332 S MANSFIELD AVE 90036

Certificate Information: 332 S MANSFIELD AVE 90036

Application / Permit
22014-10000-04488
Plan Check / Job No.
B22LA18021
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ADU WITH ADDITION per state law
Permit Issued
Issued on 3/1/2023
Issuing Office
Metro
Current Status
Issued on 3/1/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/8/2022 APPLICANT
Assigned to Plan Check Engineer 9/12/2022 AUNG SOE
Corrections Issued 9/19/2022 AUNG SOE
Building Plans Picked Up 9/23/2022 APPLICANT
Applicant returned to address corrections 12/14/2022 MINA HABILI
Plan Check Approved 1/9/2023 MINA HABILI
Plan Check Approved 2/1/2023 MINA HABILI
Issued 3/1/2023 APPLICANT

Permit Application Clearance Information

CPC Cleared 9/27/2022 DANIEL CORONADO
Address approval Cleared 10/3/2022 STEVE MELGAR
Roof/Waste drainage to street Cleared 10/3/2022 STEVE MELGAR
Sewer availability Cleared 10/3/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 10/5/2022 STEVE MELGAR
Construction near power lines Cleared 11/30/2022 RIDWAN HARDY

Contact Information

Contractor Luxe Home Solutions Inc; Lic. No.: 1098199-B 329 N WETHERLY DRIVE   SUITE 205    BEVERLY HILLS, CA 90211
Engineer Ramirez, Cid, Jose Carlos; Lic. No.: C91046 5164 N RATON CIR      LONG BEACH, CA 90807

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/13/2023 Corrections Issued RICHARD DOCKUS
PLUMBING-Rough 4/17/2023 Corrections Issued RICHARD DOCKUS
PLUMBING-Rough 5/2/2023 Corrections Issued RICHARD DOCKUS
PLUMBING-Rough 5/9/2023 Partial Approval RICHARD DOCKUS
Excavation/Setback/Form/Re-Bar 5/15/2023 Approved RICHARD DOCKUS
Footing/Foundation/Slab 5/15/2023 Approved RICHARD DOCKUS
METHANE-Barrier 5/15/2023 Approved RICHARD DOCKUS
METHANE-Subgrade 5/15/2023 Approved RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 6/1/2023 Partial Approval RICHARD DOCKUS
BUILDING-Rough-Frame 6/14/2023 Partial Approval RICHARD DOCKUS
ELECTRICAL-Rough 7/19/2023 Corrections Issued JEFFREY MEAD
HVAC-Rough 7/19/2023 Corrections Issued JEFFREY MEAD
PLUMBING-Rough 7/19/2023 Corrections Issued JEFFREY MEAD
BUILDING-Rough-Frame 7/24/2023 Partial Approval SCOTT FINNILA
ELECTRICAL-Rough 7/24/2023 Corrections Issued SCOTT FINNILA
Green Building Rough 7/24/2023 Partial Approval SCOTT FINNILA
HVAC-Rough 7/24/2023 Approved SCOTT FINNILA
METHANE-Rough 7/24/2023 Conditional Approval SCOTT FINNILA
PLUMBING-Rough 7/24/2023 Approved SCOTT FINNILA
Wood Frame 7/24/2023 Partial Approval SCOTT FINNILA
Sewer 7/31/2023 Partial Approval LILIANA PORTILLO
ELECTRICAL-Rough 8/10/2023 Partial Approval JOSEPH MCGARRY
Interior/Exterior Lathing 8/14/2023 Partial Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 8/18/2023 Conditional Approval JOSEPH MCGARRY
ELECTRICAL-Rough 8/18/2023 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 8/18/2023 Partial Approval JOSEPH MCGARRY
Insulation 8/25/2023 Approved ROY SPAULDING
Drywall Nailing 8/30/2023 Partial Approval ROY SPAULDING
Drywall Nailing 10/10/2023 Approved RICHARD DOCKUS
Shower Pan 10/10/2023 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 12/8/2023 Approved RICHARD DOCKUS
Final 12/8/2023 Corrections Issued RICHARD DOCKUS
Green Building Final 12/8/2023 Approved RICHARD DOCKUS
Green Building Rough 12/8/2023 Approved RICHARD DOCKUS
METHANE-Final 12/8/2023 Approved RICHARD DOCKUS
METHANE-Rough 12/8/2023 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 12/8/2023 SGSOV Approved RICHARD DOCKUS
Smoke Detectors 12/8/2023 Approved RICHARD DOCKUS
Final 12/15/2023 Conditional Approval RICHARD DOCKUS
Final 5/30/2025 Not Ready for Inspection RAUL BARAJAS