4861 N ENFIELD AVE 91316

Certificate Information: 4861 N ENFIELD AVE 91316

Application / Permit
22014-10000-04323
Plan Check / Job No.
B22LA17233
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE ENTIRE SFD EXCEPT 35.33LF OF NORTH WALL & ADD 1-STORY SFD W/ ATTACHED 2-CAR GARAGE (NFPA-13D FIRE SPRINKLELRS THROUGHOUT)
Permit Issued
Issued on 12/20/2022
Issuing Office
Current Status
CofO Issued on 8/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/29/2022 APPLICANT
Assigned to Plan Check Engineer 9/1/2022 NILOOFAR MEHRAIN
Corrections Issued 9/6/2022 NILOOFAR MEHRAIN
Quality Review Completed 9/13/2022 STEVEN KIM
Applicant returned to address corrections 11/1/2022 NILOOFAR MEHRAIN
Applicant returned to address corrections 12/14/2022 NILOOFAR MEHRAIN
Plan Check Approved 12/19/2022 NILOOFAR MEHRAIN
Issued 12/20/2022 APPLICANT
CofO in Progress 8/23/2023 SEAN HAUPT
CofO Issued 8/29/2023 JOHN JANSON
Permit Finaled 8/29/2023 JOHN JANSON

Permit Application Clearance Information

Sewer availability Cleared 9/8/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 9/12/2022 CARLOS AGUILERA
Trees in Parkway Cleared 10/3/2022 ADALBERTO VERA
Hydrant and Access approval Cleared 10/8/2022 GILBERT URREA
Low Impact Development Cleared 10/12/2022 ROGELIO CORTES
Permit Cleared 10/13/2022 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 10/13/2022 LEE GUILBEAUX
GPI Written Notices Cleared 12/14/2022 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 12/14/2022 NILOOFAR MEHRAIN

Contact Information

Contractor Owner-Builder       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/29/2022 Corrections Issued SEAN HAUPT
Excavation/Setback/Form/Re-Bar 1/23/2023 Corrections Issued DAVID SANDOVAL
Footing/Foundation/Slab 1/26/2023 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 2/21/2023 Partial Inspection DAVID SANDOVAL
PLUMBING-Rough 2/21/2023 Corrections Issued DAVID SANDOVAL
PLUMBING-Rough 2/24/2023 Partial Approval DAVID SANDOVAL
Underground Mechanical 2/24/2023 Partial Approval DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 3/3/2023 Partial Approval DAVID SANDOVAL
Special/Order Compliance 3/3/2023 Partial Inspection MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 3/23/2023 Not Ready for Inspection DAVID SANDOVAL
Deputy Wood Construction 3/28/2023 Approved DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 3/28/2023 Approved DAVID SANDOVAL
PLUMBING-Rough 4/5/2023 Approved SEAN HAUPT
PLUMBING-Rough 4/10/2023 Not Ready for Inspection DAVID SANDOVAL
Special/Order Compliance 4/10/2023 Partial Inspection MORRIS JACKSON
HVAC-Rough 4/14/2023 Approved DAVID SANDOVAL
Interior/Exterior Lathing 4/14/2023 Partial Approval DAVID SANDOVAL
ELECTRICAL-Rough 4/18/2023 Approved DAVID SANDOVAL
Pre-Inspection 4/18/2023 Partial Inspection JUSTIN HAWLEY
Shower Pan 4/25/2023 Approved SEAN HAUPT
Special/Order Compliance 4/25/2023 Partial Inspection MORRIS JACKSON
Shower Pan 4/26/2023 Approved SEAN HAUPT
BUILDING-Rough-Frame 5/3/2023 Approved SEAN HAUPT
Green Building Rough 5/3/2023 Approved SEAN HAUPT
Insulation 5/3/2023 Approved SEAN HAUPT
Interior/Exterior Lathing 5/3/2023 Approved SEAN HAUPT
Verify Sprinkler Sign Off 5/3/2023 Approved SEAN HAUPT
Drywall Nailing 5/8/2023 Approved SEAN HAUPT
Deck 5/16/2023 Approved SEAN HAUPT
Final 7/14/2023 Corrections Issued SEAN HAUPT
Green Building Final 7/14/2023 Not Ready for Inspection SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 7/14/2023 SGSOV Approved SEAN HAUPT
Smoke Detectors 7/14/2023 Approved SEAN HAUPT
Final 8/22/2023 OK to Issue CofO SEAN HAUPT
Green Building Final 8/22/2023 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 8/22/2023 SGSOV Approved SEAN HAUPT
Service/Power Release 9/6/2023 Approved SEAN HAUPT