6846 N BELLINGHAM AVE 91605

Certificate Information: 6846 N BELLINGHAM AVE 91605

Application / Permit
22014-10000-04617
Plan Check / Job No.
B22LA18628
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE WITH A (N) 8'-0" x 16'-0" ADDTION INTO A (N) 28'-0" x18'-6" DETACHED ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33 (c)(d) PER ENGINEERING
Permit Issued
Issued on 12/7/2022
Issuing Office
Current Status
CofO Issued on 5/8/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/15/2022 APPLICANT
Assigned to Plan Check Engineer 9/19/2022 KHUONG TRUONG
Corrections Issued 9/19/2022 KHUONG TRUONG
Building Plans Picked Up 9/22/2022 APPLICANT
Issued 12/7/2022 APPLICANT
CofO in Progress 5/7/2024 JUAN VALENZUELA
Permit Finaled 5/8/2024 RUBEN SALAS
CofO Issued 5/8/2024 RUBEN SALAS
Permit Finaled 5/8/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/5/2022 COLIN LOREDO
Roof/Waste drainage to street Cleared 10/5/2022 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 10/11/2022 COLIN LOREDO
Sewer availability Cleared 10/11/2022 COLIN LOREDO
Construction near power lines Cleared 12/2/2022 RIDWAN HARDY

Contact Information

Contractor Neo Builders Inc; Lic. No.: 1061134-B 6238 ALCOVE AVE      NORTH HOLLYWOOD, CA 91606
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/20/2023 Approved KIRK SANDERS
Footing/Foundation/Slab 4/6/2023 Corrections Issued KIRK SANDERS
Footing/Foundation/Slab 4/18/2023 Approved KIRK SANDERS
ELECTRICAL-Rough 6/14/2023 Corrections Issued KIRK SANDERS
HVAC-Rough 6/14/2023 Approved KIRK SANDERS
PLUMBING-Rough 6/14/2023 Approved KIRK SANDERS
BUILDING-Rough-Frame 6/28/2023 Approved KIRK SANDERS
ELECTRICAL-Rough 6/28/2023 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 6/28/2023 Corrections Issued KIRK SANDERS
Green Building Rough 6/28/2023 Approved KIRK SANDERS
Insulation 6/28/2023 Partial Approval KIRK SANDERS
Deputy Wood Construction 7/11/2023 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 7/17/2023 Approved KIRK SANDERS
Interior/Exterior Lathing 8/8/2023 Corrections Issued CHRISTOPHE COCHRAN
Insulation 8/14/2023 Approved JUAN VALENZUELA
Interior/Exterior Lathing 8/14/2023 Partial Approval JUAN VALENZUELA
Shower Pan 8/14/2023 Approved JUAN VALENZUELA
Drywall Nailing 8/29/2023 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 9/13/2023 Approved KIRK SANDERS
Final 11/21/2023 Corrections Issued JUAN VALENZUELA
Green Building Final 11/21/2023 Approved JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 11/21/2023 SGSOV Not Ready JUAN VALENZUELA
Smoke Detectors 11/21/2023 Approved JUAN VALENZUELA
Final 3/28/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 3/28/2024 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Final 4/12/2024 Corrections Issued JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 4/12/2024 SGSOV Approved JUAN VALENZUELA
ELECTRICAL-Final 4/30/2024 Approved JUAN VALENZUELA
Final 4/30/2024 OK to Issue CofO JUAN VALENZUELA
HVAC-Final 4/30/2024 Approved JUAN VALENZUELA
PLUMBING-Final 4/30/2024 Approved JUAN VALENZUELA