9111 N TELFAIR AVE 91352
Certificate Information: 9111 N TELFAIR AVE 91352
- Application / Permit
- 22014-10000-04178
- Plan Check / Job No.
- B22LA16549
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1 OF 2 694 SF GROUND FLOOR ONE STORY ADDITION, CONVERT EXISITING 387 SF CARPORT TO NEW MASTER BEDROOM
- Permit Issued
- Issued on 10/3/2024
- Issuing Office
- Valley
- Current Status
- Issued on 10/3/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/8/2022 | MARCELA FRANQUEZ |
| Corrections Issued | 9/15/2022 | MARCELA FRANQUEZ |
| Quality Review Completed | 9/21/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 9/28/2022 | APPLICANT |
| Applicant returned to address corrections | 10/18/2022 | MARCELA FRANQUEZ |
| Plan Check Approved | 12/1/2022 | MARCELA FRANQUEZ |
| Issued | 10/3/2024 | APPLICANT |
Permit Application Clearance Information
| Clean Up Green Up | Cleared | 10/28/2022 | YINGSHI HUANG |
| Eng Process Fee Ord 176,300 | Cleared | 10/28/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 10/28/2022 | MEGAN GODINEZ |
| ZI | Cleared | 10/28/2022 | YINGSHI HUANG |
| Low Impact Development | Cleared | 11/23/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 11/30/2022 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kator,, Khaled; Lic. No.: C69781 | 19519 TULSA ST NORTHRIDGE, CA 91326 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/7/2024 | No Access for Inspection | MATTHEW NELSON |
| Footing/Foundation/Slab | 10/9/2024 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 10/9/2024 | Partial Approval | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2024 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 12/11/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Green Building Rough | 12/11/2024 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 1/17/2025 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 1/17/2025 | Approved | MATTHEW NELSON |
| Deputy Wood Construction | 2/25/2025 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2025 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 9/11/2025 | Partial Approval | MATTHEW NELSON |
| Green Building Rough | 9/11/2025 | Approved | MATTHEW NELSON |
| HVAC-Rough | 9/11/2025 | Corrections Issued | MATTHEW NELSON |
| BUILDING-Rough-Frame | 9/24/2025 | Not Ready for Inspection | MATTHEW NELSON |
| HVAC-Rough | 9/24/2025 | Corrections Issued | MATTHEW NELSON |
| HVAC-Rough | 9/25/2025 | Approved | MATTHEW NELSON |
| Insulation | 10/1/2025 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 10/27/2025 | Approved | MATTHEW NELSON |
| Drywall Nailing | 10/27/2025 | Approved | MATTHEW NELSON |
| Shower Pan | 11/13/2025 | Approved | MATTHEW NELSON |
| Pre-Inspection | 2/12/2026 | Partial Inspection | MATTHEW NELSON |