1165 S ROSALIND AVE 90023

Certificate Information: 1165 S ROSALIND AVE 90023

Application / Permit
22014-10000-04223
Plan Check / Job No.
B22LA16774
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. Addition to & Conversion of existing 1-story Detached Garage to 2-story Accessory Dwelling Unit
Permit Issued
Issued on 3/7/2023
Issuing Office
Current Status
CofO Issued on 2/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/22/2022 APPLICANT
Assigned to Plan Check Engineer 9/2/2022 KELVIN CHUONG
Corrections Issued 9/7/2022 PRANITA SHAH
Quality Review Completed 9/23/2022 MICHAEL PEREZ
Applicant returned to address corrections 12/13/2022 KELVIN CHUONG
Applicant returned to address corrections 1/31/2023 KELVIN CHUONG
Applicant returned to address corrections 2/8/2023 KELVIN CHUONG
Applicant returned to address corrections 2/22/2023 KELVIN CHUONG
Plan Check Approved 3/7/2023 KELVIN CHUONG
Issued 3/7/2023 APPLICANT
CofO in Progress 10/2/2023 ALIZAH MAYAGOITIA
Permit Finaled 2/29/2024 DEROLD HAUFF
CofO Issued 2/29/2024 DEROLD HAUFF
Permit Finaled 2/29/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/24/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 9/27/2022 JEANETTE VONG
Sewer availability Cleared 9/27/2022 JEANETTE VONG
Clean Up Green Up Cleared 9/28/2022 DALIA MOKAYED
Grading Pre-Inspection Cleared 10/5/2022 ROBERT HUGHES
Low Impact Development Cleared 11/30/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 12/7/2022 AMAAN MALIK
GPI Written Notices Cleared 1/5/2023 PRANITA SHAH

Contact Information

Contractor Tech Master Construction Inc; Lic. No.: 1054601-B       ,

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/3/2023 Approved FREDDIE RIVERA
Sewer 4/21/2023 Approved FREDDIE RIVERA
Deputy Drilled-In Anchors 4/28/2023 Conditional Approval FREDDIE RIVERA
Footing/Foundation/Slab 4/28/2023 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 5/4/2023 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 5/22/2023 Partial Approval FREDDIE RIVERA
ELECTRICAL-Rough 6/12/2023 Approved FREDDIE RIVERA
PLUMBING-Rough 6/12/2023 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 6/20/2023 Partial Inspection FREDDIE RIVERA
HVAC-Rough 6/20/2023 Corrections Issued FREDDIE RIVERA
MERV13>=Rough 6/20/2023 Partial Inspection FREDDIE RIVERA
Deputy Wood Construction 6/21/2023 Conditional Approval FREDDIE RIVERA
BUILDING-Rough-Frame 6/26/2023 Corrections Issued FREDDIE RIVERA
MERV13>=Rough 6/26/2023 Partial Inspection FREDDIE RIVERA
Insulation 7/7/2023 Corrections Issued ALIZAH MAYAGOITIA
Interior/Exterior Lathing 7/7/2023 Partial Approval ALIZAH MAYAGOITIA
Drywall Nailing 7/14/2023 Corrections Issued FREDDIE RIVERA
Interior/Exterior Lathing 7/14/2023 Approved FREDDIE RIVERA
Shower Pan 7/14/2023 Corrections Issued FREDDIE RIVERA
Drywall Nailing 7/18/2023 Approved FREDDIE RIVERA
Shower Pan 7/18/2023 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 9/6/2023 Partial Inspection FREDDIE RIVERA
Final 9/6/2023 Corrections Issued FREDDIE RIVERA
MERV13>=Final 9/6/2023 Partial Inspection FREDDIE RIVERA
MERV13>=Rough 9/6/2023 Not Ready for Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 9/6/2023 SGSOV Not Ready FREDDIE RIVERA
Smoke Detectors 9/6/2023 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 9/15/2023 Approved FREDDIE RIVERA
Final 9/15/2023 Corrections Issued FREDDIE RIVERA
MERV13>=Final 9/15/2023 Approved FREDDIE RIVERA
MERV13>=Rough 9/15/2023 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 9/15/2023 SGSOV Not Ready FREDDIE RIVERA
Final 9/21/2023 Not Ready for Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 9/21/2023 SGSOV Approved FREDDIE RIVERA
Final 9/29/2023 OK to Issue CofO ALIZAH MAYAGOITIA