7031 N SHIRLEY AVE 91335
Certificate Information: 7031 N SHIRLEY AVE 91335
- Application / Permit
- 22014-10000-04227
- Plan Check / Job No.
- B22LA16794
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION AND CONVERSION EXISTING DETACGED GARAGE WITH ATTACHED PATIO TO AN ADU. PER LAMC 12.22 A.33 (c)(d) ALL WORK DONE PER ENGINEERING
- Permit Issued
- Issued on 2/17/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/22/2022 | KHUONG TRUONG |
| Corrections Issued | 8/24/2022 | KHUONG TRUONG |
| Building Plans Picked Up | 9/16/2022 | APPLICANT |
| Applicant returned to address corrections | 11/15/2022 | LUKE GONZALES |
| Plan Check Approved | 2/17/2023 | DANIEL SMILEY |
| Issued | 2/17/2023 | APPLICANT |
| CofO in Progress | 12/8/2023 | JEFFREY BULL |
| Permit Finaled | 7/23/2024 | JOHN JANSON |
| CofO Issued | 7/23/2024 | JOHN JANSON |
| Permit Finaled | 7/23/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/30/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/4/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 10/4/2022 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 10/4/2022 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 10/4/2022 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 10/4/2022 | MEGAN GODINEZ |
| ZI | Cleared | 10/13/2022 | RYAN LY |
| Roof/Waste drainage to street | Cleared | 12/20/2022 | JOHN LIN |
| Construction near power lines | Cleared | 2/11/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 7/25/2023 | Approved | JEFFREY BULL |
| Footing/Foundation/Slab | 7/27/2023 | Approved | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2023 | Approved | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2023 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 8/22/2023 | Partial Approval | JEFFREY BULL |
| BUILDING-Rough-Frame | 9/1/2023 | Approved | JEFFREY BULL |
| ELECTRICAL-Rough | 9/1/2023 | Approved | JEFFREY BULL |
| Green Building Rough | 9/1/2023 | Approved | JEFFREY BULL |
| HVAC-Rough | 9/1/2023 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 9/1/2023 | Approved | JEFFREY BULL |
| Wood Frame | 9/1/2023 | Approved | JEFFREY BULL |
| Insulation | 9/6/2023 | Approved | JUSTIN HAWLEY |
| Drywall Nailing | 9/11/2023 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 9/11/2023 | Approved | HENRY KIM |
| ELECTRICAL-Final | 12/7/2023 | Approved | JEFFREY BULL |
| Final | 12/7/2023 | OK to Issue CofO | JEFFREY BULL |
| Green Building Final | 12/7/2023 | Approved | JEFFREY BULL |
| HVAC-Final | 12/7/2023 | Approved | JEFFREY BULL |
| PLUMBING-Final | 12/7/2023 | Approved | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 12/7/2023 | SGSOV Approved | JEFFREY BULL |
| Service/Power Release | 12/7/2023 | Approved | JEFFREY BULL |
| Smoke Detectors | 12/7/2023 | Approved | JEFFREY BULL |