570 N LUCERNE BLVD 90004

Certificate Information: 570 N LUCERNE BLVD 90004

Application / Permit
22014-10000-04265
Plan Check / Job No.
B22LA16957
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND INTERIOR REMODEL TO EXISTING 2 STORY SINGLE FAMILY DEWLLING PER ENGINEER DEISGN
Permit Issued
Issued on 4/25/2023
Issuing Office
Metro
Current Status
CofO Issued on 3/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/24/2022 APPLICANT
Assigned to Plan Check Engineer 8/25/2022 AUNG SOE
Corrections Issued 8/29/2022 AUNG SOE
Building Plans Picked Up 8/31/2022 APPLICANT
Plan Check Approved 11/4/2022 KHUONG TRUONG
Issued 4/25/2023 APPLICANT
CofO in Progress 3/19/2024 JEFFREY MEAD
Permit Finaled 3/29/2024 DEROLD HAUFF
Permit Finaled 3/29/2024 DEROLD HAUFF
CofO Issued 3/29/2024 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/5/2022 JEANIE LAM
Roof/Waste drainage to street Cleared 10/5/2022 JEANIE LAM
Sewer availability Cleared 10/5/2022 JEANIE LAM

Contact Information

Contractor Pearson Management Services; Lic. No.: 885937-B PO BOX 50700      PASADENA, CA 91115
Engineer Garcia,, Francisco Javier; Lic. No.: C76510 2705 S FREMONT AVE APT D      ALHAMBRA, CA 91803

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/19/2023 Partial Approval JEFFREY MEAD
Excavation/Setback/Form/Re-Bar 5/23/2023 Approved JEFFREY MEAD
Footing/Foundation/Slab 5/23/2023 Approved JEFFREY MEAD
METHANE-Barrier 5/23/2023 Approved JEFFREY MEAD
METHANE-Subgrade 5/23/2023 Approved JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 8/14/2023 Partial Approval SCOTT FINNILA
Rough-Elec/Plmb/HVAC 8/14/2023 Approved SCOTT FINNILA
BUILDING-Rough-Frame 8/17/2023 Partial Approval JEFFREY MEAD
Green Building Rough 8/17/2023 Approved JEFFREY MEAD
METHANE-Rough 8/17/2023 Approved JEFFREY MEAD
Deputy Wood Construction 8/21/2023 Partial Approval JEFFREY MEAD
BUILDING-Rough-Frame 8/24/2023 Approved JEFFREY MEAD
Insulation 8/24/2023 Approved JEFFREY MEAD
Drywall Nailing 9/5/2023 Approved JEFFREY MEAD
Shower Pan 9/5/2023 Approved JEFFREY MEAD
Interior/Exterior Lathing 10/2/2023 Partial Approval JEFFREY MEAD
Interior/Exterior Lathing 11/7/2023 Approved JEFFREY MEAD
Rough-Elec/Plmb/HVAC 12/12/2023 Approved JEFFREY MEAD
Rough-Elec/Plmb/HVAC 12/13/2023 Approved JEFFREY MEAD
Wood Frame 12/13/2023 Approved JEFFREY MEAD
Drywall Nailing 12/21/2023 Approved JEFFREY MEAD
Insulation 12/21/2023 Approved JEFFREY MEAD
Interior/Exterior Lathing 1/3/2024 Approved JEFFREY MEAD
Final 2/8/2024 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 2/8/2024 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 2/8/2024 SGSOV Approved ALIZAH MAYAGOITIA
Smoke Detectors 2/8/2024 Approved ALIZAH MAYAGOITIA
Final 3/18/2024 OK to Issue CofO JEFFREY MEAD