1156 N SANBORN AVE 90029

Certificate Information: 1156 N SANBORN AVE 90029

Application / Permit
22014-10000-04335
Plan Check / Job No.
B22LA17265
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan Remodel and 620 SF addition to single family residence.
Permit Issued
Issued on 3/20/2023
Issuing Office
Current Status
CofO Issued on 3/2/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/26/2022 APPLICANT
Assigned to Plan Check Engineer 9/15/2022 ARSALAN SHABESTARI
Corrections Issued 10/5/2022 ARSALAN SHABESTARI
Quality Review Completed 10/6/2022 GARO TELMI
Plan Check Approved 3/6/2023 ARSALAN SHABESTARI
Issued 3/20/2023 APPLICANT
CofO in Progress 2/22/2024 THOMAS LOGRASSO
Permit Finaled 3/2/2024 RONALD MYRICK
CofO Issued 3/2/2024 RONALD MYRICK
Permit Finaled 3/2/2024 RONALD MYRICK

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 10/20/2022 STEVE MELGAR
Sewer availability Cleared 10/20/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 10/24/2022 STEVE MELGAR
GPI Written Notices Cleared 12/13/2022 ARSALAN SHABESTARI
Grading Pre-Inspection Cleared 12/13/2022 ARSALAN SHABESTARI

Contact Information

Architect Farnham,, Emily; Lic. No.: NA34247       ,
Contractor Fig Tree Construction And Remodeling Inc; Lic. No.: 1088754-B       ,

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/15/2023 Corrections Issued THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 7/10/2023 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 7/19/2023 Partial Approval FREDDIE RIVERA
PLUMBING-Rough 7/19/2023 Partial Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 7/24/2023 Approved THOMAS LOGRASSO
Insulation 7/24/2023 Partial Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 8/7/2023 Partial Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 9/8/2023 Not Ready for Inspection THOMAS LOGRASSO
Deputy Wood Construction 9/11/2023 Conditional Approval THOMAS LOGRASSO
ELECTRICAL-Rough 9/22/2023 Approved THOMAS LOGRASSO
HVAC-Rough 9/22/2023 Approved THOMAS LOGRASSO
PLUMBING-Rough 9/22/2023 Corrections Issued THOMAS LOGRASSO
BUILDING-Rough-Frame 10/4/2023 Corrections Issued THOMAS LOGRASSO
Green Building Rough 10/4/2023 Not Ready for Inspection THOMAS LOGRASSO
PLUMBING-Rough 10/4/2023 Approved THOMAS LOGRASSO
Insulation 10/13/2023 Approved STUART CHAPMAN
Interior/Exterior Lathing 10/13/2023 Partial Approval STUART CHAPMAN
Drywall Nailing 10/20/2023 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 10/20/2023 Approved THOMAS LOGRASSO
Shower Pan 10/20/2023 Approved THOMAS LOGRASSO
HVAC-Final 1/24/2024 Partial Approval FREDDIE RIVERA
BUILDING-Rough-Frame 2/6/2024 Conditional Approval THOMAS LOGRASSO
Final 2/6/2024 Corrections Issued THOMAS LOGRASSO
Footing/Foundation/Slab 2/6/2024 Approved THOMAS LOGRASSO
Green Building Final 2/6/2024 Not Ready for Inspection THOMAS LOGRASSO
Green Building Rough 2/6/2024 Approved THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 2/6/2024 SGSOV Approved THOMAS LOGRASSO
Smoke Detectors 2/6/2024 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 2/21/2024 Approved THOMAS LOGRASSO
Final 2/21/2024 OK to Issue CofO THOMAS LOGRASSO
Green Building Final 2/21/2024 Approved THOMAS LOGRASSO