4510 N VESPER AVE 91403

Certificate Information: 4510 N VESPER AVE 91403

Application / Permit
22014-10000-04296
Plan Check / Job No.
B22LA17133
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT GARAGE AND ADDITION INTO A.D.U. PER STATE LAW
Permit Issued
Issued on 9/19/2022
Issuing Office
Current Status
CofO Issued on 9/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/25/2022 APPLICANT
Assigned to Plan Check Engineer 8/29/2022 LAWRENCE QUIRANTE
Corrections Issued 9/1/2022 LAWRENCE QUIRANTE
Building Plans Picked Up 9/2/2022 APPLICANT
Plan Check Approved 9/19/2022 FERNANDO FLORES
Issued 9/19/2022 APPLICANT
CofO in Progress 9/11/2023 MISAEL ESPARZA
Permit Finaled 9/29/2023 RUBEN SALAS
CofO Issued 9/29/2023 RUBEN SALAS
Permit Finaled 9/29/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/1/2022 COLIN LOREDO
Roof/Waste drainage to street Cleared 9/1/2022 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 9/2/2022 COLIN LOREDO
Sewer availability Cleared 9/2/2022 COLIN LOREDO
Supp. Use District POD/CDO/TDO Cleared 9/6/2022 LOUIS ORTEGA
Construction near power lines Cleared 9/16/2022 WALTER RAMIREZ

Contact Information

Contractor Precision Construction Experts Inc; Lic. No.: 1026997-B 16656 CALLE ARBOLADA      PACIFIC PALISADES, CA 90272
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/3/2022 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 10/3/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 10/3/2022 Partial Approval MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 10/7/2022 No Access for Inspection MISAEL ESPARZA
Footing/Foundation/Slab 10/7/2022 No Access for Inspection MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 10/13/2022 Not Ready for Inspection MISAEL ESPARZA
Footing/Foundation/Slab 10/13/2022 Not Ready for Inspection MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 10/15/2022 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 10/15/2022 Not Ready for Inspection RAUL OLAGI
Excavation/Setback/Form/Re-Bar 10/28/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Footing/Foundation/Slab 10/28/2022 Corrections Issued CHRISTOPHE COCHRAN
Footing/Foundation/Slab 10/29/2022 Approved RAUL OLAGI
BUILDING-Rough-Frame 12/5/2022 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 12/5/2022 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 12/5/2022 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 12/5/2022 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 12/8/2022 Approved MISAEL ESPARZA
PLUMBING-Rough 12/8/2022 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 12/14/2022 No Access for Inspection MISAEL ESPARZA
Green Building Rough 12/14/2022 No Access for Inspection MISAEL ESPARZA
PLUMBING-Rough 12/14/2022 No Access for Inspection MISAEL ESPARZA
PLUMBING-Rough 12/23/2022 Partial Approval JACK KARGODORIAN
Wood Frame 12/23/2022 Corrections Issued JACK KARGODORIAN
BUILDING-Rough-Frame 1/20/2023 Approved MISAEL ESPARZA
Green Building Rough 1/20/2023 Approved MISAEL ESPARZA
Insulation 1/20/2023 Partial Approval MISAEL ESPARZA
Interior/Exterior Lathing 1/20/2023 Partial Approval MISAEL ESPARZA
Drywall Nailing 1/24/2023 Approved MISAEL ESPARZA
Sewer 4/20/2023 Corrections Issued MISAEL ESPARZA
Sewer 4/25/2023 Not Ready for Inspection MISAEL ESPARZA
Underground Mechanical 4/25/2023 Not Ready for Inspection MISAEL ESPARZA
Gas Test 5/8/2023 Corrections Issued MISAEL ESPARZA
Sewer 5/8/2023 Approved MISAEL ESPARZA
Gas Test 5/15/2023 Approved MATTHEW NELSON
Sewer 5/15/2023 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Final 6/27/2023 Not Ready for Inspection JOHN COLEMAN
Final 6/27/2023 Corrections Issued JOHN COLEMAN
Green Building Final 6/27/2023 Corrections Issued JOHN COLEMAN
HVAC-Final 6/27/2023 Corrections Issued JOHN COLEMAN
PLUMBING-Final 6/27/2023 Approved JOHN COLEMAN
SGSOV-Seismic Gas S/O Valve 6/27/2023 SGSOV Not Ready JOHN COLEMAN
Service/Power Release 6/27/2023 Corrections Issued JOHN COLEMAN
Smoke Detectors 6/27/2023 Corrections Issued JOHN COLEMAN
HVAC-Final 6/29/2023 Not Ready for Inspection JOHN COLEMAN
Service/Power Release 6/29/2023 Not Ready for Inspection JOHN COLEMAN
Final 7/20/2023 Corrections Issued MISAEL ESPARZA
Green Building Final 7/20/2023 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 7/20/2023 SGSOV Not Ready MISAEL ESPARZA
Smoke Detectors 7/20/2023 Corrections Issued MISAEL ESPARZA
Final 8/7/2023 Not Ready for Inspection MISAEL ESPARZA
Green Building Final 8/7/2023 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 8/7/2023 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 8/7/2023 Corrections Issued MISAEL ESPARZA
Final 8/31/2023 OK to Issue CofO MISAEL ESPARZA
Green Building Final 8/31/2023 Approved MISAEL ESPARZA
Smoke Detectors 8/31/2023 Approved MISAEL ESPARZA