6432 W 86TH PL 90045

Certificate Information: 6432 W 86TH PL 90045

Application / Permit
22014-10000-04334
Plan Check / Job No.
B22LA17258
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
EPLAN* NEW 13'-0" X 13'-0" ATTACHED COVERED PATIO AND 6'-0" X 5'-5" AND 25'-1" X 5'-9" ADDITIONS TO EXISTING DUPLEX - ALL WORK PER ENGINEER
Permit Issued
Issued on 10/6/2022
Issuing Office
Current Status
CofO Issued on 7/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/27/2022 APPLICANT
Assigned to Plan Check Engineer 9/2/2022 DANIEL ABRAMYAN
Corrections Issued 9/3/2022 DANIEL ABRAMYAN
Plan Check Approved 9/20/2022 DANIEL ABRAMYAN
Issued 10/6/2022 APPLICANT
CofO in Progress 7/5/2023 BOBBY KEY
Permit Finaled 7/8/2023 DANIEL ORRANTE
CofO Issued 7/8/2023 DANIEL ORRANTE
Permit Finaled 7/8/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/19/2022 DENNIS BRAGIN
Roof/Waste drainage to street Cleared 9/19/2022 DENNIS BRAGIN

Contact Information

Contractor Owner-Builder       ,
Engineer Reith,, David Lee; Lic. No.: C72122 1319 FEATHER AVE      THOUSAND OAKS, CA 91360

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/21/2022 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 10/28/2022 Partial Approval BOBBY KEY
Insulation 10/28/2022 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 11/16/2022 Approved BOBBY KEY
ELECTRICAL-Rough 12/14/2022 Approved BOBBY KEY
BUILDING-Rough-Frame 1/12/2023 Approved BOBBY KEY
Green Building Rough 1/12/2023 Approved BOBBY KEY
Interior/Exterior Lathing 1/12/2023 Approved BOBBY KEY
Rough-Elec/Plmb/HVAC 1/12/2023 Approved BOBBY KEY
Insulation 1/17/2023 Approved BOBBY KEY
Drywall Nailing 1/19/2023 Approved HERBERT GIRON
Insulation 1/19/2023 Approved HERBERT GIRON
ELECTRICAL-Final 3/13/2023 Approved BOBBY KEY
Final 3/13/2023 Corrections Issued BOBBY KEY
Final 7/5/2023 OK to Issue CofO BOBBY KEY
Footing/Foundation/Slab 7/5/2023 Approved BOBBY KEY
Green Building Final 7/5/2023 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 7/5/2023 SGSOV Approved BOBBY KEY
Service/Power Release 7/5/2023 Approved BOBBY KEY
Smoke Detectors 7/5/2023 Approved BOBBY KEY