1111 E INDIANA AVE 90291

Certificate Information: 1111 E INDIANA AVE 90291

Application / Permit
22014-10000-04233
Plan Check / Job No.
B22LA16812
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan 1. RENOVATIONS AT AN EXISTING ONE-STORY 1,225 SQ.FT. SINGLE FAMILY DWELLING INCLUDES; MAJOR RENOVATIONS AT AN EXISTING FIRST FLOOR 390 SQ.FT. ADDITION TO AN EXISTING FIRST FLOOR NEW 625 SQ.FT. SECOND STORY ADDITION.
Permit Issued
Issued on 7/19/2023
Issuing Office
Current Status
CofO Issued on 11/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/22/2022 APPLICANT
Assigned to Plan Check Engineer 8/25/2022 VARAND SARKISIAN
Corrections Issued 8/30/2022 VARAND SARKISIAN
Quality Review Completed 9/4/2022 PRANITA SHAH
Applicant returned to address corrections 10/20/2022 VARAND SARKISIAN
Plan Check Approved 3/30/2023 VARAND SARKISIAN
Issued 7/19/2023 APPLICANT
CofO in Progress 11/7/2025 JESUS RODRIGUEZ
Permit Finaled 11/10/2025 RICHARD STEINBACH
CofO Issued 11/10/2025 RICHARD STEINBACH
Permit Finaled 11/10/2025 RICHARD STEINBACH

Permit Application Clearance Information

Specific Plan Cleared 9/19/2022 FREDDY GARCIA
Hydrant and Access approval Cleared 10/7/2022 RUEL COLE
Low Impact Development Cleared 2/22/2023 AMMAR ELTAWIL
Eng Process Fee Ord 176,300 Cleared 2/27/2023 JENSON LEE
Roof/Waste drainage to street Cleared 2/27/2023 JENSON LEE

Contact Information

Contractor Ciccone Builders Inc; Lic. No.: 850466-B       ,
Engineer Yaprak,, Taskin Tolga; Lic. No.: C72927 560 31ST ST      MANHATTAN BEACH, CA 90266

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/7/2023 Conditional Approval HERBERT GIRON
Deputy Drilled-In Anchors 9/27/2023 Conditional Approval HERBERT GIRON
Footing/Foundation/Slab 9/29/2023 Partial Approval HERBERT GIRON
Deputy Drilled-In Anchors 10/4/2023 Approved HERBERT GIRON
BUILDING-Rough-Frame 11/14/2023 Corrections Issued JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 11/14/2023 Partial Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 11/14/2023 Approved JESUS RODRIGUEZ
PLUMBING-Rough 11/14/2023 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 11/22/2023 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 12/1/2023 Corrections Issued HERBERT GIRON
HVAC-Rough 4/9/2024 Corrections Issued TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 4/11/2024 Partial Approval HERBERT GIRON
HVAC-Rough 4/11/2024 Not Ready for Inspection HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 4/12/2024 Partial Approval HERBERT GIRON
HVAC-Rough 6/6/2024 Approved JESUS RODRIGUEZ
PLUMBING-Rough 11/25/2024 Approved HERBERT GIRON
BUILDING-Rough-Frame 12/9/2024 Not Ready for Inspection HERBERT GIRON
ELECTRICAL-Rough 12/9/2024 Not Ready for Inspection HERBERT GIRON
Green Building Rough 12/9/2024 Not Ready for Inspection HERBERT GIRON
Verify Sprinkler Sign Off 12/9/2024 Approved HERBERT GIRON
BUILDING-Rough-Frame 12/19/2024 Approved MICHAEL ALLEN
ELECTRICAL-Rough 12/19/2024 Conditional Approval MICHAEL ALLEN
Green Building Rough 12/19/2024 Approved MICHAEL ALLEN
Insulation 1/31/2025 Corrections Issued BOBBY KEY
Interior/Exterior Lathing 1/31/2025 Corrections Issued BOBBY KEY
HVAC-Rough 2/14/2025 Corrections Issued HERBERT GIRON
Insulation 2/14/2025 Corrections Issued HERBERT GIRON
Interior/Exterior Lathing 2/14/2025 Partial Approval HERBERT GIRON
HVAC-Rough 2/24/2025 Approved HERBERT GIRON
Insulation 2/24/2025 Partial Approval HERBERT GIRON
Drywall Nailing 3/3/2025 Partial Approval HERBERT GIRON
Interior/Exterior Lathing 3/3/2025 Not Ready for Inspection HERBERT GIRON
Interior/Exterior Lathing 3/7/2025 Approved HERBERT GIRON
Shower Pan 3/7/2025 Approved HERBERT GIRON
ELECTRICAL-Final 6/23/2025 Corrections Issued JESUS RODRIGUEZ
Underground Mechanical 6/23/2025 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 6/25/2025 Approved JESUS RODRIGUEZ
Gas Test 8/5/2025 Approved MICHAEL ALLEN
HVAC-Final 8/5/2025 Corrections Issued MICHAEL ALLEN
PLUMBING-Final 8/5/2025 Not Ready for Inspection MICHAEL ALLEN
HVAC-Final 8/29/2025 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Final 8/29/2025 Corrections Issued JESUS RODRIGUEZ
Service/Power Release 9/22/2025 Approved JESUS RODRIGUEZ
Final 10/29/2025 Corrections Issued JESUS RODRIGUEZ
Green Building Final 10/29/2025 Approved JESUS RODRIGUEZ
HVAC-Final 10/29/2025 Approved JESUS RODRIGUEZ
PLUMBING-Final 10/29/2025 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 10/29/2025 SGSOV Not Ready JESUS RODRIGUEZ
Smoke Detectors 10/29/2025 Not Ready for Inspection JESUS RODRIGUEZ
Final 11/5/2025 OK to Issue CofO JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 11/5/2025 SGSOV Approved JESUS RODRIGUEZ
Smoke Detectors 11/5/2025 Approved JESUS RODRIGUEZ