1934 N DEL PASO AVE 90032

Certificate Information: 1934 N DEL PASO AVE 90032

Application / Permit
22014-10000-04359
Plan Check / Job No.
B22LA17390
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
*EPLAN*- basement and ground floor addition of (e) 1-story SFD ENCLOSE (E) DECK AT SECOND FLOOR FOR (N) MASTER BATHROOM ENCLOSE (E) ROOF OVERHANG AT ENTRY FOR (N) ENTRY (N) CLOSET ADDITION AT SECOND FLOOR BEDROOM AND (N) ATTIC OVER (N) POWDER ROOM INTERIOR REMODEL OF KITCHEN, DINING, LIVING ROOM, LAUNDRY, MASTER SUITE AND BEDROOM UPGRADE TO 200 AMP ELECTRICAL PANEL (N) TANKLESS WATER HEATER (N) FAU IN MECH. CLOSET (N) AC ON CONC. PAD REPLACE (E) ROOF W/ CLASS A COOL ROOF ASPHALT SHINGLE ROOF
Permit Issued
Issued on 4/8/2023
Issuing Office
Current Status
Issued on 4/8/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/30/2022 APPLICANT
Assigned to Plan Check Engineer 9/15/2022 KELVIN CHUONG
Corrections Issued 9/22/2022 KELVIN CHUONG
Quality Review Completed 9/30/2022 RODOLFO ARIAS
Applicant returned to address corrections 12/15/2022 KELVIN CHUONG
Applicant returned to address corrections 3/10/2023 KELVIN CHUONG
Applicant returned to address corrections 3/22/2023 KELVIN CHUONG
Plan Check Approved 3/24/2023 KELVIN CHUONG
Issued 4/8/2023 APPLICANT

Permit Application Clearance Information

Miscellaneous Cleared 11/10/2022 ANACANY HURTADO
Miscellaneous Cleared 11/10/2022 ANACANY HURTADO
Miscellaneous Cleared 11/10/2022 ANACANY HURTADO
ZI Cleared 11/10/2022 ANACANY HURTADO
Private street Cleared 11/15/2022 DANIEL CORONADO
Private street Cleared 11/15/2022 DANIEL CORONADO
BHO/Hillside ordinance Cleared 12/5/2022 STEVE MELGAR
BHO/Hillside ordinance Cleared 12/5/2022 STEVE MELGAR
BHO/Hillside ordinance Cleared 12/5/2022 STEVE MELGAR
BHO/Hillside ordinance Cleared 12/5/2022 STEVE MELGAR
Sewer availability Cleared 12/5/2022 STEVE MELGAR
Excavation more than 5-ft deep Cleared 12/6/2022 CALOSHA APPROVED
Low Impact Development Cleared 12/6/2022 SARAH YOUSSEF
"D" conditions Cleared 12/12/2022 DANIEL CORONADO
"Q" conditions Cleared 12/12/2022 DANIEL CORONADO
Hydrant and Access approval Cleared 12/12/2022 MATTHEW CRAIG
ZI Cleared 12/12/2022 DANIEL CORONADO
Grading Pre-Inspection Cleared 12/13/2022 KELVIN CHUONG
BHO/Hillside ordinance Cleared 12/22/2022 TREVOR QUAN
Roof/Waste drainage to street Cleared 12/22/2022 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 12/27/2022 JEANETTE VONG
GPI Written Notices Cleared 1/18/2023 KELVIN CHUONG
Construction near power lines Cleared 2/22/2023 RIDWAN HARDY
Zoning Information File Cleared 3/22/2023 KELVIN CHUONG

Contact Information

Contractor Owner-Builder       ,
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403
Engineer Liu,, Haiyan Harry; Lic. No.: C81463 10855 BECKFORD AVE      NORTHRIDGE, CA 91326
Geologist Swiatek,, Mark A; Lic. No.: EG1781 24203 VALLEY ST      NEWHALL, CA 91321

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/11/2023 Corrections Issued AMY COLIN
Piling/Pier/Caisson 9/11/2023 Not Ready for Inspection AMY COLIN
PLUMBING-Rough 9/22/2023 Partial Approval ROY SPAULDING
Excavation/Setback/Form/Re-Bar 9/26/2023 Not Ready for Inspection AMY COLIN
Footing/Foundation/Slab 9/26/2023 Not Ready for Inspection AMY COLIN
Excavation/Setback/Form/Re-Bar 9/28/2023 Approved AMY COLIN
Footing/Foundation/Slab 10/6/2023 Conditional Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 12/14/2023 Partial Approval AMY COLIN
Footing/Foundation/Slab 12/14/2023 Approved AMY COLIN
BUILDING-Rough-Frame 2/28/2024 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Rough 2/28/2024 Corrections Issued CRAIG VAUGHAN
Gas Test 2/28/2024 Approved CRAIG VAUGHAN
HVAC-Rough 2/28/2024 Corrections Issued CRAIG VAUGHAN
Interior/Exterior Lathing 2/28/2024 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 2/28/2024 Corrections Issued CRAIG VAUGHAN
Rough-Elec/Plmb/HVAC 2/28/2024 Not Ready for Inspection CRAIG VAUGHAN
Shower Pan 2/28/2024 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 3/7/2024 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 3/7/2024 Approved LILIANA PORTILLO
Gas Test 3/7/2024 Approved LILIANA PORTILLO
HVAC-Rough 3/7/2024 Approved LILIANA PORTILLO
PLUMBING-Rough 3/7/2024 Approved LILIANA PORTILLO
Insulation 3/12/2024 Approved LILIANA PORTILLO
Drywall Nailing 3/22/2024 Conditional Approval LILIANA PORTILLO
Green Building Rough 3/22/2024 Approved LILIANA PORTILLO
Gas Test 4/4/2024 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 4/4/2024 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 4/5/2024 No Access for Inspection JOSEPH MCGARRY
ELECTRICAL-Final 6/24/2024 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 11/1/2024 Approved LILIANA PORTILLO
Drywall Nailing 11/1/2024 Approved LILIANA PORTILLO
Final 11/1/2024 Corrections Issued LILIANA PORTILLO
Green Building Final 11/1/2024 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 11/1/2024 SGSOV Not Ready LILIANA PORTILLO
Smoke Detectors 11/1/2024 Approved LILIANA PORTILLO
Final 11/26/2024 Not Ready for Inspection JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 11/26/2024 SGSOV Not Ready JOHN QUINTANILLA
Final 12/3/2024 Not Ready for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 12/3/2024 SGSOV Not Ready LILIANA PORTILLO
Final 12/12/2024 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 12/12/2024 SGSOV Approved LILIANA PORTILLO