5642 N HALBRENT AVE 91411

Certificate Information: 5642 N HALBRENT AVE 91411

Application / Permit
22014-10000-04317
Plan Check / Job No.
B22LA17213
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan ADD 399 ft² TO ENLARGE LIVING ROOM & BEDROOM, ADD BATHROOM & ADD BEDROOM
Permit Issued
Issued on 11/28/2022
Issuing Office
Current Status
CofO Issued on 5/3/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/26/2022 APPLICANT
Assigned to Plan Check Engineer 9/1/2022 KHUONG TRUONG
Corrections Issued 9/2/2022 KHUONG TRUONG
Plan Check Approved 9/15/2022 KHUONG TRUONG
Issued 11/28/2022 APPLICANT
CofO in Progress 5/2/2023 RYAN SALAZAR
CofO Issued 5/3/2023 MICHAEL SMITH
Permit Finaled 5/3/2023 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/9/2022 ROMAN GUTIERREZ
Roof/Waste drainage to street Cleared 9/9/2022 ROMAN GUTIERREZ
ZI Cleared 9/13/2022 BRENNEN OBETO
Sewer availability Cleared 9/14/2022 ROMAN GUTIERREZ
ZI Cleared 9/14/2022 BRENNEN OBETO

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor L E A D Enterprises Inc; Lic. No.: 955824-B       ,
Contractor Pearl Remodeling; Lic. No.: 955824-B       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/16/2022 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 12/16/2022 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 1/3/2023 Partial Approval RYAN SALAZAR
PLUMBING-Rough 1/3/2023 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 1/19/2023 Partial Approval MATTHEW NELSON
ELECTRICAL-Rough 2/3/2023 Approved RYAN SALAZAR
PLUMBING-Rough 2/3/2023 Approved RYAN SALAZAR
Wood Frame 2/3/2023 Partial Approval RYAN SALAZAR
Deputy Wood Construction 2/6/2023 Conditional Approval ROBERT GOLD
Wood Frame 2/15/2023 Partial Approval MATTHEW NELSON
Insulation 2/17/2023 Approved DAVID ANDERSON
Drywall Nailing 2/23/2023 Approved RYAN SALAZAR
Shower Pan 2/23/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 3/3/2023 Approved RYAN SALAZAR
BUILDING-Rough-Frame 5/1/2023 Approved RYAN SALAZAR
Final 5/1/2023 OK to Issue CofO RYAN SALAZAR
Green Building Final 5/1/2023 Approved RYAN SALAZAR
Green Building Rough 5/1/2023 Approved RYAN SALAZAR
MERV13>=Final 5/1/2023 Approved RYAN SALAZAR
MERV13>=Rough 5/1/2023 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 5/1/2023 SGSOV Approved RYAN SALAZAR
Smoke Detectors 5/1/2023 Approved RYAN SALAZAR