8017 S HOLY CROSS PL 90045
Certificate Information: 8017 S HOLY CROSS PL 90045
- Application / Permit
- 22014-10000-04408
- Plan Check / Job No.
- B22LA15836
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel and addition to (E) SFD
- Permit Issued
- Issued on 1/9/2023
- Issuing Office
- Current Status
- CofO Issued on 8/28/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/31/2022 | JOE VO |
| Corrections Issued | 9/1/2022 | JOE VO |
| Quality Review Completed | 9/1/2022 | GARO TELMI |
| Plan Check Approved | 1/4/2023 | JOE VO |
| Issued | 1/9/2023 | APPLICANT |
| CofO in Progress | 8/27/2024 | BOBBY KEY |
| Permit Finaled | 8/28/2024 | RICHARD STEINBACH |
| CofO Issued | 8/28/2024 | RICHARD STEINBACH |
| Permit Finaled | 8/28/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Sewer availability | Cleared | 10/27/2022 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/28/2022 | ANTHONY MAINEZ |
| Specific Plan | Cleared | 12/6/2022 | PEDRO AYALA |
| Roof/Waste drainage to street | Cleared | 12/8/2022 | DINAH GARIN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/11/2023 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 4/19/2023 | Approved | BOBBY KEY |
| PLUMBING-Rough | 4/19/2023 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2023 | Conditional Approval | JESUS RODRIGUEZ |
| Green Building Rough | 9/5/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 9/22/2023 | Conditional Approval | BOBBY KEY |
| PLUMBING-Rough | 9/22/2023 | Corrections Issued | BOBBY KEY |
| BUILDING-Rough-Frame | 10/11/2023 | Approved | BOBBY KEY |
| Green Building Rough | 10/11/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 10/11/2023 | Partial Approval | BOBBY KEY |
| Rough-Elec/Plmb/HVAC | 10/11/2023 | Conditional Approval | BOBBY KEY |
| Deputy Other (see comments) | 10/12/2023 | Conditional Approval | BOBBY KEY |
| HVAC-Rough | 10/19/2023 | Approved | BOBBY KEY |
| Insulation | 10/19/2023 | Approved | BOBBY KEY |
| Shower Pan | 10/19/2023 | Approved | BOBBY KEY |
| Drywall Nailing | 10/30/2023 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 11/9/2023 | Approved | BOBBY KEY |
| Gas Test | 1/29/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 5/6/2024 | Corrections Issued | BOBBY KEY |
| Final | 5/6/2024 | Corrections Issued | BOBBY KEY |
| Green Building Final | 5/6/2024 | Approved | BOBBY KEY |
| HVAC-Final | 5/6/2024 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 5/6/2024 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 5/6/2024 | SGSOV Not Ready | BOBBY KEY |
| Smoke Detectors | 5/6/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 7/25/2024 | Approved | BOBBY KEY |
| Final | 7/25/2024 | Corrections Issued | BOBBY KEY |
| HVAC-Final | 7/25/2024 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 7/25/2024 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 7/25/2024 | SGSOV Not Ready | BOBBY KEY |
| Service/Power Release | 7/25/2024 | Approved | BOBBY KEY |
| Final | 8/27/2024 | OK to Issue CofO | BOBBY KEY |
| HVAC-Final | 8/27/2024 | Approved | BOBBY KEY |
| PLUMBING-Final | 8/27/2024 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 8/27/2024 | SGSOV Approved | BOBBY KEY |