4637 N NOBLE AVE 91403

Certificate Information: 4637 N NOBLE AVE 91403

Application / Permit
22014-10000-04342
Plan Check / Job No.
B22LA17280
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERET (E) GARAGE INTO (N) ACCESSORY DWELLING UNIT & EXPAND (IRR 41' X 11'-6") PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g)
Permit Issued
Issued on 12/21/2022
Issuing Office
Current Status
CofO Issued on 3/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/29/2022 APPLICANT
Assigned to Plan Check Engineer 9/1/2022 NILOOFAR MEHRAIN
Corrections Issued 9/6/2022 NILOOFAR MEHRAIN
Quality Review Completed 9/13/2022 STEVEN KIM
Applicant returned to address corrections 11/9/2022 NILOOFAR MEHRAIN
Applicant returned to address corrections 11/15/2022 NILOOFAR MEHRAIN
Plan Check Approved 12/20/2022 NILOOFAR MEHRAIN
Issued 12/21/2022 APPLICANT
CofO in Progress 2/10/2025 JACK KARGODORIAN
CofO in Progress 2/14/2025 JUAN VALENZUELA
No Progress 2/18/2025 JACK KARGODORIAN
CofO in Progress 2/18/2025 JACK KARGODORIAN
CofO in Progress 3/12/2025 JUAN VALENZUELA
Permit Finaled 3/13/2025 RUBEN SALAS
CofO Issued 3/13/2025 RUBEN SALAS
Permit Finaled 3/13/2025 RUBEN SALAS

Permit Application Clearance Information

Hydrant and Access approval Cleared 10/8/2022 RUEL COLE
Construction near power lines Cleared 10/17/2022 RIDWAN HARDY
Construction within easement Cleared 10/17/2022 RIDWAN HARDY
Address approval Cleared 10/21/2022 ROMAN GUTIERREZ
Roof/Waste drainage to street Cleared 10/21/2022 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 10/24/2022 ROMAN GUTIERREZ
Sewer availability Cleared 10/24/2022 ROMAN GUTIERREZ
Low Impact Development Cleared 10/31/2022 MARTIN FRAGOSO

Contact Information

Contractor Owner-Builder       ,
Engineer Gosen,, James W; Lic. No.: NA43590       ,

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/5/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
PLUMBING-Rough 1/5/2023 Corrections Issued CHRISTOPHE COCHRAN
Deputy Drilled-In Anchors 1/6/2023 Conditional Approval MISAEL ESPARZA
PLUMBING-Rough 1/6/2023 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 1/12/2023 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 1/23/2023 Partial Approval THOMAS FINNILA
Footing/Foundation/Slab 1/26/2023 Partial Approval THOMAS FINNILA
Footing/Foundation/Slab 1/31/2023 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 2/15/2023 Corrections Issued THOMAS FINNILA
ELECTRICAL-Rough 2/15/2023 Approved THOMAS FINNILA
HVAC-Rough 2/15/2023 Approved THOMAS FINNILA
PLUMBING-Rough 2/15/2023 Approved THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 2/17/2023 Partial Approval THOMAS FINNILA
BUILDING-Rough-Frame 2/22/2023 Approved THOMAS FINNILA
Insulation 2/24/2023 Approved THOMAS FINNILA
Interior/Exterior Lathing 2/24/2023 Not Ready for Inspection THOMAS FINNILA
Drywall Nailing 2/27/2023 Approved THOMAS FINNILA
Interior/Exterior Lathing 2/27/2023 Approved THOMAS FINNILA
ELECTRICAL-Final 4/18/2024 Corrections Issued THOMAS FINNILA
Gas Test 4/18/2024 Approved THOMAS FINNILA
HVAC-Final 4/18/2024 Corrections Issued THOMAS FINNILA
PLUMBING-Final 4/18/2024 Approved THOMAS FINNILA
Final 4/25/2024 Corrections Issued THOMAS FINNILA
Final 1/23/2025 Not Ready for Inspection JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 1/23/2025 SGSOV Approved JACK KARGODORIAN
Smoke Detectors 1/23/2025 Approved JACK KARGODORIAN
Final 2/10/2025 Not Ready for Inspection JACK KARGODORIAN
Final 2/18/2025 Corrections Issued JACK KARGODORIAN
Final 3/12/2025 OK to Issue CofO JUAN VALENZUELA