2639 S GENESEE AVE 90016
Certificate Information: 2639 S GENESEE AVE 90016
- Application / Permit
- 22014-10000-04639
- Plan Check / Job No.
- B22LA18714
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan Remodel and addition of 285 sqft to SFD New 735 square foot attached ADU PER LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 1/10/2023
- Issuing Office
- Current Status
- CofO Issued on 11/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/6/2022 | JAD BASMA |
| Corrections Issued | 10/13/2022 | JAD BASMA |
| Quality Review Completed | 10/20/2022 | TEODORO DIAZ RODRIGUEZ |
| Plan Check Approved | 12/19/2022 | JAD BASMA |
| Issued | 1/10/2023 | APPLICANT |
| CofO in Progress | 10/16/2023 | JOSE AVILA |
| CofO Issued | 11/5/2023 | DEROLD HAUFF |
| Permit Finaled | 11/5/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/31/2022 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 11/10/2022 | CELINA MORENO |
| Sewer availability | Cleared | 11/10/2022 | CELINA MORENO |
| Low Impact Development | Cleared | 12/6/2022 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 12/7/2022 | TREVOR QUAN |
Contact Information
| Contractor | Zenith Builder Llc; Lic. No.: 1035285-B | 5917 OAK AVE #325 TEMPLE CITY, CA 91780 |
| Engineer | Muwanes,, David; Lic. No.: NA77659 | , |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/31/2023 | Partial Inspection | JOSE AVILA |
| Footing/Foundation/Slab | 2/10/2023 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 2/14/2023 | Corrections Issued | JOSE AVILA |
| BUILDING-Rough-Frame | 3/9/2023 | Partial Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 3/9/2023 | Partial Approval | FREDDIE RIVERA |
| Sewer | 3/9/2023 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2023 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2023 | Partial Approval | JOSE AVILA |
| PLUMBING-Rough | 4/11/2023 | Partial Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 4/17/2023 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 4/25/2023 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2023 | Conditional Approval | JOSE AVILA |
| Deputy Wood Construction | 6/15/2023 | Conditional Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/22/2023 | Partial Approval | JOSE AVILA |
| ELECTRICAL-Rough | 6/28/2023 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 6/28/2023 | Not Ready for Inspection | JOSE AVILA |
| PLUMBING-Rough | 6/28/2023 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 7/5/2023 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 7/5/2023 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 7/6/2023 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 7/12/2023 | Conditional Approval | JOSE AVILA |
| ELECTRICAL-Rough | 7/12/2023 | Approved | JOSE AVILA |
| HVAC-Rough | 7/12/2023 | Approved | JOSE AVILA |
| Insulation | 7/17/2023 | Approved | JOSE AVILA |
| Drywall Nailing | 7/26/2023 | Corrections Issued | THOMAS LOGRASSO |
| Sewer | 7/26/2023 | Partial Approval | THOMAS LOGRASSO |
| Shower Pan | 7/26/2023 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 7/31/2023 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 7/31/2023 | Approved | JOSE AVILA |
| Gas Test | 9/18/2023 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 9/25/2023 | Corrections Issued | JOSE AVILA |
| HVAC-Final | 9/25/2023 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 9/25/2023 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Final | 10/2/2023 | Approved | JOSE AVILA |
| HVAC-Final | 10/2/2023 | Approved | JOSE AVILA |
| PLUMBING-Final | 10/2/2023 | Corrections Issued | JOSE AVILA |
| BUILDING-Rough-Frame | 10/4/2023 | Approved | JOSE AVILA |
| Final | 10/4/2023 | Corrections Issued | JOSE AVILA |
| Smoke Detectors | 10/4/2023 | Approved | JOSE AVILA |
| Final | 10/10/2023 | Corrections Issued | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 10/10/2023 | SGSOV Approved | JOSE AVILA |
| Final | 10/13/2023 | OK to Issue CofO | JOSE AVILA |
| Service/Power Release | 10/19/2023 | Approved | JOSE AVILA |