1283 S SYCAMORE AVE 90019

Certificate Information: 1283 S SYCAMORE AVE 90019

Application / Permit
22014-10000-04260
Plan Check / Job No.
B22LA16936
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT EXISTING 2-STORY DUPLEX INTO SFD. INCLUDES NEW ATTACHED DECK AT REAR AND ENCLOSURE OF FRONT EXTERIOR STAIRS.
Permit Issued
Issued on 9/30/2022
Issuing Office
Metro
Current Status
CofO Issued on 10/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/23/2022 APPLICANT
Assigned to Plan Check Engineer 8/25/2022 LAWRENCE QUIRANTE
Corrections Issued 8/27/2022 LAWRENCE QUIRANTE
Building Plans Picked Up 8/31/2022 APPLICANT
Plan Check Approved 9/30/2022 LAWRENCE QUIRANTE
Issued 9/30/2022 APPLICANT
CofO in Progress 10/12/2023 CALEB MEISTER
Permit Finaled 10/24/2023 DEROLD HAUFF
CofO Issued 10/24/2023 DEROLD HAUFF
Permit Finaled 10/24/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/7/2022 CINDY QI
Roof/Waste drainage to street Cleared 9/7/2022 CINDY QI
Sewer availability Cleared 9/7/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 9/8/2022 CINDY QI
Tenant Habitability Plan Cleared 9/13/2022 ISMAEL HERNANDEZ

Contact Information

Contractor Marquel Group Inc; Lic. No.: 1059595-B 5231 VIRGINIA AVE      LOS ANGELES, CA 90029
Engineer Nguyen,, Tuan Minh; Lic. No.: S5883 5552 W 123RD PLACE      HAWTHORNE, CA 90250

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/21/2022 Approved STUART CHAPMAN
Footing/Foundation/Slab 10/21/2022 Approved STUART CHAPMAN
METHANE-Barrier 10/21/2022 Approved STUART CHAPMAN
METHANE-Subgrade 10/21/2022 Approved STUART CHAPMAN
Footing/Foundation/Slab 10/26/2022 Approved RUBEN SALAS
Deputy Drilled-In Anchors 11/10/2022 Conditional Approval STUART CHAPMAN
Deputy Drilled-In Anchors 1/18/2023 Conditional Approval CALEB MEISTER
Deputy Wood Construction 5/10/2023 Conditional Approval CALEB MEISTER
BUILDING-Rough-Frame 5/18/2023 Approved CALEB MEISTER
Floor/Roof Diaphrgm/Shear Wall 5/18/2023 Approved CALEB MEISTER
Green Building Rough 5/18/2023 Not Ready for Inspection CALEB MEISTER
METHANE-Rough 5/18/2023 Approved CALEB MEISTER
ELECTRICAL-Rough 5/19/2023 Approved CALEB MEISTER
HVAC-Rough 5/19/2023 Approved CALEB MEISTER
Gas Test 5/26/2023 Approved CALEB MEISTER
Green Building Rough 5/26/2023 Not Ready for Inspection CALEB MEISTER
PLUMBING-Rough 5/26/2023 Approved CALEB MEISTER
Insulation 6/1/2023 Approved CALEB MEISTER
Shower Pan 6/1/2023 Approved CALEB MEISTER
BUILDING-Rough-Frame 6/8/2023 Approved CALEB MEISTER
Drywall Nailing 6/8/2023 Approved CALEB MEISTER
Green Building Rough 6/8/2023 Approved CALEB MEISTER
Interior/Exterior Lathing 6/8/2023 Approved CALEB MEISTER
Final 10/3/2023 Not Ready for Inspection CALEB MEISTER
Green Building Final 10/3/2023 Approved CALEB MEISTER
SGSOV-Seismic Gas S/O Valve 10/3/2023 SGSOV Approved CALEB MEISTER
Service/Power Release 10/3/2023 Approved CALEB MEISTER
Smoke Detectors 10/3/2023 Approved CALEB MEISTER
Final 10/6/2023 Corrections Issued CALEB MEISTER
ELECTRICAL-Final 10/11/2023 Approved CALEB MEISTER
Final 10/11/2023 OK to Issue CofO CALEB MEISTER
HVAC-Final 10/11/2023 Approved CALEB MEISTER
PLUMBING-Final 10/11/2023 Approved CALEB MEISTER