16120 W WOODVALE ROAD 91436

Certificate Information: 16120 W WOODVALE ROAD 91436

Application / Permit
22014-10000-04529
Plan Check / Job No.
B22LA18185
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: REMODEL AND ADDITION OF 25'-0" x 10''-4" (N) RECREATION ROOM TO (E) S.F.D., CONVERT A PORTION OF (E) ATTACHED GARAGE TO A (N) RECREATION ROOM AND (N) BATHROOM, ADDITION OF 27'-4" x 2'-0" TO (E) GARAGE, REMODEL TO (E) KITCHEN AND DINING ROOM, AND REPLACE DOOR AND WINDOW. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 8/31/2023
Issuing Office
Current Status
CofO Issued on 4/25/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/12/2022 APPLICANT
Assigned to Plan Check Engineer 9/19/2022 ALFRED RAMIREZ
Corrections Issued 9/20/2022 ALFRED RAMIREZ
Applicant returned to address corrections 10/4/2022 ALFRED RAMIREZ
Plan Check Approved 10/6/2022 ALFRED RAMIREZ
Plan Check Approved 8/29/2023 ALFRED RAMIREZ
Issued 8/31/2023 APPLICANT
CofO in Progress 8/26/2025 THOMAS FINNILA
Permit Finaled 4/25/2026 MICHAEL PELHAM
CofO Issued 4/25/2026 MICHAEL PELHAM
Permit Finaled 4/25/2026 MICHAEL PELHAM

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/21/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 9/22/2022 DAGOVERTO GUERRERO
Grading Pre-Inspection Cleared 9/27/2022 VASIL MIHALEV

Contact Information

Contractor Stevens Mark Construction Co Inc; Lic. No.: 681686-B       ,
Engineer Le,, Thang Huu; Lic. No.: NA4978       ,

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/19/2023 Partial Approval VINCENT HANLEY
Deputy Drilled-In Anchors 10/31/2023 Partial Approval VINCENT HANLEY
Footing/Foundation/Slab 11/1/2023 Partial Approval VINCENT HANLEY
Footing/Foundation/Slab 11/14/2023 Approved VINCENT HANLEY
PLUMBING-Rough 11/28/2023 Partial Approval SEAN HAUPT
Footing/Foundation/Slab 12/5/2023 Approved VINCENT HANLEY
BUILDING-Rough-Frame 12/26/2023 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 12/26/2023 Partial Approval VINCENT HANLEY
Green Building Rough 12/26/2023 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 2/21/2024 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 3/12/2024 Partial Approval VINCENT HANLEY
PLUMBING-Rough 3/12/2024 Partial Approval VINCENT HANLEY
Shower Pan 3/12/2024 Approved VINCENT HANLEY
Interior/Exterior Lathing 4/2/2024 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 5/14/2024 Not Ready for Inspection THOMAS FINNILA
HVAC-Rough 5/14/2024 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 5/14/2024 Approved THOMAS FINNILA
Deputy Wood Construction 5/16/2024 Conditional Approval THOMAS FINNILA
ELECTRICAL-Rough 5/20/2024 Approved JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 5/20/2024 Approved JEFFREY BULL
Green Building Rough 5/20/2024 Not Ready for Inspection JEFFREY BULL
HVAC-Rough 5/20/2024 Approved JEFFREY BULL
PLUMBING-Rough 5/20/2024 Approved JEFFREY BULL
Interior/Exterior Lathing 5/23/2024 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 5/28/2024 Corrections Issued THOMAS FINNILA
Green Building Rough 5/28/2024 Approved THOMAS FINNILA
Interior/Exterior Lathing 5/28/2024 Corrections Issued THOMAS FINNILA
Insulation 6/3/2024 Corrections Issued THOMAS FINNILA
BUILDING-Rough-Frame 6/6/2024 Approved THOMAS FINNILA
Drywall Nailing 6/6/2024 Approved THOMAS FINNILA
Interior/Exterior Lathing 7/18/2024 Partial Approval MORRIS JACKSON
Interior/Exterior Lathing 8/1/2024 Partial Approval MORRIS JACKSON
Interior/Exterior Lathing 8/23/2024 Approved MORRIS JACKSON
Final 11/27/2024 Not Ready for Inspection THOMAS FINNILA
Green Building Final 11/27/2024 Not Ready for Inspection THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 11/27/2024 SGSOV Not Ready THOMAS FINNILA
Smoke Detectors 11/27/2024 Not Ready for Inspection THOMAS FINNILA
Final 1/8/2025 Not Ready for Inspection THOMAS FINNILA
Green Building Final 1/8/2025 Not Ready for Inspection THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 1/8/2025 SGSOV Not Ready THOMAS FINNILA
Smoke Detectors 1/8/2025 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Final 2/3/2025 Approved JOHN COLEMAN
Final 2/3/2025 Corrections Issued JOHN COLEMAN
Green Building Final 2/3/2025 Partial Inspection JOHN COLEMAN
PLUMBING-Final 2/3/2025 Approved JOHN COLEMAN
SGSOV-Seismic Gas S/O Valve 2/3/2025 SGSOV Gas Company JOHN COLEMAN
Smoke Detectors 2/3/2025 Approved JOHN COLEMAN
ELECTRICAL-Final 3/27/2025 Approved THOMAS FINNILA
Final 3/27/2025 Corrections Issued THOMAS FINNILA
Green Building Final 3/27/2025 Approved THOMAS FINNILA
HVAC-Final 3/27/2025 Corrections Issued THOMAS FINNILA
Final 6/27/2025 Partial Approval THOMAS FINNILA
Final 8/21/2025 OK to Issue CofO THOMAS FINNILA