6344 N BEEMAN AVE 91606

Certificate Information: 6344 N BEEMAN AVE 91606

Application / Permit
22014-10000-04367
Plan Check / Job No.
B22LA17406
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED GARAGE CONVERSION AND GROUND FLOOR ADDITION FOR ACCESSORY DWELLING UNIT WITH NEW ATTIC STORAGE PER ORDINANCE & LAMC 12.22 A33 (c)&(d) .
Permit Issued
Issued on 1/31/2023
Issuing Office
Valley
Current Status
CofO Issued on 9/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/30/2022 APPLICANT
Assigned to Plan Check Engineer 9/7/2022 LAWRENCE QUIRANTE
Corrections Issued 9/8/2022 LAWRENCE QUIRANTE
Building Plans Picked Up 9/16/2022 APPLICANT
Applicant returned to address corrections 12/16/2022 ZAW HAN
Plan Check Approved 12/16/2022 AUNG SOE
Plan Check Approved 1/27/2023 GEORGE ALVAREZ
Issued 1/31/2023 APPLICANT
CofO in Progress 12/1/2023 KIRK SANDERS
CofO Issued 9/10/2024 DANIEL ORRANTE
Permit Finaled 9/10/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 9/29/2022 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 9/29/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 10/25/2022 DAGOVERTO GUERRERO
Construction near power lines Cleared 12/1/2022 WALTER RAMIREZ
Eng Process Fee Ord 176,300 Cleared 12/16/2022 JEANETTE VONG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/10/2023 Conditional Approval KIRK SANDERS
Footing/Foundation/Slab 3/16/2023 Corrections Issued JOHN COLEMAN
Footing/Foundation/Slab 5/2/2023 Corrections Issued KIRK SANDERS
Footing/Foundation/Slab 6/20/2023 Corrections Issued KIRK SANDERS
Footing/Foundation/Slab 6/30/2023 Approved JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 8/3/2023 Partial Approval JUAN VALENZUELA
Wood Frame 8/3/2023 Partial Inspection JUAN VALENZUELA
BUILDING-Rough-Frame 8/11/2023 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 8/11/2023 Corrections Issued MISAEL ESPARZA
Green Building Rough 8/11/2023 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 8/11/2023 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 8/11/2023 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 8/21/2023 Approved KIRK SANDERS
ELECTRICAL-Rough 8/21/2023 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 8/21/2023 Partial Approval KIRK SANDERS
Green Building Rough 8/21/2023 Approved KIRK SANDERS
HVAC-Rough 8/21/2023 Approved KIRK SANDERS
Insulation 8/21/2023 Partial Approval KIRK SANDERS
Interior/Exterior Lathing 8/24/2023 Partial Approval CHRISTOPHER ROJAS
Shower Pan 8/24/2023 Approved CHRISTOPHER ROJAS
Insulation 8/29/2023 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 8/29/2023 Approved CHRISTOPHER ROJAS
Drywall Nailing 8/31/2023 Approved CHRISTOPHER ROJAS
Final 10/26/2023 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 10/26/2023 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 10/26/2023 SGSOV Not Ready CHRISTOPHER ROJAS
Smoke Detectors 10/26/2023 Approved CHRISTOPHER ROJAS
Final 11/15/2023 Corrections Issued KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 11/15/2023 SGSOV Not Ready KIRK SANDERS
Final 11/30/2023 OK to Issue CofO KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 11/30/2023 SGSOV Approved KIRK SANDERS