10134-10136 N CREBS AVE 91324

Certificate Information: 10134-10136 N CREBS AVE 91324

Application / Permit
22014-10000-04433
Plan Check / Job No.
B22LA17717
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(N) 24.5 FT X 38.5 FT ATTACHED, 1-STORY SFD PER SB9 ATTACHED TO EXISTING SFD WITH ATTACHED GARAGE
Permit Issued
Issued on 6/21/2023
Issuing Office
Valley
Current Status
CofO Issued on 7/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/2/2022 APPLICANT
Assigned to Plan Check Engineer 9/8/2022 CRYSTEL MAALOUF
Corrections Issued 9/21/2022 CRYSTEL MAALOUF
Quality Review Completed 9/30/2022 FARUK SEZER
Building Plans Picked Up 10/3/2022 APPLICANT
Plan Check Approved 6/12/2023 CRYSTEL MAALOUF
Issued 6/21/2023 APPLICANT
CofO in Progress 6/24/2024 DAVID SCANTLIN
Permit Finaled 7/5/2024 JOHN JANSON
CofO Issued 7/5/2024 JOHN JANSON
Permit Finaled 7/5/2024 JOHN JANSON

Permit Application Clearance Information

Senate Bill 9 Cleared 5/3/2023 NATHAN ROMINE
Low Impact Development Cleared 5/23/2023 SARAH YOUSSEF
Address approval Cleared 5/31/2023 ROMAN GUTIERREZ
Roof/Waste drainage to street Cleared 5/31/2023 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 6/1/2023 ROMAN GUTIERREZ
Sewer availability Cleared 6/1/2023 ROMAN GUTIERREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/26/2023 Approved JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 6/26/2023 Approved JOHN KIDWELL
Underground Mechanical 6/26/2023 Approved JOHN KIDWELL
BUILDING-Rough-Frame 8/1/2023 Not Ready for Inspection DAVID SCANTLIN
Deputy Wood Construction 8/1/2023 Conditional Approval DAVID SCANTLIN
FLOOD-Proofing Certificate 8/1/2023 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 8/1/2023 Partial Approval DAVID SCANTLIN
Green Building Rough 8/1/2023 Not Ready for Inspection DAVID SCANTLIN
Rough-Elec/Plmb/HVAC 8/1/2023 Approved DAVID SCANTLIN
Wood Frame 8/1/2023 Approved DAVID SCANTLIN
Interior/Exterior Lathing 8/15/2023 Not Ready for Inspection DAVID SCANTLIN
Shower Pan 8/15/2023 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 9/5/2023 Approved JOHN KIDWELL
ELECTRICAL-Rough 9/5/2023 Approved JOHN KIDWELL
Green Building Rough 9/5/2023 Approved JOHN KIDWELL
Insulation 9/5/2023 Conditional Approval JOHN KIDWELL
Interior/Exterior Lathing 9/5/2023 Partial Approval JOHN KIDWELL
Drywall Nailing 9/8/2023 Not Ready for Inspection DAVID SCANTLIN
Interior/Exterior Lathing 9/22/2023 Partial Approval JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 4/4/2024 SGSOV Not Ready JEFFREY HARTLINE
Final 4/8/2024 Corrections Issued DAVID SCANTLIN
Footing/Foundation/Slab 4/8/2024 Approved DAVID SCANTLIN
Green Building Final 4/8/2024 Approved DAVID SCANTLIN
Pre-Inspection 4/8/2024 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 4/8/2024 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 4/8/2024 Approved DAVID SCANTLIN
Final 5/1/2024 Not Ready for Inspection DAVID SCANTLIN
Final 6/24/2024 OK to Issue CofO DAVID SCANTLIN