731-731 1/2 E 33RD ST 90011

Certificate Information: 731-731 1/2 E 33RD ST 90011

Application / Permit
22014-10000-04474
Plan Check / Job No.
B22LA17904
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
FIRE DAMAGE REPAIR & 2ND STORY ADDITION TO (E) DUPLEX
Permit Issued
Issued on 9/26/2023
Issuing Office
Metro
Current Status
CofO Issued on 6/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/7/2022 APPLICANT
Assigned to Plan Check Engineer 9/22/2022 LAMAR DAVIS
Corrections Issued 9/29/2022 LAMAR DAVIS
Quality Review Completed 10/5/2022 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 10/7/2022 APPLICANT
Plan Check Approved 9/15/2023 MARCELA FRANQUEZ
Issued 9/26/2023 APPLICANT
CofO in Progress 6/14/2025 ALEJANDRO DE ARTOLA
Permit Finaled 6/17/2025 DEROLD HAUFF
CofO Issued 6/17/2025 DEROLD HAUFF
Permit Finaled 6/17/2025 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/1/2022 AMAAN MALIK
Sewer availability Cleared 11/1/2022 AMAAN MALIK
Low Impact Development Cleared 6/9/2023 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 6/12/2023 ADRIAN SANCHEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Kim,, Hong Kook; Lic. No.: C64529 3600 WILSHIRE BLVD STE 1903      LOS ANGELES, CA 90010

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/6/2023 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 11/6/2023 Corrections Issued ALEJANDRO DE ARTOLA
Deputy Drilled-In Anchors 11/7/2023 Conditional Approval ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 1/10/2024 Corrections Issued ALEJANDRO DE ARTOLA
Sewer 1/10/2024 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 1/16/2024 Corrections Issued BRENDAN MORELLI
PLUMBING-Rough 1/16/2024 Partial Approval BRENDAN MORELLI
Sewer 1/16/2024 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 2/26/2024 Corrections Issued ALEJANDRO DE ARTOLA
Sewer 2/26/2024 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 2/29/2024 Corrections Issued ANTHONY EGSON
Green Building Rough 2/29/2024 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 2/29/2024 Not Ready for Inspection ANTHONY EGSON
BUILDING-Rough-Frame 3/5/2024 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 3/5/2024 Partial Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 3/15/2024 Partial Approval ALEJANDRO DE ARTOLA
Insulation 3/15/2024 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 3/19/2024 Partial Approval ALEJANDRO DE ARTOLA
Green Building Rough 3/19/2024 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 4/8/2024 Partial Approval ALEJANDRO DE ARTOLA
Green Building Rough 4/8/2024 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 6/27/2024 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 6/27/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 6/27/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 7/2/2024 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 7/2/2024 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 7/2/2024 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 7/26/2024 Corrections Issued ALEJANDRO DE ARTOLA
Deputy Wood Construction 7/29/2024 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 7/29/2024 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 7/31/2024 Partial Approval ALEJANDRO DE ARTOLA
Wood Frame 8/7/2024 Corrections Issued ALEJANDRO DE ARTOLA
Wood Frame 8/12/2024 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 8/19/2024 Approved ALEJANDRO DE ARTOLA
Green Building Rough 8/19/2024 Approved ALEJANDRO DE ARTOLA
Insulation 8/19/2024 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 9/4/2024 Corrections Issued ALEJANDRO DE ARTOLA
Drywall Nailing 9/16/2024 Approved SABAS ALONSO
Interior/Exterior Lathing 10/4/2024 Approved JOSH MEISTER
Service/Power Release 12/13/2024 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 12/13/2024 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 12/16/2024 No Access for Inspection SABAS ALONSO
Sewer 1/14/2025 Approved MICHAEL LEWIS
ELECTRICAL-Final 3/7/2025 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 3/7/2025 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 3/7/2025 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 5/14/2025 Approved ALEJANDRO DE ARTOLA
Final 5/14/2025 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 5/14/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 5/14/2025 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 5/15/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 5/15/2025 Approved ALEJANDRO DE ARTOLA
Green Building Final 5/28/2025 Approved ALEJANDRO DE ARTOLA
HVAC-Final 5/28/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 5/30/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 5/30/2025 Approved ALEJANDRO DE ARTOLA
Final 6/10/2025 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 6/10/2025 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 6/10/2025 SGSOV Approved ALEJANDRO DE ARTOLA
Final 6/11/2025 OK to Issue CofO ALEJANDRO DE ARTOLA