2437 S COCHRAN AVE 90016
Certificate Information: 2437 S COCHRAN AVE 90016
- Application / Permit
- 22014-10000-04463
- Plan Check / Job No.
- B22LA17855
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: 16'6" X 20'6" 2 STORY ADDITION TO AND CONVERSION OF (E) 18' X 18' DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 3/6/2023
- Issuing Office
- Current Status
- CofO Issued on 3/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/13/2022 | OMAR GARNICA |
| Corrections Issued | 9/14/2022 | OMAR GARNICA |
| Plan Check Approved | 11/10/2022 | KEVIN MORALES |
| Issued | 3/6/2023 | APPLICANT |
| CofO in Progress | 9/5/2024 | ARTHUR NEGRETE |
| Permit Finaled | 3/30/2025 | DEROLD HAUFF |
| CofO Issued | 3/30/2025 | DEROLD HAUFF |
| Permit Finaled | 3/30/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/23/2022 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 9/23/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 10/5/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 10/5/2022 | STEVE MELGAR |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: NA91046 | , |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 11/22/2023 | Corrections Issued | DAVID FEILER |
| Green Building Rough | 11/22/2023 | Not Ready for Inspection | DAVID FEILER |
| MERV13>=Rough | 11/22/2023 | Not Ready for Inspection | DAVID FEILER |
| Interior/Exterior Lathing | 3/5/2024 | Partial Approval | STUART CHAPMAN |
| PLUMBING-Rough | 3/13/2024 | Not Ready for Inspection | STUART CHAPMAN |
| BUILDING-Rough-Frame | 3/14/2024 | Approved | STUART CHAPMAN |
| ELECTRICAL-Rough | 3/14/2024 | Approved | STUART CHAPMAN |
| Green Building Rough | 3/14/2024 | Approved | STUART CHAPMAN |
| HVAC-Rough | 3/14/2024 | Approved | STUART CHAPMAN |
| MERV13>=Rough | 3/14/2024 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 3/14/2024 | Approved | STUART CHAPMAN |
| Insulation | 4/1/2024 | Corrections Issued | STUART CHAPMAN |
| Drywall Nailing | 4/19/2024 | Approved | BRENDAN MORELLI |
| Insulation | 4/19/2024 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 5/28/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| Final | 5/28/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| Footing/Foundation/Slab | 5/28/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| Green Building Final | 5/28/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| HVAC-Final | 5/28/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| MERV13>=Final | 5/28/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| PLUMBING-Final | 5/28/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 5/28/2024 | SGSOV Not Ready | ARTHUR NEGRETE |
| Smoke Detectors | 5/28/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| ELECTRICAL-Final | 6/3/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| Final | 6/3/2024 | Corrections Issued | ARTHUR NEGRETE |
| Footing/Foundation/Slab | 6/3/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| Green Building Final | 6/3/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| HVAC-Final | 6/3/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| MERV13>=Final | 6/3/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| PLUMBING-Final | 6/3/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 6/3/2024 | SGSOV Not Ready | ARTHUR NEGRETE |
| Smoke Detectors | 6/3/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| Special/Order Compliance | 6/3/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 7/16/2024 | SGSOV Not Ready | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 7/23/2024 | SGSOV Not Ready | AMIR NAZARIAN |
| ELECTRICAL-Final | 7/29/2024 | Approved | ARTHUR NEGRETE |
| Final | 7/29/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| Footing/Foundation/Slab | 7/29/2024 | Approved | ARTHUR NEGRETE |
| Green Building Final | 7/29/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| HVAC-Final | 7/29/2024 | Approved | ARTHUR NEGRETE |
| MERV13>=Final | 7/29/2024 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 7/29/2024 | Approved | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 7/29/2024 | SGSOV Approved | ARTHUR NEGRETE |
| Service/Power Release | 7/29/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| Smoke Detectors | 7/29/2024 | Approved | ARTHUR NEGRETE |
| Verify Rec and Parks Fee Memo | 7/29/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| Final | 8/23/2024 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 8/23/2024 | Approved | ENRIQUE MIRELES |
| Final | 9/4/2024 | OK to Issue CofO | ARTHUR NEGRETE |
| Service/Power Release | 9/4/2024 | Approved | ARTHUR NEGRETE |