815 S CLOVERDALE AVE 90036
Certificate Information: 815 S CLOVERDALE AVE 90036
- Application / Permit
- 22014-10000-04650
- Plan Check / Job No.
- B22LA18778
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED REMODEL AND ADDITION OF (E) SFD. 1 OF 2
- Permit Issued
- Issued on 4/21/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/22/2022 | MICHAEL LOPEZ |
| Corrections Issued | 9/29/2022 | MICHAEL LOPEZ |
| Quality Review Completed | 10/5/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 10/7/2022 | APPLICANT |
| Applicant returned to address corrections | 1/30/2023 | MARCELA FRANQUEZ |
| Plan Check Approved | 2/15/2023 | MARCELA FRANQUEZ |
| Issued | 4/21/2023 | APPLICANT |
| CofO in Progress | 6/12/2025 | WILLIAM SIERRA |
| Permit Finaled | 6/17/2025 | DEROLD HAUFF |
| CofO Issued | 6/17/2025 | DEROLD HAUFF |
| Permit Finaled | 6/17/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/22/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 10/22/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 10/25/2022 | JEANETTE VONG |
| CPC | Cleared | 11/9/2022 | LOUIS ORTEGA |
| Miscellaneous | Cleared | 11/9/2022 | LOUIS ORTEGA |
| HPOZ | Cleared | 1/20/2023 | AMANDA KAINER |
Contact Information
| Architect | Torrence,, Aaron Julian; Lic. No.: C29707 | 9503 JEFFERSON BLVD CULVER CITY, CA 90232 |
| Contractor | Build Method Construction Inc; Lic. No.: 1059684-B | 4252 WHITSETT AVE STE 404 STUDIO CITY, CA 91604 |
| Engineer | Kiledjian,, George Zohrab; Lic. No.: C74761 | 11447 VIKING AVE NORTHRIDGE, CA 91326 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 5/26/2023 | Approved | RICHARD DOCKUS |
| Footing/Foundation/Slab | 6/20/2023 | Not Ready for Inspection | RICHARD DOCKUS |
| METHANE-Barrier | 6/20/2023 | Approved | RICHARD DOCKUS |
| METHANE-Subgrade | 6/20/2023 | Approved | RICHARD DOCKUS |
| Deputy Drilled-In Anchors | 6/21/2023 | Conditional Approval | RICHARD DOCKUS |
| Footing/Foundation/Slab | 7/6/2023 | Corrections Issued | RICHARD DOCKUS |
| Footing/Foundation/Slab | 7/12/2023 | Partial Approval | JEFFREY MEAD |
| Deputy Drilled-In Anchors | 7/24/2023 | Partial Approval | SCOTT FINNILA |
| Deputy Reinf. Concrete | 7/24/2023 | Conditional Approval | BRENDAN MORELLI |
| Footing/Foundation/Slab | 7/24/2023 | Conditional Approval | SCOTT FINNILA |
| Deputy Reinf. Concrete | 7/28/2023 | Partial Approval | SCOTT FINNILA |
| Sewer | 10/6/2023 | Approved | RICHARD DOCKUS |
| Underground Mechanical | 10/6/2023 | Partial Approval | RICHARD DOCKUS |
| Footing/Foundation/Slab | 10/27/2023 | Corrections Issued | DAVID FEILER |
| Footing/Foundation/Slab | 10/31/2023 | Approved | RICHARD DOCKUS |
| Deputy Reinf. Concrete | 11/2/2023 | Conditional Approval | RICHARD DOCKUS |
| Excavation/Setback/Form/Re-Bar | 11/16/2023 | Partial Approval | JEFFREY MEAD |
| PLUMBING-Rough | 12/29/2023 | Partial Approval | RICHARD DOCKUS |
| Wood Frame | 12/29/2023 | Partial Approval | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 1/9/2024 | Corrections Issued | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 1/10/2024 | Partial Approval | RICHARD DOCKUS |
| Deputy Wood Construction | 3/6/2024 | Conditional Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2024 | Approved | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2024 | Approved | RONNIE MINDANAO |
| HVAC-Rough | 7/10/2024 | Corrections Issued | RONNIE MINDANAO |
| Insulation | 7/10/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| PLUMBING-Rough | 7/10/2024 | Corrections Issued | RONNIE MINDANAO |
| Gas Test | 7/12/2024 | Corrections Issued | RONNIE MINDANAO |
| PLUMBING-Rough | 7/16/2024 | Approved | RONNIE MINDANAO |
| HVAC-Rough | 7/18/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Underground Mechanical | 7/18/2024 | Partial Approval | RONNIE MINDANAO |
| HVAC-Rough | 7/23/2024 | Approved | RONNIE MINDANAO |
| Insulation | 7/23/2024 | Partial Approval | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2024 | Corrections Issued | RONNIE MINDANAO |
| Green Building Rough | 8/1/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| METHANE-Rough | 8/1/2024 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Rough | 8/6/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2024 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Rough | 8/13/2024 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 8/22/2024 | Corrections Issued | RONNIE MINDANAO |
| ELECTRICAL-Rough | 8/22/2024 | Corrections Issued | RONNIE MINDANAO |
| Green Building Rough | 8/22/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Masonry Wall/Backfill | 8/22/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| ELECTRICAL-Rough | 8/26/2024 | Approved | RONNIE MINDANAO |
| Masonry Wall/Backfill | 8/26/2024 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 9/11/2024 | Approved | RONNIE MINDANAO |
| Green Building Rough | 9/11/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Insulation | 9/11/2024 | Approved | RONNIE MINDANAO |
| Interior/Exterior Lathing | 9/13/2024 | Approved | RONNIE MINDANAO |
| Drywall Nailing | 9/23/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Green Building Rough | 9/23/2024 | Approved | RONNIE MINDANAO |
| Drywall Nailing | 9/25/2024 | Approved | RONNIE MINDANAO |
| Shower Pan | 10/15/2024 | Approved | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 10/21/2024 | Approved | RONNIE MINDANAO |
| HVAC-Final | 5/12/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| ELECTRICAL-Final | 5/30/2025 | Corrections Issued | RONNIE MINDANAO |
| PLUMBING-Final | 5/30/2025 | Corrections Issued | RONNIE MINDANAO |
| Pre-Inspection | 5/30/2025 | Partial Inspection | RAUL BARAJAS |
| HVAC-Final | 6/2/2025 | Corrections Issued | RONNIE MINDANAO |
| ELECTRICAL-Final | 6/3/2025 | Approved | RONNIE MINDANAO |
| Final | 6/3/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Gas Test | 6/3/2025 | Approved | RONNIE MINDANAO |
| Green Building Final | 6/3/2025 | Approved | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 6/3/2025 | SGSOV Approved | RONNIE MINDANAO |
| Smoke Detectors | 6/3/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| HVAC-Final | 6/4/2025 | Corrections Issued | RONNIE MINDANAO |
| Final | 6/6/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| HVAC-Final | 6/6/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Smoke Detectors | 6/6/2025 | Approved | RONNIE MINDANAO |
| Final | 6/11/2025 | OK to Issue CofO | WILLIAM SIERRA |
| HVAC-Final | 6/11/2025 | Approved | WILLIAM SIERRA |
| Service/Power Release | 6/11/2025 | Approved | WILLIAM SIERRA |