6410 W 87TH PL 90045

Certificate Information: 6410 W 87TH PL 90045

Application / Permit
22014-10000-04647
Plan Check / Job No.
B22LA18762
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
BATHROOM REMODEL- ADDITION OF TUB ALCOVE AND INTERIOR HALF BATH
Permit Issued
Issued on 9/21/2022
Issuing Office
Metro
Current Status
CofO Issued on 1/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/19/2022 APPLICANT
Assigned to Plan Check Engineer 9/19/2022 KHUONG TRUONG
Plan Check Approved 9/19/2022 KHUONG TRUONG
Issued 9/21/2022 APPLICANT
CofO in Progress 1/10/2023 BOBBY KEY
Permit Finaled 1/19/2023 DANIEL ORRANTE
CofO Issued 1/19/2023 DANIEL ORRANTE
Permit Finaled 1/19/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/19/2022 CINDY QI
Roof/Waste drainage to street Cleared 9/19/2022 CINDY QI

Contact Information

Architect Asamoah,, B Kwesi; Lic. No.: C36558 850 ROSE AVENUE      VENICE, CA 90291
Architect Ryder,, Eric Otto; Lic. No.: C32173 2004 19TH STREET      SANTA MONICA, CA 90404
Contractor Owner-Builder       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/2/2022 Approved BOBBY KEY
ELECTRICAL-Rough 11/7/2022 Partial Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 11/7/2022 Partial Approval ANDREW NAVE
ELECTRICAL-Rough 11/14/2022 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 11/14/2022 Approved BOBBY KEY
PLUMBING-Rough 11/14/2022 Corrections Issued BOBBY KEY
Wood Frame 11/14/2022 Partial Approval BOBBY KEY
BUILDING-Rough-Frame 11/18/2022 Approved BOBBY KEY
Green Building Rough 11/18/2022 Approved BOBBY KEY
HVAC-Rough 11/18/2022 Corrections Issued BOBBY KEY
Insulation 11/18/2022 Approved BOBBY KEY
Interior/Exterior Lathing 11/18/2022 Partial Approval BOBBY KEY
PLUMBING-Rough 11/18/2022 Not Ready for Inspection BOBBY KEY
Drywall Nailing 11/23/2022 Approved BOBBY KEY
HVAC-Rough 11/23/2022 Approved BOBBY KEY
Interior/Exterior Lathing 11/23/2022 Approved BOBBY KEY
PLUMBING-Rough 11/23/2022 Approved BOBBY KEY
ELECTRICAL-Final 12/27/2022 Approved BOBBY KEY
Final 12/27/2022 Corrections Issued BOBBY KEY
Green Building Final 12/27/2022 Approved BOBBY KEY
HVAC-Final 12/27/2022 Approved BOBBY KEY
PLUMBING-Final 12/27/2022 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 12/27/2022 SGSOV Not Ready BOBBY KEY
Smoke Detectors 12/27/2022 Approved BOBBY KEY
Final 1/10/2023 OK to Issue CofO BOBBY KEY
SGSOV-Seismic Gas S/O Valve 1/10/2023 SGSOV Approved BOBBY KEY