2402 1/2 S REDONDO BLVD 90016

Certificate Information: 2402 1/2 S REDONDO BLVD 90016

Application / Permit
22014-10000-04538
Plan Check / Job No.
B22LA18229
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Existing garage conversion to ADU and first and second floor addition to ADU per LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 3/3/2023
Issuing Office
Current Status
CofO Issued on 7/2/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/12/2022 APPLICANT
Assigned to Plan Check Engineer 9/16/2022 FARSHAD ALIMOHAMADI
Corrections Issued 9/16/2022 FARSHAD ALIMOHAMADI
Plan Check Approved 11/9/2022 FARSHAD ALIMOHAMADI
No Progress 11/9/2022 FARSHAD ALIMOHAMADI
Plan Check Approved 11/10/2022 FARSHAD ALIMOHAMADI
Issued 3/3/2023 APPLICANT
CofO in Progress 6/27/2024 JUSTIN HAWLEY
CofO Issued 7/2/2024 DEROLD HAUFF
Permit Finaled 7/2/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/21/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 9/26/2022 CINDY QI
Sewer availability Cleared 9/26/2022 CINDY QI
Low Impact Development Cleared 10/13/2022 LUIS LUVANO
Roof/Waste drainage to street Cleared 10/17/2022 CINDY QI
Construction near power lines Cleared 11/5/2022 RIDWAN HARDY

Contact Information

Contractor Gold Pacific Construction Inc; Lic. No.: 1024672-B 1134 W 68TH ST      LOS ANGELES, CA 90044
Engineer Carrillo,, Jesus Eduardo; Lic. No.: C77737 8207 BROOKGREEN RD      DOWNEY, CA 90240

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/7/2023 Approved CALEB MEISTER
Floor/Roof Diaphrgm/Shear Wall 4/19/2023 Partial Approval MICHAEL LEWIS
Sewer 4/19/2023 Approved MICHAEL LEWIS
Underground Mechanical 4/19/2023 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 4/26/2023 Approved CALEB MEISTER
Service/Power Release 6/12/2023 Not Ready for Inspection CALEB MEISTER
Underground Mechanical 6/27/2023 Partial Approval CALEB MEISTER
Floor/Roof Diaphrgm/Shear Wall 7/17/2023 Partial Approval CALEB MEISTER
Floor/Roof Diaphrgm/Shear Wall 9/6/2023 Approved CALEB MEISTER
ELECTRICAL-Rough 9/26/2023 Approved CALEB MEISTER
Floor/Roof Diaphrgm/Shear Wall 9/26/2023 Approved CALEB MEISTER
PLUMBING-Rough 9/26/2023 Approved CALEB MEISTER
BUILDING-Rough-Frame 10/11/2023 Approved CALEB MEISTER
Green Building Rough 10/11/2023 Not Ready for Inspection CALEB MEISTER
HVAC-Rough 10/11/2023 Approved CALEB MEISTER
MERV13>=Rough 10/11/2023 Approved CALEB MEISTER
Insulation 10/23/2023 Not Ready for Inspection CALEB MEISTER
Interior/Exterior Lathing 10/23/2023 Not Ready for Inspection CALEB MEISTER
Insulation 10/30/2023 Approved BRENDAN MORELLI
Interior/Exterior Lathing 10/30/2023 Partial Approval BRENDAN MORELLI
Shower Pan 10/30/2023 Approved BRENDAN MORELLI
Drywall Nailing 11/17/2023 Approved RONNIE MINDANAO
Interior/Exterior Lathing 11/17/2023 Not Ready for Inspection RONNIE MINDANAO
Green Building Rough 11/30/2023 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 11/30/2023 Approved JUSTIN HAWLEY
Final 6/20/2024 Corrections Issued JUSTIN HAWLEY
Green Building Final 6/20/2024 Not Ready for Inspection JUSTIN HAWLEY
MERV13>=Final 6/20/2024 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 6/20/2024 SGSOV Approved JUSTIN HAWLEY
Smoke Detectors 6/20/2024 Approved JUSTIN HAWLEY
ELECTRICAL-Final 6/27/2024 Approved JUSTIN HAWLEY
Final 6/27/2024 OK to Issue CofO JUSTIN HAWLEY
Green Building Final 6/27/2024 Approved JUSTIN HAWLEY
HVAC-Final 6/27/2024 Approved JUSTIN HAWLEY
PLUMBING-Final 6/27/2024 Approved JUSTIN HAWLEY