17659 W BURBANK BLVD 91316

Certificate Information: 17659 W BURBANK BLVD 91316

Application / Permit
22014-10000-04581
Plan Check / Job No.
B22LA18451
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) FRONT PORCH AND ADDITION TO SFD AND TO CONVERT THE (E) ATTACHED GARAGE TO BE PART OF THE SFD COMPLY WITH DEPARTMENT ORDER effective date 01/10/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
Permit Issued
Issued on 9/30/2022
Issuing Office
Metro
Current Status
CofO Issued on 10/3/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/14/2022 APPLICANT
Assigned to Plan Check Engineer 9/15/2022 AUNG SOE
Corrections Issued 9/19/2022 AUNG SOE
Building Plans Picked Up 9/21/2022 APPLICANT
Plan Check Approved 9/30/2022 FERNANDO FLORES
Issued 9/30/2022 APPLICANT
CofO in Progress 8/17/2023 PATRICK LIEBREGT
CofO Issued 10/3/2023 DANIEL SANCHEZ
Permit Finaled 10/3/2023 DANIEL SANCHEZ

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/19/2022 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 9/19/2022 LEE GUILBEAUX
Sewer availability Cleared 9/19/2022 LEE GUILBEAUX
Watercourse Cleared 9/19/2022 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 9/19/2022 LEE GUILBEAUX
ZI Cleared 9/28/2022 ASHLEY RODARTE

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

JOEL ORDAZ, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
PTOLEMY HILL, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVAKIAN, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
EDMOND DECKERT, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
TIMOTHY KEY, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT CHAVEZ, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/19/2022 Corrections Issued GORDON ZUBER
Deputy Drilled-In Anchors 1/24/2023 Approved PATRICK LIEBREGT
Excavation/Setback/Form/Re-Bar 1/24/2023 Partial Approval ROBERT MINASSIANS
Footing/Foundation/Slab 1/24/2023 Partial Approval ROBERT MINASSIANS
MERV13>=Rough 1/24/2023 Partial Inspection ROBERT MINASSIANS
Excavation/Setback/Form/Re-Bar 1/26/2023 Approved PATRICK LIEBREGT
Rough-Elec/Plmb/HVAC 2/3/2023 Approved PATRICK LIEBREGT
Wood Frame 2/15/2023 Approved PATRICK LIEBREGT
Service/Power Release 2/22/2023 Approved PATRICK LIEBREGT
Drywall Nailing 3/3/2023 Approved PATRICK LIEBREGT
Shower Pan 3/20/2023 Approved ROBERT MINASSIANS
BUILDING-Rough-Frame 5/17/2023 Approved PATRICK LIEBREGT
Final 5/17/2023 Not Ready for Inspection PATRICK LIEBREGT
Footing/Foundation/Slab 5/17/2023 Approved PATRICK LIEBREGT
MERV13>=Final 5/17/2023 Not Ready for Inspection PATRICK LIEBREGT
MERV13>=Rough 5/17/2023 Approved PATRICK LIEBREGT
SGSOV-Seismic Gas S/O Valve 5/17/2023 SGSOV Approved PATRICK LIEBREGT
Smoke Detectors 5/17/2023 Not Ready for Inspection PATRICK LIEBREGT
Final 7/10/2023 Not Ready for Inspection JOEL ORDAZ
MERV13>=Final 7/10/2023 Corrections Issued JOEL ORDAZ
Smoke Detectors 7/10/2023 Approved JOEL ORDAZ
Final 8/17/2023 OK to Issue CofO PATRICK LIEBREGT
MERV13>=Final 8/17/2023 Approved PATRICK LIEBREGT