEJANDRO DE ARTOLA
Final 2/1/2024 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 2/1/2024 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 2/1/2024 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 2/1/2024 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 2/1/2024 SGSOV Not Ready ALEJANDRO DE ARTOLA
Smoke Detectors 2/1/2024 Approved ALEJANDRO DE ARTOLA
Final 2/20/2024 OK to Issue CofO ALEJANDRO DE ARTOLA
Green Building Final 2/20/2024 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 2/20/2024 SGSOV Approved ALEJANDRO DE ARTOLA