1557 W 46TH ST 90062

Certificate Information: 1557 W 46TH ST 90062

Application / Permit
22014-10000-04456
Plan Check / Job No.
B22LA17810
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2 STORY ADU w/ attached GARAGE and STORAGE - 1ST FLOOR 1-CAR GARAGE AND STORAGE ROOM; 2ND FLOOR ADU PER LAMC 12.22A.33(c) and (d)
Permit Issued
Issued on 6/5/2023
Issuing Office
Metro
Current Status
CofO Issued on 9/25/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/6/2022 APPLICANT
Assigned to Plan Check Engineer 9/22/2022 SAM CHANG
Corrections Issued 10/4/2022 SAM CHANG
Quality Review Completed 10/4/2022 EUGENE BARBEAU
Building Plans Picked Up 10/17/2022 APPLICANT
Applicant returned to address corrections 12/5/2022 SAM CHANG
Applicant returned to address corrections 5/8/2023 SAM CHANG
Plan Check Approved 5/22/2023 SAM CHANG
Issued 6/5/2023 APPLICANT
CofO in Progress 9/19/2024 SABAS ALONSO
Permit Finaled 9/25/2024 RUBEN SALAS
CofO Issued 9/25/2024 RUBEN SALAS
Permit Finaled 9/25/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/21/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 10/28/2022 AMAAN MALIK
Sewer availability Cleared 10/28/2022 AMAAN MALIK
Hydrant and Access approval Cleared 11/13/2022 JOHN CONNEALLY
Low Impact Development Cleared 4/26/2023 ERNEST TSE
Roof/Waste drainage to street Cleared 5/22/2023 STEVE MELGAR

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/21/2023 Approved SABAS ALONSO
Footing/Foundation/Slab 6/21/2023 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 7/17/2023 Partial Approval BRENDAN MORELLI
Green Building Rough 7/17/2023 Not Ready for Inspection BRENDAN MORELLI
Sewer 7/17/2023 Partial Approval BRENDAN MORELLI
Deputy Wood Construction 8/1/2023 Conditional Approval SABAS ALONSO
Deputy Steel/Welding 8/7/2023 Conditional Approval SABAS ALONSO
ELECTRICAL-Rough 8/8/2023 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 8/8/2023 Approved SABAS ALONSO
HVAC-Rough 8/8/2023 Approved SABAS ALONSO
PLUMBING-Rough 8/8/2023 Approved SABAS ALONSO
Sewer 8/8/2023 Approved SABAS ALONSO
Underground Mechanical 8/8/2023 Partial Approval SABAS ALONSO
BUILDING-Rough-Frame 8/17/2023 Approved STUART CHAPMAN
Green Building Rough 8/17/2023 Approved STUART CHAPMAN
Interior/Exterior Lathing 8/17/2023 Partial Approval STUART CHAPMAN
Shower Pan 8/17/2023 Approved STUART CHAPMAN
Verify Sprinkler Sign Off 8/17/2023 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 9/7/2023 Approved BRENDAN MORELLI
Insulation 9/7/2023 Conditional Approval BRENDAN MORELLI
Interior/Exterior Lathing 9/7/2023 Approved BRENDAN MORELLI
Drywall Nailing 3/14/2024 Approved SABAS ALONSO
Final 6/11/2024 Corrections Issued ANTHONY EGSON
Green Building Final 6/11/2024 Approved ANTHONY EGSON
Final 6/26/2024 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 6/26/2024 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 6/26/2024 SGSOV Approved SABAS ALONSO
Service/Power Release 6/26/2024 Not Ready for Inspection SABAS ALONSO
Smoke Detectors 6/26/2024 Not Ready for Inspection SABAS ALONSO
Smoke Detectors 9/6/2024 Approved SABAS ALONSO
Final 9/12/2024 Corrections Issued SABAS ALONSO
Service/Power Release 9/12/2024 Not Ready for Inspection SABAS ALONSO
Final 9/16/2024 OK to Issue CofO SABAS ALONSO