1929 1/2 W 65TH ST 90047

Certificate Information: 1929 1/2 W 65TH ST 90047

Application / Permit
22014-10000-04635
Plan Check / Job No.
B22LA18703
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE (288SF) INTO NEW ACCESSORY DWELLING UNIT WITH ADDITION (1,200 SF max per Ordinance, LAMC 12.22 A.33 (c)-(d))
Permit Issued
Issued on 1/17/2023
Issuing Office
Metro
Current Status
CofO Issued on 7/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/16/2022 APPLICANT
Assigned to Plan Check Engineer 9/22/2022 AUNG SOE
Corrections Issued 9/27/2022 AUNG SOE
Building Plans Picked Up 11/14/2022 APPLICANT
Applicant returned to address corrections 1/17/2023 WEIJIAN HUANG
Plan Check Approved 1/17/2023 DANIEL SMILEY
Issued 1/17/2023 APPLICANT
CofO in Progress 7/17/2023 ENRIQUE MIRELES
CofO in Progress 7/17/2023 ENRIQUE MIRELES
Permit Finaled 7/23/2023 DEROLD HAUFF
CofO Issued 7/23/2023 DEROLD HAUFF
Permit Finaled 7/23/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/17/2022 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 12/1/2022 AMAAN MALIK
Roof/Waste drainage to street Cleared 12/1/2022 AMAAN MALIK
Sewer availability Cleared 12/1/2022 AMAAN MALIK
Construction near power lines Cleared 1/8/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/2/2023 Approved ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 2/10/2023 Corrections Issued ENRIQUE MIRELES
Underground Mechanical 2/10/2023 Approved ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 2/16/2023 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 2/16/2023 Approved ENRIQUE MIRELES
Sewer 2/27/2023 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 3/15/2023 Approved ENRIQUE MIRELES
Wood Frame 3/15/2023 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 3/20/2023 Approved ENRIQUE MIRELES
Green Building Rough 3/20/2023 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 3/30/2023 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 3/30/2023 Approved ENRIQUE MIRELES
PLUMBING-Rough 3/30/2023 Approved ENRIQUE MIRELES
Gas Test 4/13/2023 Approved ENRIQUE MIRELES
Insulation 4/13/2023 Approved ENRIQUE MIRELES
Drywall Nailing 4/21/2023 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 5/15/2023 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 5/30/2023 Approved ENRIQUE MIRELES
ELECTRICAL-Final 6/27/2023 Approved ENRIQUE MIRELES
Final 6/27/2023 Corrections Issued ENRIQUE MIRELES
Green Building Final 6/27/2023 Approved ENRIQUE MIRELES
HVAC-Final 6/27/2023 Approved ENRIQUE MIRELES
PLUMBING-Final 6/27/2023 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 6/27/2023 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 6/27/2023 Approved ENRIQUE MIRELES
Final 7/13/2023 OK to Issue CofO ENRIQUE MIRELES