3767 S MUIRFIELD ROAD 90016

Certificate Information: 3767 S MUIRFIELD ROAD 90016

Application / Permit
22014-10000-04586
Plan Check / Job No.
B22LA18475
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition to existing single family dwelling (front and rear) and remodel. Fire sprinklers required. All work done per engineering.
Permit Issued
Issued on 4/4/2023
Issuing Office
Metro
Current Status
CofO Issued on 2/28/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/14/2022 APPLICANT
Assigned to Plan Check Engineer 9/19/2022 KHUONG TRUONG
Corrections Issued 9/23/2022 KHUONG TRUONG
Building Plans Picked Up 2/27/2023 APPLICANT
Plan Check Approved 3/29/2023 JOSEPH RAFOLS
Issued 4/4/2023 APPLICANT
CofO in Progress 2/22/2024 ANTHONY EGSON
Permit Finaled 2/28/2024 DEROLD HAUFF
CofO Issued 2/28/2024 DEROLD HAUFF
Permit Finaled 2/28/2024 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/22/2023 ADRIAN SANCHEZ
Roof/Waste drainage to street Cleared 2/22/2023 ADRIAN SANCHEZ
Sewer availability Cleared 2/22/2023 ADRIAN SANCHEZ
Low Impact Development Cleared 3/23/2023 MARTIN FRAGOSO

Contact Information

Contractor Owner-Builder       ,
Engineer Mani,, Dev; Lic. No.: C62778 P O BOX 1451      DUARTE, CA 91009
Engineer Nuno,, Arnulfo; Lic. No.: C88425 7057 DWIGHT WAY      SAN BERNARDINO, CA 92404

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/12/2023 Approved ANTHONY EGSON
Footing/Foundation/Slab 4/12/2023 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 4/18/2023 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 4/24/2023 Not Ready for Inspection BRENDAN MORELLI
Insulation 4/24/2023 Partial Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 5/22/2023 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 5/25/2023 No Access for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 5/30/2023 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 6/1/2023 Approved ANTHONY EGSON
Green Building Rough 7/6/2023 Corrections Issued ANTHONY EGSON
Wood Frame 7/6/2023 Corrections Issued ANTHONY EGSON
Rough-Elec/Plmb/HVAC 7/10/2023 Corrections Issued ANTHONY EGSON
Wood Frame 7/10/2023 Not Ready for Inspection ANTHONY EGSON
Deputy Wood Construction 7/11/2023 Approved ANTHONY EGSON
Wood Frame 7/12/2023 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 7/13/2023 Approved ANTHONY EGSON
Rough-Elec/Plmb/HVAC 7/17/2023 Corrections Issued ANTHONY EGSON
ELECTRICAL-Rough 7/18/2023 Corrections Issued ANTHONY EGSON
Interior/Exterior Lathing 7/19/2023 Approved ANTHONY EGSON
Rough-Elec/Plmb/HVAC 7/19/2023 Approved ANTHONY EGSON
BUILDING-Rough-Frame 7/21/2023 Approved ANTHONY EGSON
Green Building Rough 7/21/2023 Approved ANTHONY EGSON
Insulation 7/21/2023 Approved ANTHONY EGSON
Interior/Exterior Lathing 7/31/2023 Approved ANTHONY EGSON
Drywall Nailing 8/4/2023 Approved ANTHONY EGSON
ELECTRICAL-Final 10/25/2023 Corrections Issued ANTHONY EGSON
PLUMBING-Final 10/26/2023 Corrections Issued ANTHONY EGSON
HVAC-Final 10/27/2023 Corrections Issued ANTHONY EGSON
ELECTRICAL-Final 11/1/2023 Not Ready for Inspection ANTHONY EGSON
HVAC-Final 11/1/2023 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Final 11/1/2023 Not Ready for Inspection ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 11/2/2023 SGSOV Not Ready ANTHONY EGSON
ELECTRICAL-Final 11/7/2023 Approved ANTHONY EGSON
HVAC-Final 11/7/2023 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Final 11/7/2023 Approved ANTHONY EGSON
Final 11/8/2023 Not Ready for Inspection ANTHONY EGSON
Green Building Final 11/8/2023 Not Ready for Inspection ANTHONY EGSON
HVAC-Final 11/8/2023 Not Ready for Inspection ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 11/8/2023 SGSOV Approved ANTHONY EGSON
Smoke Detectors 11/8/2023 Approved ANTHONY EGSON
HVAC-Final 11/10/2023 Off-Hour Fees Due
HVAC-Final 11/14/2023 Approved ANTHONY EGSON
Final 11/17/2023 Corrections Issued ANTHONY EGSON
Green Building Final 11/17/2023 Approved ANTHONY EGSON
Final 2/21/2024 OK to Issue CofO ANTHONY EGSON
Service/Power Release 2/22/2024 Approved ANTHONY EGSON