6014 W 82ND ST 90045
Certificate Information: 6014 W 82ND ST 90045
- Application / Permit
- 22014-10000-04526
- Plan Check / Job No.
- B22LA18175
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND INTERIOR REMODEL TO (E) SFD
- Permit Issued
- Issued on 4/5/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/15/2022 | KHUONG TRUONG |
| Corrections Issued | 9/17/2022 | KHUONG TRUONG |
| Building Plans Picked Up | 9/23/2022 | APPLICANT |
| Plan Check Approved | 10/25/2022 | FERNANDO FLORES |
| Issued | 4/5/2023 | APPLICANT |
| CofO in Progress | 12/13/2023 | BOBBY KEY |
| Permit Finaled | 12/14/2023 | DANIEL ORRANTE |
| CofO Issued | 12/14/2023 | DANIEL ORRANTE |
| Permit Finaled | 12/14/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/20/2022 | ANTHONY MAINEZ |
| Roof/Waste drainage to street | Cleared | 10/20/2022 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 10/20/2022 | ANTHONY MAINEZ |
Contact Information
| Contractor | Ramos Manuel; Lic. No.: 937994-B | 29021 BOUQUET CANYON RD SP 341 SANTA CLARITA, CA 91390 |
| Engineer | Hwang,, Junho; Lic. No.: S5592 | 815 FAIRVIEW AVE #205 SOUTH PASADENA, CA 91030 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/24/2023 | Conditional Approval | BOBBY KEY |
| Footing/Foundation/Slab | 4/26/2023 | Conditional Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/7/2023 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 6/7/2023 | Approved | BOBBY KEY |
| PLUMBING-Rough | 6/7/2023 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Rough | 6/9/2023 | Corrections Issued | BOBBY KEY |
| HVAC-Rough | 6/9/2023 | Approved | BOBBY KEY |
| PLUMBING-Rough | 6/9/2023 | Approved | BOBBY KEY |
| Shower Pan | 6/9/2023 | Partial Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 6/14/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 6/14/2023 | Approved | BOBBY KEY |
| Green Building Rough | 6/14/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 6/14/2023 | Partial Approval | BOBBY KEY |
| Insulation | 6/20/2023 | Approved | BOBBY KEY |
| Drywall Nailing | 6/30/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 9/27/2023 | Corrections Issued | BOBBY KEY |
| Final | 9/27/2023 | Corrections Issued | BOBBY KEY |
| Green Building Final | 9/27/2023 | Approved | BOBBY KEY |
| HVAC-Final | 9/27/2023 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 9/27/2023 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 9/27/2023 | SGSOV Not Ready | BOBBY KEY |
| Smoke Detectors | 9/27/2023 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 11/28/2023 | SGSOV Not Ready | BOBBY KEY |
| ELECTRICAL-Final | 12/13/2023 | Approved | BOBBY KEY |
| Final | 12/13/2023 | OK to Issue CofO | BOBBY KEY |
| HVAC-Final | 12/13/2023 | Approved | BOBBY KEY |
| PLUMBING-Final | 12/13/2023 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 12/13/2023 | SGSOV Approved | BOBBY KEY |