6432 W 86TH PL 90045
Certificate Information: 6432 W 86TH PL 90045
- Application / Permit
- 22014-10000-04334
- Plan Check / Job No.
- B22LA17258
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- EPLAN* NEW 13'-0" X 13'-0" ATTACHED COVERED PATIO AND 6'-0" X 5'-5" AND 25'-1" X 5'-9" ADDITIONS TO EXISTING DUPLEX - ALL WORK PER ENGINEER
- Permit Issued
- Issued on 10/6/2022
- Issuing Office
- Current Status
- CofO Issued on 7/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/2/2022 | DANIEL ABRAMYAN |
| Corrections Issued | 9/3/2022 | DANIEL ABRAMYAN |
| Plan Check Approved | 9/20/2022 | DANIEL ABRAMYAN |
| Issued | 10/6/2022 | APPLICANT |
| CofO in Progress | 7/5/2023 | BOBBY KEY |
| Permit Finaled | 7/8/2023 | DANIEL ORRANTE |
| CofO Issued | 7/8/2023 | DANIEL ORRANTE |
| Permit Finaled | 7/8/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/19/2022 | DENNIS BRAGIN |
| Roof/Waste drainage to street | Cleared | 9/19/2022 | DENNIS BRAGIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Reith,, David Lee; Lic. No.: C72122 | 1319 FEATHER AVE THOUSAND OAKS, CA 91360 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/21/2022 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2022 | Partial Approval | BOBBY KEY |
| Insulation | 10/28/2022 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2022 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 12/14/2022 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 1/12/2023 | Approved | BOBBY KEY |
| Green Building Rough | 1/12/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 1/12/2023 | Approved | BOBBY KEY |
| Rough-Elec/Plmb/HVAC | 1/12/2023 | Approved | BOBBY KEY |
| Insulation | 1/17/2023 | Approved | BOBBY KEY |
| Drywall Nailing | 1/19/2023 | Approved | HERBERT GIRON |
| Insulation | 1/19/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 3/13/2023 | Approved | BOBBY KEY |
| Final | 3/13/2023 | Corrections Issued | BOBBY KEY |
| Final | 7/5/2023 | OK to Issue CofO | BOBBY KEY |
| Footing/Foundation/Slab | 7/5/2023 | Approved | BOBBY KEY |
| Green Building Final | 7/5/2023 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 7/5/2023 | SGSOV Approved | BOBBY KEY |
| Service/Power Release | 7/5/2023 | Approved | BOBBY KEY |
| Smoke Detectors | 7/5/2023 | Approved | BOBBY KEY |