6014 W 82ND ST 90045

Certificate Information: 6014 W 82ND ST 90045

Application / Permit
22014-10000-04526
Plan Check / Job No.
B22LA18175
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND INTERIOR REMODEL TO (E) SFD
Permit Issued
Issued on 4/5/2023
Issuing Office
Metro
Current Status
CofO Issued on 12/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/9/2022 APPLICANT
Assigned to Plan Check Engineer 9/15/2022 KHUONG TRUONG
Corrections Issued 9/17/2022 KHUONG TRUONG
Building Plans Picked Up 9/23/2022 APPLICANT
Plan Check Approved 10/25/2022 FERNANDO FLORES
Issued 4/5/2023 APPLICANT
CofO in Progress 12/13/2023 BOBBY KEY
Permit Finaled 12/14/2023 DANIEL ORRANTE
CofO Issued 12/14/2023 DANIEL ORRANTE
Permit Finaled 12/14/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/20/2022 ANTHONY MAINEZ
Roof/Waste drainage to street Cleared 10/20/2022 ANTHONY MAINEZ
Sewer availability Cleared 10/20/2022 ANTHONY MAINEZ

Contact Information

Contractor Ramos Manuel; Lic. No.: 937994-B 29021 BOUQUET CANYON RD SP 341      SANTA CLARITA, CA 91390
Engineer Hwang,, Junho; Lic. No.: S5592 815 FAIRVIEW AVE #205      SOUTH PASADENA, CA 91030

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/24/2023 Conditional Approval BOBBY KEY
Footing/Foundation/Slab 4/26/2023 Conditional Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 6/7/2023 Approved BOBBY KEY
Footing/Foundation/Slab 6/7/2023 Approved BOBBY KEY
PLUMBING-Rough 6/7/2023 Partial Approval BOBBY KEY
ELECTRICAL-Rough 6/9/2023 Corrections Issued BOBBY KEY
HVAC-Rough 6/9/2023 Approved BOBBY KEY
PLUMBING-Rough 6/9/2023 Approved BOBBY KEY
Shower Pan 6/9/2023 Partial Approval BOBBY KEY
BUILDING-Rough-Frame 6/14/2023 Approved BOBBY KEY
ELECTRICAL-Rough 6/14/2023 Approved BOBBY KEY
Green Building Rough 6/14/2023 Approved BOBBY KEY
Interior/Exterior Lathing 6/14/2023 Partial Approval BOBBY KEY
Insulation 6/20/2023 Approved BOBBY KEY
Drywall Nailing 6/30/2023 Approved BOBBY KEY
ELECTRICAL-Final 9/27/2023 Corrections Issued BOBBY KEY
Final 9/27/2023 Corrections Issued BOBBY KEY
Green Building Final 9/27/2023 Approved BOBBY KEY
HVAC-Final 9/27/2023 Corrections Issued BOBBY KEY
PLUMBING-Final 9/27/2023 Corrections Issued BOBBY KEY
SGSOV-Seismic Gas S/O Valve 9/27/2023 SGSOV Not Ready BOBBY KEY
Smoke Detectors 9/27/2023 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 11/28/2023 SGSOV Not Ready BOBBY KEY
ELECTRICAL-Final 12/13/2023 Approved BOBBY KEY
Final 12/13/2023 OK to Issue CofO BOBBY KEY
HVAC-Final 12/13/2023 Approved BOBBY KEY
PLUMBING-Final 12/13/2023 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 12/13/2023 SGSOV Approved BOBBY KEY