13723 W MAGNOLIA BLVD 91423

Certificate Information: 13723 W MAGNOLIA BLVD 91423

Application / Permit
22014-10000-04595
Plan Check / Job No.
B22LA18503
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL AND ADDITION TO (E) SFD (1-STORY)
Permit Issued
Issued on 2/3/2023
Issuing Office
Current Status
CofO Issued on 6/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/15/2022 APPLICANT
Assigned to Plan Check Engineer 9/22/2022 CARLOS MONTES
Corrections Issued 9/24/2022 CARLOS MONTES
Quality Review Completed 9/27/2022 GARO TELMI
Applicant returned to address corrections 12/1/2022 CARLOS MONTES
Plan Check Approved 1/10/2023 CARLOS MONTES
Issued 2/3/2023 APPLICANT
CofO in Progress 5/23/2024 RYAN SALAZAR
Permit Finaled 6/6/2024 RUBEN SALAS
CofO Issued 6/6/2024 RUBEN SALAS
Permit Finaled 6/6/2024 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/18/2022 COLIN LOREDO
Roof/Waste drainage to street Cleared 10/18/2022 COLIN LOREDO
Sewer availability Cleared 10/18/2022 COLIN LOREDO

Contact Information

Architect Woodcraft,, Astra E; Lic. No.: NA32722       ,
Contractor Build Method Construction Inc; Lic. No.: 1059684-B       ,
Engineer Tan,, Henreik Steven; Lic. No.: NA65723       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/18/2023 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 5/8/2023 Approved JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 5/10/2023 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 5/26/2023 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 6/21/2023 Partial Approval RYAN SALAZAR
PLUMBING-Rough 6/21/2023 Not Ready for Inspection RYAN SALAZAR
HVAC-Rough 6/27/2023 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 7/12/2023 Not Ready for Inspection RYAN SALAZAR
Shower Pan 7/12/2023 Not Ready for Inspection RYAN SALAZAR
Deputy Wood Construction 7/13/2023 Conditional Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 7/13/2023 Partial Approval RYAN SALAZAR
ELECTRICAL-Rough 7/26/2023 Approved DAVID MATSON
HVAC-Rough 7/26/2023 Approved DAVID MATSON
PLUMBING-Rough 7/26/2023 Approved DAVID MATSON
Shower Pan 7/26/2023 Approved DAVID MATSON
Interior/Exterior Lathing 8/3/2023 Partial Approval DAVID MATSON
BUILDING-Rough-Frame 8/30/2023 Approved RYAN SALAZAR
Green Building Rough 8/30/2023 Approved RYAN SALAZAR
Insulation 9/21/2023 Approved RYAN SALAZAR
Drywall Nailing 10/3/2023 Not Ready for Inspection MICHEL ABAJAN
Drywall Nailing 10/6/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 10/6/2023 Approved RYAN SALAZAR
Gas Test 1/23/2024 Approved RYAN SALAZAR
ELECTRICAL-Final 1/31/2024 Approved RYAN SALAZAR
HVAC-Final 1/31/2024 Approved RYAN SALAZAR
PLUMBING-Final 1/31/2024 Approved RYAN SALAZAR
Service/Power Release 2/21/2024 Approved RYAN SALAZAR
ELECTRICAL-Final 5/22/2024 Approved RYAN SALAZAR
Final 5/22/2024 OK to Issue CofO RYAN SALAZAR
Footing/Foundation/Slab 5/22/2024 Approved RYAN SALAZAR
Green Building Final 5/22/2024 Approved RYAN SALAZAR
HVAC-Final 5/22/2024 Approved RYAN SALAZAR
PLUMBING-Final 5/22/2024 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 5/22/2024 SGSOV Approved RYAN SALAZAR
Service/Power Release 5/22/2024 Approved RYAN SALAZAR
Smoke Detectors 5/22/2024 Approved RYAN SALAZAR