3896 N FILION ST 90065
Certificate Information: 3896 N FILION ST 90065
- Application / Permit
- 22014-10000-04516
- Plan Check / Job No.
- B22LA18142
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior remodel of a 3-story SFD. (E) dwelling is 3bed/2bath, proposed dwelling is 5bed/2 1/2 bath. Enclosing two small areas under the (E) roofline to create a laundry room (41SF) and increase the size of the entry foyer (18SF). Major remodel.
- Permit Issued
- Issued on 11/28/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/29/2022 | JAD BASMA |
| Corrections Issued | 10/7/2022 | JAD BASMA |
| Quality Review Completed | 10/17/2022 | TEODORO DIAZ RODRIGUEZ |
| Plan Check Approved | 11/23/2022 | JAD BASMA |
| Issued | 11/28/2022 | APPLICANT |
| CofO in Progress | 11/15/2023 | HAMIK HARTOUNIAN |
| Permit Finaled | 11/17/2023 | DEROLD HAUFF |
| CofO Issued | 11/17/2023 | DEROLD HAUFF |
| Permit Finaled | 11/17/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/17/2022 | ALEXANDER HELFER |
| Eng Process Fee Ord 176,300 | Cleared | 11/4/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 11/4/2022 | AMAAN MALIK |
| Supp. Use District POD/CDO/TDO | Cleared | 11/7/2022 | NASHYA JENSEN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/6/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 3/3/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 3/3/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 4/10/2023 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Rough | 4/10/2023 | Approved | SCOTT FINNILA |
| HVAC-Rough | 4/10/2023 | Corrections Issued | SCOTT FINNILA |
| PLUMBING-Rough | 4/10/2023 | Approved | SCOTT FINNILA |
| Pre-Inspection | 4/10/2023 | Partial Inspection | SCOTT FINNILA |
| ELECTRICAL-Rough | 4/11/2023 | Partial Inspection | SCOTT FINNILA |
| HVAC-Rough | 4/11/2023 | Not Ready for Inspection | SCOTT FINNILA |
| PLUMBING-Rough | 4/11/2023 | Partial Inspection | SCOTT FINNILA |
| Pre-Inspection | 4/11/2023 | Not Ready for Inspection | SCOTT FINNILA |
| Interior/Exterior Lathing | 4/26/2023 | Partial Approval | JEFFREY MEAD |
| BUILDING-Rough-Frame | 5/3/2023 | Approved | JEFFREY MEAD |
| Green Building Rough | 5/3/2023 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 5/10/2023 | Conditional Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2023 | Approved | SCOTT FINNILA |
| Shower Pan | 5/10/2023 | Approved | SCOTT FINNILA |
| Interior/Exterior Lathing | 5/15/2023 | Approved | SCOTT FINNILA |
| BUILDING-Rough-Frame | 5/30/2023 | Approved | SCOTT FINNILA |
| Insulation | 5/30/2023 | Conditional Approval | SCOTT FINNILA |
| Insulation | 5/31/2023 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 6/8/2023 | Approved | HAMIK HARTOUNIAN |
| Insulation | 6/8/2023 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 10/12/2023 | Approved | HAMIK HARTOUNIAN |
| Final | 10/12/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 10/12/2023 | Approved | HAMIK HARTOUNIAN |
| HVAC-Final | 10/12/2023 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Final | 10/12/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 10/12/2023 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 10/12/2023 | Approved | HAMIK HARTOUNIAN |
| Final | 11/7/2023 | OK to Issue CofO | HAMIK HARTOUNIAN |