7029 N LOUISE AVE 91406

Certificate Information: 7029 N LOUISE AVE 91406

Application / Permit
22014-10000-04361
Plan Check / Job No.
B22LA17395
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION/REMODEL 1-STORY SFD ADD 232 SF OF (N) MASTER BEDROOM &W/C REMODEL (E) HALLWAY; (N) BATH #2
Permit Issued
Issued on 10/6/2022
Issuing Office
Metro
Current Status
CofO Issued on 5/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/30/2022 APPLICANT
Assigned to Plan Check Engineer 9/5/2022 RICARDO RAMIREZ
Corrections Issued 9/5/2022 RICARDO RAMIREZ
Building Plans Picked Up 9/9/2022 APPLICANT
Applicant returned to address corrections 9/21/2022 STANLEY RAAP
Plan Check Approved 9/29/2022 JOSEPH RAFOLS
Issued 10/6/2022 APPLICANT
CofO in Progress 5/23/2023 JON MCHUGH
CofO in Progress 5/23/2023 JON MCHUGH
CofO Issued 5/23/2023 JOHN JANSON
Permit Finaled 5/23/2023 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/12/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 9/14/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Sin,, John Paul; Lic. No.: C91162 122 N GRAMERCY PL      LOS ANGELES, CA 90004

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/17/2022 Conditional Approval JUSTIN HAWLEY
Excavation/Setback/Form/Re-Bar 10/20/2022 Approved SEAN HAUPT
BUILDING-Rough-Frame 10/26/2022 Partial Approval SEAN HAUPT
Green Building Rough 10/26/2022 Not Ready for Inspection SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 10/31/2022 Approved SEAN HAUPT
BUILDING-Rough-Frame 11/16/2022 Not Ready for Inspection SEAN HAUPT
ELECTRICAL-Rough 11/16/2022 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 11/16/2022 Approved SEAN HAUPT
Green Building Rough 11/16/2022 Not Ready for Inspection SEAN HAUPT
PLUMBING-Rough 11/16/2022 Not Ready for Inspection SEAN HAUPT
Insulation 11/21/2022 Approved JEFFREY BULL
Interior/Exterior Lathing 11/21/2022 Partial Approval JEFFREY BULL
Rough-Elec/Plmb/HVAC 11/21/2022 Approved JEFFREY BULL
Drywall Nailing 11/23/2022 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 11/23/2022 Not Ready for Inspection KRISTEN CAUSEY
Interior/Exterior Lathing 12/1/2022 Approved SEAN HAUPT
Shower Pan 12/1/2022 Approved SEAN HAUPT
BUILDING-Rough-Frame 1/3/2023 Approved JON MCHUGH
Final 1/3/2023 Corrections Issued JON MCHUGH
Footing/Foundation/Slab 1/3/2023 Approved JON MCHUGH
Green Building Final 1/3/2023 Approved JON MCHUGH
Green Building Rough 1/3/2023 Approved JON MCHUGH
SGSOV-Seismic Gas S/O Valve 1/3/2023 SGSOV Approved JON MCHUGH
Smoke Detectors 1/3/2023 Approved JON MCHUGH
Final 5/19/2023 No Access for Inspection HORACE FULTZ
Final 5/23/2023 OK to Issue CofO JON MCHUGH