1471 N RISING GLEN ROAD 90069

Certificate Information: 1471 N RISING GLEN ROAD 90069

Application / Permit
22014-10000-04585
Plan Check / Job No.
B22LA18472
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: Interior renovation and addition to single family residence.
Permit Issued
Issued on 4/17/2023
Issuing Office
Current Status
CofO Issued on 4/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/15/2022 APPLICANT
Assigned to Plan Check Engineer 9/15/2022 ARSALAN SHABESTARI
Corrections Issued 10/6/2022 ARSALAN SHABESTARI
Quality Review Completed 10/6/2022 GARO TELMI
Applicant returned to address corrections 4/11/2023 ARSALAN SHABESTARI
Plan Check Approved 4/17/2023 ARSALAN SHABESTARI
Issued 4/17/2023 APPLICANT
CofO in Progress 4/10/2025 ROY SPAULDING
Permit Finaled 4/13/2025 DEROLD HAUFF
CofO Issued 4/13/2025 DEROLD HAUFF
Permit Finaled 4/13/2025 DEROLD HAUFF

Permit Application Clearance Information

ZI Cleared 10/13/2022 MAYELA VILLA
Eng Process Fee Ord 176,300 Cleared 10/21/2022 AMAAN MALIK
Roof/Waste drainage to street Cleared 10/21/2022 AMAAN MALIK
Sewer availability Cleared 10/21/2022 AMAAN MALIK
Grading Pre-Inspection Cleared 4/12/2023 ARSALAN SHABESTARI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/11/2023 Conditional Approval RAUL BARAJAS
Footing/Foundation/Slab 5/25/2023 Approved RAUL BARAJAS
Deputy Drilled-In Anchors 6/7/2023 Conditional Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 10/10/2023 Not Ready for Inspection RAUL BARAJAS
HVAC-Rough 10/17/2023 Partial Approval RAUL BARAJAS
ELECTRICAL-Rough 12/14/2023 Approved RAUL BARAJAS
HVAC-Rough 12/14/2023 Partial Approval RAUL BARAJAS
PLUMBING-Rough 12/14/2023 Approved RAUL BARAJAS
BUILDING-Rough-Frame 1/17/2024 Conditional Approval RAUL BARAJAS
Interior/Exterior Lathing 3/1/2024 Approved RAUL BARAJAS
Insulation 3/21/2024 Approved RAUL BARAJAS
Drywall Nailing 4/4/2024 Approved RAUL BARAJAS
HVAC-Final 2/5/2025 Approved ROY SPAULDING
PLUMBING-Final 2/5/2025 Approved ROY SPAULDING
ELECTRICAL-Final 2/10/2025 Approved ROY SPAULDING
BUILDING-Rough-Frame 2/18/2025 Approved ROY SPAULDING
Final 2/18/2025 Corrections Issued ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 2/18/2025 SGSOV Not Ready ROY SPAULDING
Smoke Detectors 2/18/2025 Approved ROY SPAULDING
Final 3/14/2025 Corrections Issued ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 3/14/2025 SGSOV Approved ROY SPAULDING
Final 4/1/2025 Not Ready for Inspection ROY SPAULDING
Final 4/9/2025 OK to Issue CofO ROY SPAULDING