1441 W 215TH ST 90501
Certificate Information: 1441 W 215TH ST 90501
- Application / Permit
- 22014-10000-04375
- Plan Check / Job No.
- B22LA17441
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *EPLAN* 345 sf addition to existing Single-Family Dwelling, including bedroom, bathroom, and laundry room.
- Permit Issued
- Issued on 11/19/2022
- Issuing Office
- Current Status
- CofO Issued on 9/13/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/13/2022 | MINA HABILI |
| Corrections Issued | 9/13/2022 | MINA HABILI |
| Applicant returned to address corrections | 11/1/2022 | MINA HABILI |
| Plan Check Approved | 11/16/2022 | JOSEPH RAFOLS |
| Issued | 11/19/2022 | APPLICANT |
| CofO in Progress | 9/13/2024 | JOSEPH MCGARRY |
| Permit Finaled | 9/13/2024 | ANSON MAGLASANG |
| CofO Issued | 9/13/2024 | ANSON MAGLASANG |
| Permit Finaled | 9/13/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/29/2022 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 10/3/2022 | ERIK BEASLEY |
| Sewer availability | Cleared | 10/17/2022 | ERIK BEASLEY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/27/2023 | Partial Approval | EUGENE CASSIDY |
| Deputy Drilled-In Anchors | 8/17/2023 | Partial Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 8/21/2023 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 8/28/2023 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 9/8/2023 | Partial Approval | EUGENE CASSIDY |
| Insulation | 9/8/2023 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 9/12/2023 | Partial Approval | EUGENE CASSIDY |
| Green Building Rough | 9/12/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2023 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2023 | Partial Approval | EUGENE CASSIDY |
| PLUMBING-Rough | 10/17/2023 | Corrections Issued | EUGENE CASSIDY |
| Wood Frame | 10/17/2023 | Partial Approval | EUGENE CASSIDY |
| Shower Pan | 10/30/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Rough | 11/3/2023 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 11/3/2023 | Approved | EUGENE CASSIDY |
| Shower Pan | 11/3/2023 | Approved | EUGENE CASSIDY |
| Wood Frame | 11/3/2023 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 11/6/2023 | Approved | EUGENE CASSIDY |
| Green Building Rough | 11/6/2023 | Approved | EUGENE CASSIDY |
| Insulation | 11/6/2023 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 11/6/2023 | Partial Approval | EUGENE CASSIDY |
| Drywall Nailing | 11/9/2023 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 11/9/2023 | Approved | EUGENE CASSIDY |
| Final | 7/25/2024 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 7/25/2024 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 7/25/2024 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 7/25/2024 | Approved | EUGENE CASSIDY |
| Final | 9/12/2024 | OK to Issue CofO | JOSEPH MCGARRY |