3548 N COPELAND PL 90032

Certificate Information: 3548 N COPELAND PL 90032

Application / Permit
22014-10000-04186
Plan Check / Job No.
B22LA16611
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ONE STORY ADDITION AT REAR TO (E) SFD 1 OF 2
Permit Issued
Issued on 3/7/2023
Issuing Office
Metro
Current Status
CofO Issued on 4/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/18/2022 APPLICANT
Assigned to Plan Check Engineer 9/8/2022 MARCELA FRANQUEZ
Corrections Issued 9/14/2022 MARCELA FRANQUEZ
Quality Review Completed 9/21/2022 TEODORO DIAZ RODRIGUEZ
Plan Check Approved 2/27/2023 MARCELA FRANQUEZ
Issued 3/7/2023 APPLICANT
CofO in Progress 3/29/2024 LILIANA PORTILLO
Permit Finaled 4/16/2024 DEROLD HAUFF
CofO Issued 4/16/2024 DEROLD HAUFF
Permit Finaled 4/16/2024 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/2/2022 JEANIE LAM
Sewer availability Cleared 11/2/2022 JEANIE LAM
Low Impact Development Cleared 1/11/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 1/13/2023 WALLIE JONG
GPI Written Notices Cleared 2/27/2023 MANUEL TEJADA
Grading Pre-Inspection Cleared 2/27/2023 MARCELA FRANQUEZ

Contact Information

Contractor Safe Quake Construction; Lic. No.: 571102-B 2088 S ATLANTIC BL #291      MONTEREY PARK, CA 91754
Engineer Dorta,, Michael Rohrs; Lic. No.: C72538 2445 VIA SONOMA      PALOS VERDES ESTATES, CA 90274

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/19/2023 Approved AMY COLIN
Excavation/Setback/Form/Re-Bar 4/19/2023 Approved AMY COLIN
Footing/Foundation/Slab 4/19/2023 Approved AMY COLIN
Excavation/Setback/Form/Re-Bar 4/20/2023 Approved AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 5/3/2023 Partial Approval AMY COLIN
PLUMBING-Rough 5/3/2023 Partial Approval AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 5/12/2023 Partial Approval AMY COLIN
Insulation 5/12/2023 Partial Approval AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 5/15/2023 Partial Approval AMY COLIN
Insulation 5/15/2023 Partial Approval AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 6/20/2023 Corrections Issued AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 7/11/2023 Partial Approval AMY COLIN
BUILDING-Rough-Frame 8/9/2023 Not Ready for Inspection AMY COLIN
ELECTRICAL-Rough 8/9/2023 Approved AMY COLIN
Green Building Rough 8/9/2023 Approved AMY COLIN
HVAC-Rough 8/9/2023 Approved AMY COLIN
PLUMBING-Rough 8/9/2023 Approved AMY COLIN
Verify Sprinkler Sign Off 8/9/2023 Corrections Issued AMY COLIN
BUILDING-Rough-Frame 8/22/2023 Approved AMY COLIN
Insulation 8/22/2023 Approved AMY COLIN
Drywall Nailing 9/6/2023 Approved AMY COLIN
Interior/Exterior Lathing 9/28/2023 Approved AMY COLIN
ELECTRICAL-Final 1/31/2024 Partial Approval CRAIG VAUGHAN
HVAC-Final 1/31/2024 Corrections Issued CRAIG VAUGHAN
PLUMBING-Final 1/31/2024 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Final 2/8/2024 Approved ALIZAH MAYAGOITIA
HVAC-Final 2/8/2024 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 2/8/2024 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 3/5/2024 SGSOV Not Ready LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 3/19/2024 SGSOV Not Ready LILIANA PORTILLO
ELECTRICAL-Final 3/21/2024 Approved LILIANA PORTILLO
Final 3/21/2024 Corrections Issued LILIANA PORTILLO
HVAC-Final 3/21/2024 Approved LILIANA PORTILLO
PLUMBING-Final 3/21/2024 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 3/21/2024 SGSOV Approved LILIANA PORTILLO
Service/Power Release 3/21/2024 Not Required LILIANA PORTILLO
Smoke Detectors 3/21/2024 Approved LILIANA PORTILLO
ELECTRICAL-Final 3/28/2024 Approved LILIANA PORTILLO
Final 3/28/2024 OK to Issue CofO LILIANA PORTILLO
Green Building Final 3/28/2024 Approved LILIANA PORTILLO
HVAC-Final 3/28/2024 Approved LILIANA PORTILLO
PLUMBING-Final 3/28/2024 Approved LILIANA PORTILLO
Service/Power Release 3/28/2024 Not Required LILIANA PORTILLO