2368-2370 N HIDALGO AVE 90039

Certificate Information: 2368-2370 N HIDALGO AVE 90039

Application / Permit
22014-10000-04225
Plan Check / Job No.
B22LA16777
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan Convert existing 406.66 sq ft portion of Single Family Dwelling to an ADU per CA Govt. Code 65852.2(e)(1)(A) & convert (E) flat roof of existing attached garage to walking deck by adding Guard rails
Permit Issued
Issued on 1/7/2024
Issuing Office
Current Status
CofO Issued on 7/5/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/22/2022 APPLICANT
Assigned to Plan Check Engineer 9/6/2022 HANS SANTIAGO
Corrections Issued 9/7/2022 HANS SANTIAGO
Quality Review Completed 9/7/2022 LIPING TENG
Applicant returned to address corrections 12/7/2023 HANS SANTIAGO
Plan Check Approved 1/3/2024 ANDREW SANTIAGO
Issued 1/7/2024 APPLICANT
Issued 1/7/2024 SUYA LY
CofO in Progress 7/3/2025 HAMIK HARTOUNIAN
Permit Finaled 7/5/2025 DEROLD HAUFF
CofO Issued 7/5/2025 DEROLD HAUFF
Permit Finaled 7/5/2025 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 9/27/2022 KIRK LINKLATER
Address approval Cleared 5/27/2023 STEVE MELGAR
Sewer availability Cleared 5/27/2023 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 6/22/2023 STEVE MELGAR

Contact Information

Architect Diradourian,, Richard C; Lic. No.: NA10336       ,
Contractor Owner-Builder       ,

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/2/2024 Not Ready for Inspection THOMAS LOGRASSO
Pre-Inspection 2/13/2024 Partial Inspection THOMAS LOGRASSO
Footing/Foundation/Slab 10/1/2024 Corrections Issued HAMIK HARTOUNIAN
Deck 10/24/2024 Corrections Issued HAMIK HARTOUNIAN
Pre-Inspection 12/10/2024 Partial Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 12/17/2024 Approved HAMIK HARTOUNIAN
Pre-Inspection 12/20/2024 Partial Inspection OSVALDO PARAMO
Pre-Inspection 1/15/2025 Partial Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 2/3/2025 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 2/3/2025 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 2/10/2025 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Rough 2/10/2025 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 2/21/2025 Approved HAMIK HARTOUNIAN
HVAC-Rough 2/21/2025 Approved HAMIK HARTOUNIAN
Insulation 2/21/2025 Approved HAMIK HARTOUNIAN
Drywall Nailing 3/4/2025 Approved JOSH MEISTER
Interior/Exterior Lathing 3/4/2025 Approved JOSH MEISTER
Final 4/16/2025 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 4/16/2025 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 4/16/2025 Approved HAMIK HARTOUNIAN
HVAC-Final 6/16/2025 Corrections Issued HAMIK HARTOUNIAN
Final 7/1/2025 OK to Issue CofO HAMIK HARTOUNIAN