438 S SALTAIR AVE 90049

Certificate Information: 438 S SALTAIR AVE 90049

Application / Permit
22014-10000-04487
Plan Check / Job No.
B22LA18009
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1 of 3 New interior remodel with addition to basement (605 SF), first floor (237 SF), and second floor (106 SF). Garage alteration to an (E) 2-story SFD.
Permit Issued
Issued on 8/15/2023
Issuing Office
West Los Angeles
Current Status
Issued on 8/15/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/8/2022 APPLICANT
Assigned to Plan Check Engineer 9/8/2022 VARAND SARKISIAN
Corrections Issued 9/13/2022 VARAND SARKISIAN
Quality Review Completed 9/15/2022 HANS SANTIAGO
Applicant returned to address corrections 12/16/2022 VARAND SARKISIAN
Plan Check Approved 3/16/2023 VARAND SARKISIAN
Issued 8/15/2023 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/11/2023 JENSON LEE
Sewer availability Cleared 1/11/2023 JENSON LEE
Specific Plan Cleared 1/20/2023 JOSHUA JONES
Hydrant and Access approval Cleared 1/22/2023 MATTHEW CRAIG
Low Impact Development Cleared 2/15/2023 CHRIS VONG
Roof/Waste drainage to street Cleared 2/24/2023 JENSON LEE
GPI Written Notices Cleared 3/16/2023 ANDREW SANTIAGO
Grading Pre-Inspection Cleared 3/16/2023 ANDREW SANTIAGO

Contact Information

Contractor Valle/Reinis Builders Inc; Lic. No.: 839178-B 11661 SAN VICENTE BLVD STE 302      LOS ANGELES, CA 90049
Engineer Ruan,, Federico R; Lic. No.: S6689 553 S OAK KNOLL AVE      PASADENA, CA 91101

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/25/2023 Partial Inspection KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 11/22/2023 Partial Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 12/13/2023 Partial Approval ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 12/28/2023 Partial Approval ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 1/11/2024 Partial Approval ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 1/18/2024 Partial Approval KENNETH NAGLE
Excavation/Setback/Form/Re-Bar 1/30/2024 Not Ready for Inspection ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 4/2/2024 Partial Approval ARAM AVEDISIAN
Footing/Foundation/Slab 5/1/2024 Partial Approval ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 5/10/2024 Partial Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 5/17/2024 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 5/31/2024 Partial Approval ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 6/11/2024 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 6/11/2024 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 6/14/2024 Partial Approval ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 6/24/2024 Partial Approval ARAM AVEDISIAN
Underground Mechanical 7/3/2024 Partial Approval KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 7/9/2024 Partial Approval CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 7/22/2024 Partial Approval ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 8/1/2024 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 8/28/2024 Partial Approval JESUS RODRIGUEZ
HVAC-Rough 8/29/2024 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 8/30/2024 Partial Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 9/17/2024 Corrections Issued JESUS RODRIGUEZ
Shower Pan 9/26/2024 Approved REGINA MENDEZ
ELECTRICAL-Rough 10/10/2024 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Rough 10/17/2024 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 10/17/2024 Approved JESUS RODRIGUEZ
Green Building Rough 10/17/2024 Not Ready for Inspection JESUS RODRIGUEZ
Interior/Exterior Lathing 10/29/2024 Corrections Issued SEAN HAUPT
Interior/Exterior Lathing 10/31/2024 Partial Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 11/22/2024 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 12/17/2024 Partial Approval JESUS RODRIGUEZ
BUILDING-Rough-Frame 1/6/2025 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 1/6/2025 Approved JESUS RODRIGUEZ
Green Building Rough 1/6/2025 Approved JESUS RODRIGUEZ
Insulation 1/6/2025 Approved JESUS RODRIGUEZ
PLUMBING-Rough 1/6/2025 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 1/24/2025 Approved JESUS RODRIGUEZ
Drywall Nailing 2/3/2025 Partial Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 4/3/2025 Partial Inspection HERBERT GIRON
Drywall Nailing 5/14/2025 Not Ready for Inspection HERBERT GIRON
Sewer 6/12/2025 Partial Approval ARAM AVEDISIAN
Underground Mechanical 6/20/2025 Partial Approval HERBERT GIRON
Underground Mechanical 7/17/2025 Corrections Issued HERBERT GIRON
Underground Mechanical 7/21/2025 Partial Approval MICHAEL ALLEN
Underground Mechanical 7/31/2025 Partial Approval HERBERT GIRON
Underground Mechanical 9/10/2025 Corrections Issued HERBERT GIRON
Underground Mechanical 9/19/2025 Partial Approval HERBERT GIRON
Underground Mechanical 9/25/2025 Partial Approval HERBERT GIRON
Underground Mechanical 9/30/2025 Partial Approval HERBERT GIRON
Underground Mechanical 10/7/2025 Partial Approval HERBERT GIRON
Underground Mechanical 10/10/2025 Partial Approval TEMISTOCLES CAAL
Underground Mechanical 10/24/2025 Partial Approval HERBERT GIRON
Underground Mechanical 10/31/2025 Partial Approval HERBERT GIRON
Underground Mechanical 11/17/2025 Partial Approval HERBERT GIRON
Drywall Nailing 11/21/2025 Approved HERBERT GIRON
Gas Test 12/2/2025 Approved HERBERT GIRON
Underground Mechanical 1/21/2026 Approved HERBERT GIRON
PLUMBING-Final 2/9/2026 Corrections Issued HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 2/9/2026 SGSOV Approved HERBERT GIRON
PLUMBING-Final 3/11/2026 Approved KEVIN SARGSYAN
HVAC-Final 4/13/2026 Corrections Issued DANIEL VERA
HVAC-Final 4/20/2026 Approved KEVIN SARGSYAN
ELECTRICAL-Final 4/27/2026 Approved EVAN COOPER
Service/Power Release 4/27/2026 Approved EVAN COOPER
Underground Mechanical 5/21/2026 Approved KEVIN SARGSYAN