2639 S GENESEE AVE 90016

Certificate Information: 2639 S GENESEE AVE 90016

Application / Permit
22014-10000-04639
Plan Check / Job No.
B22LA18714
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan Remodel and addition of 285 sqft to SFD New 735 square foot attached ADU PER LAMC 12.22 A.33(c) and (e)
Permit Issued
Issued on 1/10/2023
Issuing Office
Current Status
CofO Issued on 11/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/19/2022 APPLICANT
Assigned to Plan Check Engineer 10/6/2022 JAD BASMA
Corrections Issued 10/13/2022 JAD BASMA
Quality Review Completed 10/20/2022 TEODORO DIAZ RODRIGUEZ
Plan Check Approved 12/19/2022 JAD BASMA
Issued 1/10/2023 APPLICANT
CofO in Progress 10/16/2023 JOSE AVILA
CofO Issued 11/5/2023 DEROLD HAUFF
Permit Finaled 11/5/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/31/2022 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 11/10/2022 CELINA MORENO
Sewer availability Cleared 11/10/2022 CELINA MORENO
Low Impact Development Cleared 12/6/2022 ERNEST TSE
Roof/Waste drainage to street Cleared 12/7/2022 TREVOR QUAN

Contact Information

Contractor Zenith Builder Llc; Lic. No.: 1035285-B 5917 OAK AVE #325      TEMPLE CITY, CA 91780
Engineer Muwanes,, David; Lic. No.: NA77659       ,

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/31/2023 Partial Inspection JOSE AVILA
Footing/Foundation/Slab 2/10/2023 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 2/14/2023 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 3/9/2023 Partial Approval FREDDIE RIVERA
PLUMBING-Rough 3/9/2023 Partial Approval FREDDIE RIVERA
Sewer 3/9/2023 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 3/24/2023 Partial Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 3/31/2023 Partial Approval JOSE AVILA
PLUMBING-Rough 4/11/2023 Partial Approval THOMAS LOGRASSO
Footing/Foundation/Slab 4/17/2023 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 4/25/2023 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 6/6/2023 Conditional Approval JOSE AVILA
Deputy Wood Construction 6/15/2023 Conditional Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 6/22/2023 Partial Approval JOSE AVILA
ELECTRICAL-Rough 6/28/2023 Corrections Issued JOSE AVILA
HVAC-Rough 6/28/2023 Not Ready for Inspection JOSE AVILA
PLUMBING-Rough 6/28/2023 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 7/5/2023 Corrections Issued JOSE AVILA
HVAC-Rough 7/5/2023 Corrections Issued JOSE AVILA
PLUMBING-Rough 7/6/2023 Approved JOSE AVILA
BUILDING-Rough-Frame 7/12/2023 Conditional Approval JOSE AVILA
ELECTRICAL-Rough 7/12/2023 Approved JOSE AVILA
HVAC-Rough 7/12/2023 Approved JOSE AVILA
Insulation 7/17/2023 Approved JOSE AVILA
Drywall Nailing 7/26/2023 Corrections Issued THOMAS LOGRASSO
Sewer 7/26/2023 Partial Approval THOMAS LOGRASSO
Shower Pan 7/26/2023 Approved THOMAS LOGRASSO
Drywall Nailing 7/31/2023 Approved JOSE AVILA
Interior/Exterior Lathing 7/31/2023 Approved JOSE AVILA
Gas Test 9/18/2023 Approved LILIANA PORTILLO
ELECTRICAL-Final 9/25/2023 Corrections Issued JOSE AVILA
HVAC-Final 9/25/2023 Corrections Issued JOSE AVILA
PLUMBING-Final 9/25/2023 Corrections Issued JOSE AVILA
ELECTRICAL-Final 10/2/2023 Approved JOSE AVILA
HVAC-Final 10/2/2023 Approved JOSE AVILA
PLUMBING-Final 10/2/2023 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 10/4/2023 Approved JOSE AVILA
Final 10/4/2023 Corrections Issued JOSE AVILA
Smoke Detectors 10/4/2023 Approved JOSE AVILA
Final 10/10/2023 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 10/10/2023 SGSOV Approved JOSE AVILA
Final 10/13/2023 OK to Issue CofO JOSE AVILA
Service/Power Release 10/19/2023 Approved JOSE AVILA