24050-24052 W HAMLIN ST 91307
Certificate Information: 24050-24052 W HAMLIN ST 91307
- Application / Permit
- 22014-10000-04575
- Plan Check / Job No.
- B22LA18405
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO SINGLE FAMILY DWELLING AT REAR, AND ADD TRELLIS AT REAR (P/BC 2020-006) , AND ADD NEW PORCH AT FRONT. AND CONVERT ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e)
- Permit Issued
- Issued on 11/23/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/2/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/16/2022 | LUKE GONZALES |
| Corrections Issued | 9/17/2022 | LUKE GONZALES |
| Building Plans Picked Up | 9/22/2022 | APPLICANT |
| Applicant returned to address corrections | 10/6/2022 | RACHEL BEYENE |
| Issued | 11/23/2022 | APPLICANT |
| CofO in Progress | 3/20/2023 | JUSTIN HAWLEY |
| Permit Finaled | 5/2/2023 | JOHN JANSON |
| CofO Issued | 5/2/2023 | JOHN JANSON |
| Permit Finaled | 5/2/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/28/2022 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 9/28/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 9/28/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 10/6/2022 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 11/18/2022 | ERNEST TSE |
Contact Information
| Contractor | Cavalier Builders Inc; Lic. No.: 758563-B | 6520 PLATT AVE #732 WEST HILLS, CA 91307 |
| Engineer | Singh,, Jasbir; Lic. No.: C38767 | 16194 EASTRIDGE CT CHINO HILLS, CA 91709 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/2/2022 | Partial Approval | TROY SANDERS |
| Footing/Foundation/Slab | 12/6/2022 | Approved | TROY SANDERS |
| PLUMBING-Rough | 12/6/2022 | Partial Approval | TROY SANDERS |
| Insulation | 12/30/2022 | Approved | TROY SANDERS |
| Drywall Nailing | 1/19/2023 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 1/19/2023 | Approved | TROY SANDERS |
| Green Building Rough | 1/19/2023 | Approved | TROY SANDERS |
| HVAC-Rough | 1/19/2023 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 1/19/2023 | Approved | TROY SANDERS |
| PLUMBING-Rough | 1/19/2023 | Approved | TROY SANDERS |
| Shower Pan | 1/19/2023 | Approved | TROY SANDERS |
| Special/Order Compliance | 1/19/2023 | Partial Inspection | MORRIS JACKSON |
| BUILDING-Rough-Frame | 3/9/2023 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Final | 3/9/2023 | Corrections Issued | DAVID SANDOVAL |
| Final | 3/9/2023 | Corrections Issued | DAVID SANDOVAL |
| Green Building Final | 3/9/2023 | Not Ready for Inspection | DAVID SANDOVAL |
| HVAC-Final | 3/9/2023 | Approved | DAVID SANDOVAL |
| PLUMBING-Final | 3/9/2023 | Approved | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 3/9/2023 | SGSOV Approved | DAVID SANDOVAL |
| Smoke Detectors | 3/9/2023 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Final | 3/20/2023 | Approved | JUSTIN HAWLEY |
| Final | 3/20/2023 | OK to Issue CofO | JUSTIN HAWLEY |
| Green Building Final | 3/20/2023 | Approved | JUSTIN HAWLEY |
| HVAC-Final | 3/20/2023 | Approved | JUSTIN HAWLEY |
| PLUMBING-Final | 3/20/2023 | Approved | JUSTIN HAWLEY |
| Service/Power Release | 3/20/2023 | Approved | JUSTIN HAWLEY |
| Special/Order Compliance | 3/20/2023 | Approved | TROY SANDERS |