2115 S KERWOOD AVE 90025

Certificate Information: 2115 S KERWOOD AVE 90025

Application / Permit
22014-10000-04439
Plan Check / Job No.
B22LA17739
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN REMODEL OF SINGLE FAMILY DWELLING: 1. ADDITION OF ONE(1) 162 SQFT ATTACHED FAMILY ROOM @ EXISTING PATIO AREA IN REAR YARD 2. INTERIOR REMODEL OF KITCHEN, BEDROOM & BATHROOM "COMPLY WITH DEPARTMENT ORDER effective date 06/14/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
Permit Issued
Issued on 8/15/2023
Issuing Office
Current Status
CofO Issued on 9/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/4/2022 APPLICANT
Assigned to Plan Check Engineer 9/22/2022 JAD BASMA
Corrections Issued 9/30/2022 JAD BASMA
Quality Review Completed 10/12/2022 TEODORO DIAZ RODRIGUEZ
Plan Check Approved 8/15/2023 JAD BASMA
Issued 8/15/2023 APPLICANT
CofO in Progress 3/11/2024 PETER RUBIO
Permit Finaled 9/6/2024 DANIEL SANCHEZ
CofO Issued 9/6/2024 DANIEL SANCHEZ
Permit Finaled 9/6/2024 DANIEL SANCHEZ

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/19/2023 DINAH GARIN
Roof/Waste drainage to street Cleared 1/19/2023 JENSON LEE
Grading Pre-Inspection Cleared 1/25/2023 KIRK LINKLATER
Specific Plan Cleared 1/26/2023 ALESSANDRO MERCURI

Contact Information

Contractor Tech La Builder; Lic. No.: 1097275-B       ,

Inspector Information

PETER RUBIO, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
JOHN TCHANG, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
RYAN TAGUINES, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/22/2023 Approved PETER RUBIO
Footing/Foundation/Slab 9/13/2023 Approved PETER RUBIO
METHANE-Barrier 9/13/2023 Approved PETER RUBIO
METHANE-Subgrade 9/13/2023 Approved PETER RUBIO
Deputy Reinf. Concrete 9/15/2023 Partial Approval PETER RUBIO
Floor/Roof Diaphrgm/Shear Wall 9/21/2023 Partial Approval RUBEN PEREZ
ELECTRICAL-Rough 9/28/2023 Approved ROBERT NILES
Sewer 9/28/2023 Approved ROBERT NILES
Wood Frame 10/4/2023 Approved RUBEN PEREZ
Deputy Wood Construction 10/10/2023 Conditional Approval RUBEN PEREZ
Floor/Roof Diaphrgm/Shear Wall 10/11/2023 Approved RUBEN PEREZ
ELECTRICAL-Rough 10/17/2023 Approved ROBERT NILES
Insulation 10/17/2023 Approved ROBERT NILES
Interior/Exterior Lathing 10/17/2023 Not Ready for Inspection ROBERT NILES
Drywall Nailing 10/19/2023 Approved ROBERT NILES
Interior/Exterior Lathing 10/19/2023 Not Ready for Inspection ROBERT NILES
Shower Pan 10/19/2023 Approved ROBERT NILES
Interior/Exterior Lathing 10/23/2023 Approved ROBERT NILES
BUILDING-Rough-Frame 1/2/2024 Approved PETER RUBIO
Final 1/2/2024 Corrections Issued PETER RUBIO
Green Building Final 1/2/2024 Not Ready for Inspection PETER RUBIO
Green Building Rough 1/2/2024 Approved PETER RUBIO
METHANE-Final 1/2/2024 Approved PETER RUBIO
METHANE-Rough 1/2/2024 Approved PETER RUBIO
SGSOV-Seismic Gas S/O Valve 1/2/2024 SGSOV Approved PETER RUBIO
Smoke Detectors 1/2/2024 Approved PETER RUBIO
Final 1/10/2024 Conditional Approval PETER RUBIO
Green Building Final 1/10/2024 Approved PETER RUBIO
Final 3/8/2024 OK to Issue CofO PETER RUBIO