1156 S HIGHLAND AVE 90019
Certificate Information: 1156 S HIGHLAND AVE 90019
- Application / Permit
- 22014-10000-04468
- Plan Check / Job No.
- B22LA17883
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- EPLAN; INT AND EXT REMODEL OF (E) DUPLEX AND 26 SF OF PORCH ENCLOSED IN THE BACK
- Permit Issued
- Issued on 4/17/2023
- Issuing Office
- Current Status
- Permit Finaled on 10/26/2023
Permit Application Status History
| Submitted | 9/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/8/2022 | ALEC MOUSAKHANIAN |
| Corrections Issued | 9/9/2022 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 4/15/2023 | MOHAMMAD ESMAILI |
| Issued | 4/17/2023 | APPLICANT |
| Permit Finaled | 10/26/2023 | JUSTIN HAWLEY |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/15/2022 | TREVOR QUAN |
| Sewer availability | Cleared | 9/15/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 9/19/2022 | TREVOR QUAN |
| Demo/Removal of Rental Units | Cleared | 11/30/2022 | MICHELLE MATHEWS |
| Tenant Habitability Plan | Cleared | 11/30/2022 | MICHAEL SOTO |
| Abandoned oil well | Cleared | 12/2/2022 | GILBERT URREA |
| Address approval | Cleared | 4/15/2023 | FADI ABBOUD |
Contact Information
| Contractor | Rebuilt Homes Inc; Lic. No.: 1063540-B | , |
| Contractor | Rebuilt; Lic. No.: 1063540-B | , |
| Engineer | Gonzalez,, Felix Bolivar; Lic. No.: NA64738 | , |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/19/2023 | Corrections Issued | STUART CHAPMAN |
| Footing/Foundation/Slab | 4/25/2023 | Approved | STUART CHAPMAN |
| ELECTRICAL-Rough | 6/6/2023 | Approved | RICHARD DOCKUS |
| METHANE-Rough | 6/6/2023 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 6/6/2023 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 6/14/2023 | Partial Approval | RICHARD DOCKUS |
| HVAC-Rough | 6/14/2023 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 6/20/2023 | Partial Approval | RICHARD DOCKUS |
| Interior/Exterior Lathing | 6/26/2023 | Partial Approval | RICHARD DOCKUS |
| Insulation | 7/3/2023 | Approved | RICHARD DOCKUS |
| Drywall Nailing | 7/10/2023 | Approved | RICHARD DOCKUS |
| Shower Pan | 8/3/2023 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 8/9/2023 | Partial Approval | LILIANA PORTILLO |
| Interior/Exterior Lathing | 8/11/2023 | Partial Approval | STUART CHAPMAN |
| Interior/Exterior Lathing | 8/16/2023 | Approved | LILIANA PORTILLO |
| Gas Test | 9/25/2023 | Not Ready for Inspection | RICHARD DOCKUS |
| Gas Test | 9/28/2023 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 10/16/2023 | Approved | RICHARD DOCKUS |
| Green Building Final | 10/16/2023 | Approved | RICHARD DOCKUS |
| Green Building Rough | 10/16/2023 | Approved | RICHARD DOCKUS |
| PLUMBING-Final | 10/16/2023 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 10/16/2023 | SGSOV Not Ready | RICHARD DOCKUS |
| Smoke Detectors | 10/16/2023 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Final | 10/18/2023 | Approved | RICHARD DOCKUS |
| HVAC-Final | 10/18/2023 | Corrections Issued | RICHARD DOCKUS |
| Final | 10/24/2023 | Not Ready for Inspection | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 10/24/2023 | SGSOV Approved | RICHARD DOCKUS |
| ELECTRICAL-Final | 10/26/2023 | Approved | JUSTIN HAWLEY |
| Final | 10/26/2023 | Permit Finaled | JUSTIN HAWLEY |
| HVAC-Final | 10/26/2023 | Approved | JUSTIN HAWLEY |
| PLUMBING-Final | 10/26/2023 | Approved | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 10/26/2023 | SGSOV Approved | JUSTIN HAWLEY |