3136 S BENTLEY AVE 90034
Certificate Information: 3136 S BENTLEY AVE 90034
- Application / Permit
- 22014-10000-04472
- Plan Check / Job No.
- B22LA17900
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL OF EXISTING SINGLE FAMILY RESIDENCE WITH ADDITION 1 OF 2
- Permit Issued
- Issued on 1/11/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/22/2022 | CRYSTEL MAALOUF |
| Corrections Issued | 10/3/2022 | CRYSTEL MAALOUF |
| Quality Review Completed | 10/12/2022 | FARUK SEZER |
| Building Plans Picked Up | 10/14/2022 | APPLICANT |
| Applicant returned to address corrections | 11/1/2022 | CRYSTEL MAALOUF |
| Plan Check Approved | 12/29/2022 | CRYSTEL MAALOUF |
| Issued | 1/11/2023 | APPLICANT |
| CofO in Progress | 7/13/2023 | JESUS PINEDA |
| Permit Finaled | 7/24/2023 | DANIEL ORRANTE |
| CofO Issued | 7/24/2023 | DANIEL ORRANTE |
| Permit Finaled | 7/24/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Sewer availability | Cleared | 10/17/2022 | ANTHONY MAINEZ |
| Grading Pre-Inspection | Cleared | 10/18/2022 | KIRK LINKLATER |
| Specific Plan | Cleared | 10/18/2022 | ROBERT SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/19/2022 | ANTHONY MAINEZ |
| Roof/Waste drainage to street | Cleared | 10/19/2022 | ANTHONY MAINEZ |
| GPI Written Notices | Cleared | 11/9/2022 | CRYSTEL MAALOUF |
Contact Information
| Architect | Sacre,, Ramzi; Lic. No.: C35009 | 3604 WESTWOOD BLVD #101 LOS ANGELES, CA 90034 |
| Contractor | Owner-Builder | , |
| Engineer | Dass,, Praveen Kumar; Lic. No.: C74200 | 1945 SHERINGTON PLACE G308 NEWPORT BEACH, CA 92663 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/17/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 1/19/2023 | Approved | JOHNNY MIRANDA |
| Underground Mechanical | 2/23/2023 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2023 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2023 | Partial Approval | JOHNNY MIRANDA |
| PLUMBING-Rough | 3/10/2023 | Conditional Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 3/16/2023 | Partial Approval | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 3/24/2023 | Partial Approval | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 3/24/2023 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 3/24/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| HVAC-Rough | 3/24/2023 | Corrections Issued | JOHNNY MIRANDA |
| MERV13>=Rough | 3/24/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 3/30/2023 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 3/30/2023 | Approved | JOHNNY MIRANDA |
| HVAC-Rough | 3/30/2023 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 3/30/2023 | Partial Approval | JOHNNY MIRANDA |
| MERV13>=Rough | 3/30/2023 | Approved | JOHNNY MIRANDA |
| Insulation | 4/4/2023 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 4/10/2023 | Corrections Issued | DAVID FEILER |
| Drywall Nailing | 4/13/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 4/13/2023 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 5/1/2023 | Corrections Issued | HERBERT GIRON |
| Interior/Exterior Lathing | 5/4/2023 | Corrections Issued | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 5/8/2023 | Approved | ASHLEY THOMPSON |
| Shower Pan | 5/8/2023 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 7/7/2023 | Approved | JESUS PINEDA |
| Final | 7/7/2023 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 7/7/2023 | Approved | JESUS PINEDA |
| HVAC-Final | 7/7/2023 | Corrections Issued | JESUS PINEDA |
| MERV13>=Final | 7/7/2023 | Approved | JESUS PINEDA |
| PLUMBING-Final | 7/7/2023 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 7/7/2023 | SGSOV Approved | JESUS PINEDA |
| Smoke Detectors | 7/7/2023 | Approved | JESUS PINEDA |
| Final | 7/12/2023 | OK to Issue CofO | JESUS PINEDA |
| HVAC-Final | 7/12/2023 | Approved | JESUS PINEDA |