4411 E YORK BLVD 1 90041
Certificate Information: 4411 E YORK BLVD 1 90041
- Application / Permit
- 22014-10000-04645
- Plan Check / Job No.
- B22LA18750
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (8) Automobile Sales - used
- Work Description
- EPLAN - TENANT IMPROVEMENT & ADDITION TO (E) AUTO SALES BUILDING
- Permit Issued
- Issued on 5/2/2023
- Issuing Office
- Current Status
- CofO Issued on 5/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/20/2022 | SERGIO GUTIERREZ |
| Corrections Issued | 10/25/2022 | SERGIO GUTIERREZ |
| Quality Review Completed | 10/26/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 1/23/2023 | SERGIO GUTIERREZ |
| Applicant returned to address corrections | 2/21/2023 | SERGIO GUTIERREZ |
| Applicant returned to address corrections | 3/20/2023 | SERGIO GUTIERREZ |
| Plan Check Approved | 5/1/2023 | SERGIO GUTIERREZ |
| Issued | 5/2/2023 | APPLICANT |
| CofO in Progress | 5/1/2024 | RAMAZANALI ALMASI |
| Permit Finaled | 5/3/2024 | RAFAEL ESPINOZA |
| CofO Issued | 5/3/2024 | RAFAEL ESPINOZA |
| Permit Finaled | 5/3/2024 | RAFAEL ESPINOZA |
Permit Application Clearance Information
| "Q" conditions | Cleared | 12/14/2022 | JAZMIN ROQUE |
| Roof/Waste drainage to street | Cleared | 12/15/2022 | TREVOR QUAN |
| Prkng lot landscape/Water mgmt | Cleared | 12/19/2022 | JAZMIN ROQUE |
| Eng Process Fee Ord 176,300 | Cleared | 2/3/2023 | TREVOR QUAN |
| Sewer availability | Cleared | 2/3/2023 | TREVOR QUAN |
| Automotive Use | Cleared | 2/8/2023 | KENTON TRINH |
| Green Code | Cleared | 2/10/2023 | SERGIO GUTIERREZ |
| DAS Clearance | Cleared | 2/15/2023 | SERGIO GUTIERREZ |
| Automotive Use | Cleared | 3/14/2023 | JAZMIN ROQUE |
| Internal circulation | Cleared | 4/12/2023 | WESTON PRINGLE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
| Engineer | Grigoryan,, Souren; Lic. No.: NA93320 | , |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/15/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Footing/Foundation/Slab | 5/18/2023 | No Access for Inspection | RAFAEL CORTES |
| Footing/Foundation/Slab | 5/31/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Excavation/Setback/Form/Re-Bar | 6/6/2023 | Partial Approval | RAFAEL CORTES |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Green Building Rough | 8/10/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Wood Frame | 8/10/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2023 | Partial Approval | RAFAEL CORTES |
| Green Building Rough | 8/28/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Wall Anchors | 8/28/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Wood Frame | 8/28/2023 | Partial Approval | RAFAEL CORTES |
| Interior/Exterior Lathing | 9/20/2023 | Approved | VAHE KELEDJIAN |
| Insulation | 9/22/2023 | Approved | VAHE KELEDJIAN |
| Drywall Nailing | 9/28/2023 | Approved | RAFAEL CORTES |
| Final | 11/3/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Footing/Foundation/Slab | 11/3/2023 | Approved | RAFAEL CORTES |
| Green Building Final | 11/3/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Green Building Rough | 11/3/2023 | Approved | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 11/3/2023 | SGSOV Not Ready | RAFAEL CORTES |
| Smoke Detectors | 11/3/2023 | Approved | RAFAEL CORTES |
| Wood Frame | 11/3/2023 | Approved | RAFAEL CORTES |
| Final | 4/19/2024 | Conditional Approval | RAMAZANALI ALMASI |
| Green Building Final | 4/19/2024 | Approved | RAMAZANALI ALMASI |
| SGSOV-Seismic Gas S/O Valve | 4/19/2024 | SGSOV No Gas | RAMAZANALI ALMASI |
| Final | 5/1/2024 | OK to Issue CofO | RAMAZANALI ALMASI |