5177 W 21ST ST 90016
Certificate Information: 5177 W 21ST ST 90016
- Application / Permit
- 22014-10000-04224
- Plan Check / Job No.
- B22LA16776
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan CONVERT + ADDITION OF (E) DETACHED GARAGE TO NEW ADU WITH ATTACHED STORAGE PER LAMC 12.22 A.33 (c)(d) ALL WORK DONE PER WFPP
- Permit Issued
- Issued on 12/18/2022
- Issuing Office
- Current Status
- CofO Issued on 11/11/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2022 | KHUONG TRUONG |
| Corrections Issued | 8/28/2022 | KHUONG TRUONG |
| Plan Check Approved | 10/6/2022 | KHUONG TRUONG |
| Issued | 12/18/2022 | APPLICANT |
| CofO in Progress | 9/26/2024 | ARTHUR NEGRETE |
| Permit Finaled | 11/11/2024 | DEROLD HAUFF |
| CofO Issued | 11/11/2024 | DEROLD HAUFF |
| Permit Finaled | 11/11/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/14/2022 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 9/14/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 10/3/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 10/3/2022 | STEVE MELGAR |
Contact Information
| Contractor | Espino Roberto; Lic. No.: 924261-B | , |
| Contractor | Marb Construction Management; Lic. No.: 924261-B | , |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/21/2022 | No Access for Inspection | JOSE AVILA |
| Sewer | 12/21/2022 | No Access for Inspection | JOSE AVILA |
| Pre-Inspection | 12/22/2022 | Approved | JOSE AVILA |
| Footing/Foundation/Slab | 2/2/2023 | Corrections Issued | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 2/13/2023 | Corrections Issued | JOSE AVILA |
| Special/Order Compliance | 2/13/2023 | Corrections Issued | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 4/7/2023 | Conditional Approval | JOSE AVILA |
| ELECTRICAL-Rough | 8/29/2023 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2023 | Partial Approval | STUART CHAPMAN |
| HVAC-Rough | 8/29/2023 | Corrections Issued | STUART CHAPMAN |
| PLUMBING-Rough | 8/29/2023 | Approved | STUART CHAPMAN |
| Wood Frame | 8/29/2023 | Corrections Issued | STUART CHAPMAN |
| BUILDING-Rough-Frame | 9/25/2023 | Corrections Issued | JOSE AVILA |
| Interior/Exterior Lathing | 10/16/2023 | Partial Approval | LILIANA PORTILLO |
| HVAC-Rough | 10/18/2023 | Corrections Issued | JOSE AVILA |
| Gas Test | 11/3/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| Underground Mechanical | 11/3/2023 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 11/13/2023 | Approved | JOSE AVILA |
| Green Building Rough | 11/13/2023 | Approved | JOSE AVILA |
| HVAC-Rough | 11/13/2023 | Approved | JOSE AVILA |
| Insulation | 11/27/2023 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 12/4/2023 | Approved | RONNIE MINDANAO |
| Sewer | 12/13/2023 | Approved | RONNIE MINDANAO |
| Shower Pan | 12/13/2023 | Approved | RONNIE MINDANAO |
| Underground Mechanical | 3/11/2024 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Final | 6/5/2024 | Corrections Issued | ARTHUR NEGRETE |
| HVAC-Final | 6/5/2024 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 6/5/2024 | Corrections Issued | ARTHUR NEGRETE |
| Service/Power Release | 6/5/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| ELECTRICAL-Final | 6/18/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| ELECTRICAL-Rough | 6/18/2024 | Approved | ARTHUR NEGRETE |
| Service/Power Release | 6/18/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| ELECTRICAL-Rough | 7/2/2024 | Corrections Issued | AMIR NAZARIAN |
| Service/Power Release | 7/2/2024 | Corrections Issued | AMIR NAZARIAN |
| Final | 8/1/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| Footing/Foundation/Slab | 8/1/2024 | Approved | ARTHUR NEGRETE |
| Green Building Final | 8/1/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 8/1/2024 | SGSOV Not Ready | ARTHUR NEGRETE |
| Smoke Detectors | 8/1/2024 | Partial Approval | ARTHUR NEGRETE |
| Final | 8/7/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| Green Building Final | 8/7/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| PLUMBING-Final | 8/7/2024 | Approved | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 8/7/2024 | SGSOV Approved | ARTHUR NEGRETE |
| Smoke Detectors | 8/7/2024 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Final | 8/15/2024 | Approved | ARTHUR NEGRETE |
| Final | 8/15/2024 | Partial Inspection | ARTHUR NEGRETE |
| Green Building Final | 8/15/2024 | Approved | ARTHUR NEGRETE |
| Final | 9/3/2024 | Corrections Issued | RONNIE MINDANAO |
| Service/Power Release | 9/3/2024 | Corrections Issued | RONNIE MINDANAO |
| Final | 9/25/2024 | OK to Issue CofO | ARTHUR NEGRETE |
| Service/Power Release | 9/25/2024 | Approved | ARTHUR NEGRETE |