4058-4062 S CRENSHAW BLVD 90008

Certificate Information: 4058-4062 S CRENSHAW BLVD 90008

Application / Permit
22014-10000-04208
Plan Check / Job No.
B22LA16700
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
PROPOSED SECOND FLOOR ADDITION OF STORAGE ROOM. EXISTING BUILDING FOOTPRINT AND ENVELOPE TO REMAIN. NO CHANGE IN HEIGHT. LIMIT THE HOURS OF OPERATION FROM 7 AM. TO 11 PM.
Permit Issued
Issued on 1/11/2023
Issuing Office
Metro
Current Status
CofO Issued on 4/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/19/2022 APPLICANT
Assigned to Plan Check Engineer 8/25/2022 MICHAEL LOPEZ
Corrections Issued 9/1/2022 MICHAEL LOPEZ
Green Plans Picked Up 9/1/2022 APPLICANT
Disabled Access Plans Picked Up 9/2/2022 APPLICANT
Quality Review Completed 9/8/2022 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 9/26/2022 APPLICANT
Applicant returned to address corrections 12/2/2022 SERGIO GUTIERREZ
Applicant returned to address corrections 12/20/2022 SERGIO GUTIERREZ
Plan Check Approved 1/11/2023 SERGIO GUTIERREZ
Issued 1/11/2023 APPLICANT
CofO in Progress 4/18/2023 ERNESTO CORRAL
CofO Issued 4/18/2023 ERNESTO CORRAL
Permit Finaled 4/18/2023 ERNESTO CORRAL

Permit Application Clearance Information

Green Code Cleared 9/30/2022 MICHAEL LOPEZ
CPC Cleared 12/28/2022 KENTON TRINH
Comm Cor/Mini-Mall Cleared 12/28/2022 KENTON TRINH
DAS Clearance Cleared 12/28/2022 MICHAEL LOPEZ
Miscellaneous Cleared 12/28/2022 KENTON TRINH
Redevelopment Project Area Cleared 12/28/2022 DAVID URITA
Specific Plan Cleared 1/6/2023 KYLE WINSTON

Contact Information

Contractor Triplett Construction; Lic. No.: 1050247-B 8939 S SEPULVEDA #528      LOS ANGELES, CA 90045
Engineer Cooke,, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Green Building Rough 1/13/2023 Partial Approval MARTIN TAVITIAN
Wood Frame 1/13/2023 Partial Approval MARTIN TAVITIAN
Green Building Rough 1/31/2023 Conditional Approval DARRYL ARNOLD
Wood Frame 1/31/2023 Conditional Approval DARRYL ARNOLD
Drywall Nailing 2/7/2023 Not Ready for Inspection ALAN MORELOS
Drywall Nailing 2/16/2023 Not Ready for Inspection ALAN MORELOS
Drywall Nailing 3/17/2023 Approved ALAN MORELOS
Final 3/30/2023 Not Ready for Inspection ALAN MORELOS
Footing/Foundation/Slab 3/30/2023 Approved ALAN MORELOS
Green Building Final 3/30/2023 Approved ALAN MORELOS
Green Building Rough 3/30/2023 Approved ALAN MORELOS
SGSOV-Seismic Gas S/O Valve 3/30/2023 SGSOV Not Required ALAN MORELOS
Smoke Detectors 3/30/2023 Not Ready for Inspection ALAN MORELOS
Wood Frame 3/30/2023 Approved ALAN MORELOS
Final 4/11/2023 Not Ready for Inspection ALAN MORELOS
Final 4/14/2023 Conditional Approval ALAN MORELOS
Smoke Detectors 4/14/2023 Approved ALAN MORELOS
Final 4/18/2023 Conditional Approval ALAN MORELOS