5642 N HALBRENT AVE 91411
Certificate Information: 5642 N HALBRENT AVE 91411
- Application / Permit
- 22014-10000-04317
- Plan Check / Job No.
- B22LA17213
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan ADD 399 ft² TO ENLARGE LIVING ROOM & BEDROOM, ADD BATHROOM & ADD BEDROOM
- Permit Issued
- Issued on 11/28/2022
- Issuing Office
- Current Status
- CofO Issued on 5/3/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/1/2022 | KHUONG TRUONG |
| Corrections Issued | 9/2/2022 | KHUONG TRUONG |
| Plan Check Approved | 9/15/2022 | KHUONG TRUONG |
| Issued | 11/28/2022 | APPLICANT |
| CofO in Progress | 5/2/2023 | RYAN SALAZAR |
| CofO Issued | 5/3/2023 | MICHAEL SMITH |
| Permit Finaled | 5/3/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/9/2022 | ROMAN GUTIERREZ |
| Roof/Waste drainage to street | Cleared | 9/9/2022 | ROMAN GUTIERREZ |
| ZI | Cleared | 9/13/2022 | BRENNEN OBETO |
| Sewer availability | Cleared | 9/14/2022 | ROMAN GUTIERREZ |
| ZI | Cleared | 9/14/2022 | BRENNEN OBETO |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: C30383 | 5739 KANAN ROAD # 133 AGOURA HILLS, CA 91301 |
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | L E A D Enterprises Inc; Lic. No.: 955824-B | , |
| Contractor | Pearl Remodeling; Lic. No.: 955824-B | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/16/2022 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 12/16/2022 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 1/3/2023 | Partial Approval | RYAN SALAZAR |
| PLUMBING-Rough | 1/3/2023 | Partial Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 1/19/2023 | Partial Approval | MATTHEW NELSON |
| ELECTRICAL-Rough | 2/3/2023 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 2/3/2023 | Approved | RYAN SALAZAR |
| Wood Frame | 2/3/2023 | Partial Approval | RYAN SALAZAR |
| Deputy Wood Construction | 2/6/2023 | Conditional Approval | ROBERT GOLD |
| Wood Frame | 2/15/2023 | Partial Approval | MATTHEW NELSON |
| Insulation | 2/17/2023 | Approved | DAVID ANDERSON |
| Drywall Nailing | 2/23/2023 | Approved | RYAN SALAZAR |
| Shower Pan | 2/23/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 3/3/2023 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 5/1/2023 | Approved | RYAN SALAZAR |
| Final | 5/1/2023 | OK to Issue CofO | RYAN SALAZAR |
| Green Building Final | 5/1/2023 | Approved | RYAN SALAZAR |
| Green Building Rough | 5/1/2023 | Approved | RYAN SALAZAR |
| MERV13>=Final | 5/1/2023 | Approved | RYAN SALAZAR |
| MERV13>=Rough | 5/1/2023 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 5/1/2023 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 5/1/2023 | Approved | RYAN SALAZAR |