2908 1/2 S 8TH AVE 90018

Certificate Information: 2908 1/2 S 8TH AVE 90018

Application / Permit
22014-10000-04240
Plan Check / Job No.
B22LA16857
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION AND CONVERSION OF EXISTING DETACHED GARAGE (277SF) INTO ADU PER (800 SF max New Construction per State Law, CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)).
Permit Issued
Issued on 11/17/2022
Issuing Office
Valley
Current Status
CofO Issued on 10/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/22/2022 APPLICANT
Assigned to Plan Check Engineer 8/25/2022 AUNG SOE
Corrections Issued 8/29/2022 AUNG SOE
Building Plans Picked Up 9/2/2022 APPLICANT
Applicant returned to address corrections 9/8/2022 LUKE GONZALES
Plan Check Approved 9/13/2022 CRISTINA SALAZAR
Issued 11/17/2022 APPLICANT
CofO in Progress 10/16/2023 CALEB MEISTER
Permit Finaled 10/24/2023 DEROLD HAUFF
Permit Finaled 10/24/2023 DEROLD HAUFF
CofO Issued 10/24/2023 DEROLD HAUFF

Permit Application Clearance Information

Tenant Habitability Plan Cleared 8/30/2022 ISMAEL HERNANDEZ
Address approval Cleared 9/1/2022 JEANETTE VONG
Roof/Waste drainage to street Cleared 9/1/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 9/2/2022 JEANETTE VONG
Sewer availability Cleared 9/2/2022 JEANETTE VONG

Contact Information

Contractor Owner-Builder       ,
Engineer Wu,, Harold Ping-Hung; Lic. No.: C35693 1168 SAN GABRIEL BLVD NO N      ROSEMEAD, CA 91770

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/10/2023 Conditional Approval CALEB MEISTER
Footing/Foundation/Slab 3/23/2023 Corrections Issued CALEB MEISTER
PLUMBING-Rough 3/23/2023 Partial Approval CALEB MEISTER
Sewer 3/23/2023 Not Ready for Inspection CALEB MEISTER
Footing/Foundation/Slab 4/11/2023 Approved CALEB MEISTER
Sewer 4/11/2023 Approved CALEB MEISTER
BUILDING-Rough-Frame 5/1/2023 Not Ready for Inspection CALEB MEISTER
ELECTRICAL-Rough 5/1/2023 Corrections Issued CALEB MEISTER
Floor/Roof Diaphrgm/Shear Wall 5/1/2023 Approved CALEB MEISTER
Gas Test 5/1/2023 Approved CALEB MEISTER
Green Building Rough 5/1/2023 Not Ready for Inspection CALEB MEISTER
HVAC-Rough 5/1/2023 Corrections Issued CALEB MEISTER
PLUMBING-Rough 5/1/2023 Corrections Issued CALEB MEISTER
Wood Frame 5/1/2023 Not Ready for Inspection CALEB MEISTER
BUILDING-Rough-Frame 5/4/2023 Approved CALEB MEISTER
ELECTRICAL-Rough 5/4/2023 Approved CALEB MEISTER
Green Building Rough 5/4/2023 Not Ready for Inspection CALEB MEISTER
PLUMBING-Rough 5/4/2023 Approved CALEB MEISTER
Rough-Elec/Plmb/HVAC 5/4/2023 Approved CALEB MEISTER
Sewer 5/4/2023 Approved CALEB MEISTER
Wood Frame 5/4/2023 Approved CALEB MEISTER
BUILDING-Rough-Frame 5/16/2023 Conditional Approval CALEB MEISTER
Green Building Rough 5/16/2023 Approved CALEB MEISTER
Insulation 5/16/2023 Corrections Issued CALEB MEISTER
Interior/Exterior Lathing 5/16/2023 Partial Approval CALEB MEISTER
Drywall Nailing 5/25/2023 Approved CALEB MEISTER
Sewer 6/30/2023 Approved CALEB MEISTER
Final 7/14/2023 Corrections Issued CALEB MEISTER
Green Building Final 7/14/2023 Not Ready for Inspection CALEB MEISTER
SGSOV-Seismic Gas S/O Valve 7/14/2023 SGSOV Approved CALEB MEISTER
Smoke Detectors 7/14/2023 Approved CALEB MEISTER
Final 9/27/2023 Conditional Approval CALEB MEISTER
Green Building Final 9/27/2023 Approved CALEB MEISTER
Final 10/10/2023 OK to Issue CofO CALEB MEISTER