3417 S STEWART AVE 90066

Certificate Information: 3417 S STEWART AVE 90066

Application / Permit
22014-10000-04197
Plan Check / Job No.
B22LA16635
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN* 36'-7.5" X 5'-0" ADDITION TO SINGLE FAMILY DWELLING - ALL WORK PER ENGINEER
Permit Issued
Issued on 10/18/2022
Issuing Office
Current Status
CofO Issued on 5/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/22/2022 APPLICANT
Assigned to Plan Check Engineer 8/29/2022 DANIEL ABRAMYAN
Corrections Issued 8/31/2022 DANIEL ABRAMYAN
Plan Check Approved 9/8/2022 DANIEL ABRAMYAN
Issued 10/18/2022 APPLICANT
CofO in Progress 5/22/2023 RICHARD STEINBACH
Permit Finaled 5/24/2023 DANIEL ORRANTE
CofO Issued 5/24/2023 DANIEL ORRANTE
Permit Finaled 5/24/2023 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/2/2022 KATHLEEN LEE
Eng Process Fee Ord 176,300 Cleared 9/6/2022 KATHLEEN LEE
Grading Pre-Inspection Cleared 9/7/2022 MICHAEL TEMPLE
Specific Plan Cleared 9/7/2022 EDUARDO HERMOSO

Contact Information

Contractor Williamson John Construction Inc; Lic. No.: 451421-B 8723 BLERIOT AVE      LOS ANGELES, CA 90045
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241
Engineer Espino,, Manuel A; Lic. No.: NA55526       ,

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/4/2022 Conditional Approval JESUS RODRIGUEZ
Service/Power Release 11/4/2022 Not Ready for Inspection JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 11/16/2022 Partial Approval JESUS RODRIGUEZ
Insulation 11/16/2022 Partial Approval JESUS RODRIGUEZ
Rough-Elec/Plmb/HVAC 11/16/2022 Partial Approval JESUS RODRIGUEZ
Service/Power Release 11/16/2022 Approved JESUS RODRIGUEZ
Deputy Wood Construction 12/14/2022 Conditional Approval JESUS RODRIGUEZ
ELECTRICAL-Rough 12/16/2022 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 12/16/2022 Approved JESUS RODRIGUEZ
Footing/Foundation/Slab 12/16/2022 Corrections Issued JESUS RODRIGUEZ
Green Building Rough 12/16/2022 Not Ready for Inspection JESUS RODRIGUEZ
BUILDING-Rough-Frame 12/23/2022 Approved JESUS RODRIGUEZ
Green Building Rough 12/23/2022 Approved JESUS RODRIGUEZ
HVAC-Rough 12/23/2022 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 12/23/2022 Approved JESUS RODRIGUEZ
PLUMBING-Rough 12/23/2022 Approved JESUS RODRIGUEZ
Drywall Nailing 12/29/2022 Approved CLAYTON GRAHAM
Service/Power Release 1/4/2023 Approved JESUS RODRIGUEZ
Shower Pan 1/4/2023 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 1/6/2023 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 5/1/2023 Approved JESUS RODRIGUEZ
Final 5/1/2023 Corrections Issued JESUS RODRIGUEZ
Footing/Foundation/Slab 5/1/2023 Approved JESUS RODRIGUEZ
Green Building Final 5/1/2023 Approved JESUS RODRIGUEZ
HVAC-Final 5/1/2023 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Final 5/1/2023 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 5/1/2023 SGSOV Approved JESUS RODRIGUEZ
Smoke Detectors 5/1/2023 Approved JESUS RODRIGUEZ
Final 5/22/2023 Partial Approval JESUS RODRIGUEZ
HVAC-Final 5/22/2023 Approved JESUS RODRIGUEZ