4510 N VESPER AVE 91403
Certificate Information: 4510 N VESPER AVE 91403
- Application / Permit
- 22014-10000-04296
- Plan Check / Job No.
- B22LA17133
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT GARAGE AND ADDITION INTO A.D.U. PER STATE LAW
- Permit Issued
- Issued on 9/19/2022
- Issuing Office
- Current Status
- CofO Issued on 9/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/29/2022 | LAWRENCE QUIRANTE |
| Corrections Issued | 9/1/2022 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 9/2/2022 | APPLICANT |
| Plan Check Approved | 9/19/2022 | FERNANDO FLORES |
| Issued | 9/19/2022 | APPLICANT |
| CofO in Progress | 9/11/2023 | MISAEL ESPARZA |
| Permit Finaled | 9/29/2023 | RUBEN SALAS |
| CofO Issued | 9/29/2023 | RUBEN SALAS |
| Permit Finaled | 9/29/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/1/2022 | COLIN LOREDO |
| Roof/Waste drainage to street | Cleared | 9/1/2022 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 9/2/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 9/2/2022 | COLIN LOREDO |
| Supp. Use District POD/CDO/TDO | Cleared | 9/6/2022 | LOUIS ORTEGA |
| Construction near power lines | Cleared | 9/16/2022 | WALTER RAMIREZ |
Contact Information
| Contractor | Precision Construction Experts Inc; Lic. No.: 1026997-B | 16656 CALLE ARBOLADA PACIFIC PALISADES, CA 90272 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/3/2022 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 10/3/2022 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 10/3/2022 | Partial Approval | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 10/7/2022 | No Access for Inspection | MISAEL ESPARZA |
| Footing/Foundation/Slab | 10/7/2022 | No Access for Inspection | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 10/13/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Footing/Foundation/Slab | 10/13/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 10/15/2022 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 10/15/2022 | Not Ready for Inspection | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 10/28/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 10/28/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 10/29/2022 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 12/5/2022 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 12/5/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 12/5/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 12/5/2022 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 12/8/2022 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 12/8/2022 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 12/14/2022 | No Access for Inspection | MISAEL ESPARZA |
| Green Building Rough | 12/14/2022 | No Access for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 12/14/2022 | No Access for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 12/23/2022 | Partial Approval | JACK KARGODORIAN |
| Wood Frame | 12/23/2022 | Corrections Issued | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 1/20/2023 | Approved | MISAEL ESPARZA |
| Green Building Rough | 1/20/2023 | Approved | MISAEL ESPARZA |
| Insulation | 1/20/2023 | Partial Approval | MISAEL ESPARZA |
| Interior/Exterior Lathing | 1/20/2023 | Partial Approval | MISAEL ESPARZA |
| Drywall Nailing | 1/24/2023 | Approved | MISAEL ESPARZA |
| Sewer | 4/20/2023 | Corrections Issued | MISAEL ESPARZA |
| Sewer | 4/25/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Underground Mechanical | 4/25/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Gas Test | 5/8/2023 | Corrections Issued | MISAEL ESPARZA |
| Sewer | 5/8/2023 | Approved | MISAEL ESPARZA |
| Gas Test | 5/15/2023 | Approved | MATTHEW NELSON |
| Sewer | 5/15/2023 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Final | 6/27/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Final | 6/27/2023 | Corrections Issued | JOHN COLEMAN |
| Green Building Final | 6/27/2023 | Corrections Issued | JOHN COLEMAN |
| HVAC-Final | 6/27/2023 | Corrections Issued | JOHN COLEMAN |
| PLUMBING-Final | 6/27/2023 | Approved | JOHN COLEMAN |
| SGSOV-Seismic Gas S/O Valve | 6/27/2023 | SGSOV Not Ready | JOHN COLEMAN |
| Service/Power Release | 6/27/2023 | Corrections Issued | JOHN COLEMAN |
| Smoke Detectors | 6/27/2023 | Corrections Issued | JOHN COLEMAN |
| HVAC-Final | 6/29/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Service/Power Release | 6/29/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Final | 7/20/2023 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 7/20/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 7/20/2023 | SGSOV Not Ready | MISAEL ESPARZA |
| Smoke Detectors | 7/20/2023 | Corrections Issued | MISAEL ESPARZA |
| Final | 8/7/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Final | 8/7/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 8/7/2023 | SGSOV Approved | MISAEL ESPARZA |
| Smoke Detectors | 8/7/2023 | Corrections Issued | MISAEL ESPARZA |
| Final | 8/31/2023 | OK to Issue CofO | MISAEL ESPARZA |
| Green Building Final | 8/31/2023 | Approved | MISAEL ESPARZA |
| Smoke Detectors | 8/31/2023 | Approved | MISAEL ESPARZA |