2408 W 74TH ST 90043
Certificate Information: 2408 W 74TH ST 90043
- Application / Permit
- 22014-10000-04460
- Plan Check / Job No.
- B22LA17853
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- addtion and convert existing detached garage (346sf) into ADU per engineer design (1,200 SF max per Ordinance, LAMC 12.22 A.33 (c)-(d))
- Permit Issued
- Issued on 8/19/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/12/2022 | AUNG SOE |
| Corrections Issued | 9/16/2022 | AUNG SOE |
| Building Plans Picked Up | 9/21/2022 | APPLICANT |
| Plan Check Approved | 11/17/2022 | AUNG SOE |
| Issued | 8/19/2024 | APPLICANT |
| CofO in Progress | 2/12/2025 | JOHN QUINTANILLA |
| Permit Finaled | 2/13/2025 | DEROLD HAUFF |
| CofO Issued | 2/13/2025 | DEROLD HAUFF |
| Permit Finaled | 2/13/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/13/2022 | AMAAN MALIK |
| Roof/Waste drainage to street | Cleared | 10/13/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 10/14/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 10/14/2022 | AMAAN MALIK |
Contact Information
| Contractor | Kafe Design & Construction; Lic. No.: 977712-B | 317 E RAMONA ROAD ALHAMBRA, CA 91801 |
| Engineer | Mchantaf,, Kamal Beshara; Lic. No.: C51050 | 23315 SARATOGA SPRINGS PL MURRIETA, CA 92562 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/22/2024 | Not Ready for Inspection | JOSE MACIAS |
| Underground Mechanical | 8/22/2024 | Corrections Issued | JOSE MACIAS |
| Excavation/Setback/Form/Re-Bar | 8/29/2024 | Corrections Issued | JOSE MACIAS |
| Footing/Foundation/Slab | 8/29/2024 | Not Ready for Inspection | JOSE MACIAS |
| Underground Mechanical | 8/29/2024 | Approved | JOSE MACIAS |
| Excavation/Setback/Form/Re-Bar | 8/30/2024 | Approved | JOSE MACIAS |
| Excavation/Setback/Form/Re-Bar | 9/4/2024 | Corrections Issued | AMIR NAZARIAN |
| Deputy Drilled-In Anchors | 9/6/2024 | Approved | AMIR NAZARIAN |
| Excavation/Setback/Form/Re-Bar | 9/20/2024 | Corrections Issued | AMIR NAZARIAN |
| Footing/Foundation/Slab | 9/20/2024 | Corrections Issued | AMIR NAZARIAN |
| Excavation/Setback/Form/Re-Bar | 9/25/2024 | Approved | AMIR NAZARIAN |
| Footing/Foundation/Slab | 9/25/2024 | Approved | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 10/18/2024 | Corrections Issued | AMIR NAZARIAN |
| ELECTRICAL-Rough | 10/18/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2024 | Corrections Issued | AMIR NAZARIAN |
| Green Building Rough | 10/18/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| HVAC-Rough | 10/18/2024 | Corrections Issued | AMIR NAZARIAN |
| PLUMBING-Rough | 10/18/2024 | Approved | AMIR NAZARIAN |
| Rough-Elec/Plmb/HVAC | 10/18/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2024 | Corrections Issued | AMIR NAZARIAN |
| Rough-Elec/Plmb/HVAC | 10/22/2024 | Corrections Issued | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 10/30/2024 | Corrections Issued | AMIR NAZARIAN |
| ELECTRICAL-Rough | 10/30/2024 | Approved | AMIR NAZARIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2024 | Corrections Issued | AMIR NAZARIAN |
| Green Building Rough | 10/30/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| HVAC-Rough | 10/30/2024 | Approved | AMIR NAZARIAN |
| ELECTRICAL-Rough | 11/7/2024 | Approved | AMIR NAZARIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2024 | Approved | AMIR NAZARIAN |
| Interior/Exterior Lathing | 11/7/2024 | Partial Approval | AMIR NAZARIAN |
| PLUMBING-Rough | 11/7/2024 | Approved | AMIR NAZARIAN |
| Insulation | 11/13/2024 | Approved | ALEX COLIN |
| Drywall Nailing | 11/18/2024 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 11/20/2024 | Corrections Issued | AMIR NAZARIAN |
| Shower Pan | 11/20/2024 | Corrections Issued | AMIR NAZARIAN |
| Shower Pan | 11/25/2024 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 12/3/2024 | Approved | ALEX COLIN |
| BUILDING-Rough-Frame | 1/10/2025 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 1/10/2025 | Not Ready for Inspection | SABAS ALONSO |
| Final | 1/10/2025 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 1/10/2025 | Approved | SABAS ALONSO |
| Green Building Rough | 1/10/2025 | Approved | SABAS ALONSO |
| HVAC-Final | 1/10/2025 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Final | 1/10/2025 | Not Ready for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 1/10/2025 | SGSOV Not Ready | SABAS ALONSO |
| Smoke Detectors | 1/10/2025 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 1/17/2025 | Corrections Issued | MICHAEL LEWIS |
| Final | 1/17/2025 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Final | 1/17/2025 | Corrections Issued | MICHAEL LEWIS |
| PLUMBING-Final | 1/17/2025 | Corrections Issued | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 1/17/2025 | SGSOV Not Required | MICHAEL LEWIS |
| ELECTRICAL-Final | 1/27/2025 | Partial Inspection | MICHAEL LEWIS |
| Final | 1/27/2025 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Final | 1/27/2025 | Partial Inspection | MICHAEL LEWIS |
| PLUMBING-Final | 1/27/2025 | Approved | MICHAEL LEWIS |
| Service/Power Release | 1/27/2025 | Not Ready for Inspection | MICHAEL LEWIS |
| ELECTRICAL-Final | 1/30/2025 | Corrections Issued | JOHN QUINTANILLA |
| Final | 1/30/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| HVAC-Final | 1/30/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| PLUMBING-Final | 1/30/2025 | Approved | JOHN QUINTANILLA |
| Service/Power Release | 1/30/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Pre-Inspection | 1/31/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| ELECTRICAL-Final | 2/4/2025 | Approved | JOHN QUINTANILLA |
| Final | 2/4/2025 | OK to Issue CofO | JOHN QUINTANILLA |
| HVAC-Final | 2/4/2025 | Approved | JOHN QUINTANILLA |
| PLUMBING-Final | 2/4/2025 | Approved | JOHN QUINTANILLA |
| Service/Power Release | 2/7/2025 | Approved | JOHN QUINTANILLA |