1111 E INDIANA AVE 90291
Certificate Information: 1111 E INDIANA AVE 90291
- Application / Permit
- 22014-10000-04233
- Plan Check / Job No.
- B22LA16812
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan 1. RENOVATIONS AT AN EXISTING ONE-STORY 1,225 SQ.FT. SINGLE FAMILY DWELLING INCLUDES; MAJOR RENOVATIONS AT AN EXISTING FIRST FLOOR 390 SQ.FT. ADDITION TO AN EXISTING FIRST FLOOR NEW 625 SQ.FT. SECOND STORY ADDITION.
- Permit Issued
- Issued on 7/19/2023
- Issuing Office
- Current Status
- CofO Issued on 11/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/25/2022 | VARAND SARKISIAN |
| Corrections Issued | 8/30/2022 | VARAND SARKISIAN |
| Quality Review Completed | 9/4/2022 | PRANITA SHAH |
| Applicant returned to address corrections | 10/20/2022 | VARAND SARKISIAN |
| Plan Check Approved | 3/30/2023 | VARAND SARKISIAN |
| Issued | 7/19/2023 | APPLICANT |
| CofO in Progress | 11/7/2025 | JESUS RODRIGUEZ |
| Permit Finaled | 11/10/2025 | RICHARD STEINBACH |
| CofO Issued | 11/10/2025 | RICHARD STEINBACH |
| Permit Finaled | 11/10/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Specific Plan | Cleared | 9/19/2022 | FREDDY GARCIA |
| Hydrant and Access approval | Cleared | 10/7/2022 | RUEL COLE |
| Low Impact Development | Cleared | 2/22/2023 | AMMAR ELTAWIL |
| Eng Process Fee Ord 176,300 | Cleared | 2/27/2023 | JENSON LEE |
| Roof/Waste drainage to street | Cleared | 2/27/2023 | JENSON LEE |
Contact Information
| Contractor | Ciccone Builders Inc; Lic. No.: 850466-B | , |
| Engineer | Yaprak,, Taskin Tolga; Lic. No.: C72927 | 560 31ST ST MANHATTAN BEACH, CA 90266 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/7/2023 | Conditional Approval | HERBERT GIRON |
| Deputy Drilled-In Anchors | 9/27/2023 | Conditional Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 9/29/2023 | Partial Approval | HERBERT GIRON |
| Deputy Drilled-In Anchors | 10/4/2023 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 11/14/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2023 | Partial Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 11/14/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 11/14/2023 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2023 | Partial Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 4/9/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2024 | Partial Approval | HERBERT GIRON |
| HVAC-Rough | 4/11/2024 | Not Ready for Inspection | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2024 | Partial Approval | HERBERT GIRON |
| HVAC-Rough | 6/6/2024 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 11/25/2024 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 12/9/2024 | Not Ready for Inspection | HERBERT GIRON |
| ELECTRICAL-Rough | 12/9/2024 | Not Ready for Inspection | HERBERT GIRON |
| Green Building Rough | 12/9/2024 | Not Ready for Inspection | HERBERT GIRON |
| Verify Sprinkler Sign Off | 12/9/2024 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 12/19/2024 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Rough | 12/19/2024 | Conditional Approval | MICHAEL ALLEN |
| Green Building Rough | 12/19/2024 | Approved | MICHAEL ALLEN |
| Insulation | 1/31/2025 | Corrections Issued | BOBBY KEY |
| Interior/Exterior Lathing | 1/31/2025 | Corrections Issued | BOBBY KEY |
| HVAC-Rough | 2/14/2025 | Corrections Issued | HERBERT GIRON |
| Insulation | 2/14/2025 | Corrections Issued | HERBERT GIRON |
| Interior/Exterior Lathing | 2/14/2025 | Partial Approval | HERBERT GIRON |
| HVAC-Rough | 2/24/2025 | Approved | HERBERT GIRON |
| Insulation | 2/24/2025 | Partial Approval | HERBERT GIRON |
| Drywall Nailing | 3/3/2025 | Partial Approval | HERBERT GIRON |
| Interior/Exterior Lathing | 3/3/2025 | Not Ready for Inspection | HERBERT GIRON |
| Interior/Exterior Lathing | 3/7/2025 | Approved | HERBERT GIRON |
| Shower Pan | 3/7/2025 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 6/23/2025 | Corrections Issued | JESUS RODRIGUEZ |
| Underground Mechanical | 6/23/2025 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 6/25/2025 | Approved | JESUS RODRIGUEZ |
| Gas Test | 8/5/2025 | Approved | MICHAEL ALLEN |
| HVAC-Final | 8/5/2025 | Corrections Issued | MICHAEL ALLEN |
| PLUMBING-Final | 8/5/2025 | Not Ready for Inspection | MICHAEL ALLEN |
| HVAC-Final | 8/29/2025 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Final | 8/29/2025 | Corrections Issued | JESUS RODRIGUEZ |
| Service/Power Release | 9/22/2025 | Approved | JESUS RODRIGUEZ |
| Final | 10/29/2025 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Final | 10/29/2025 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 10/29/2025 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 10/29/2025 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 10/29/2025 | SGSOV Not Ready | JESUS RODRIGUEZ |
| Smoke Detectors | 10/29/2025 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Final | 11/5/2025 | OK to Issue CofO | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 11/5/2025 | SGSOV Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 11/5/2025 | Approved | JESUS RODRIGUEZ |